11-3. TENANT PROTECTIONS
HUD Section 8 Renewal Policy Guidebook · 2026 edition · updated 2026-07-29 · United States
A. Importance of the Process. The process of converting from project-based assistance to tenant-based assistance can produce worry and fear for many families. Therefore, care must be taken to make sure the process is completed correctly and information is made clear and available for all families, owners, and PHAs.
B. Right to Remain. Tenants who receive an enhanced voucher have the right to remain in their units if the units are offered as rental housing. The tenant must have been issued an enhanced voucher sufficient to pay the rent charged for the unit, if the rent is reasonable. Owners may not terminate the tenancy of a tenant who exercises this right to remain except for cause under Federal, State or local law. To receive the full rent charged for the unit, the owner must agree to enter into a contract with the local PHA on behalf of each covered family. If an owner refuses to honor the tenants right to remain, the tenant’s remedy will be determined by the provision of Federal law that provides for the right to remain (i.e., 42 USC § 1437f(t)(1)) and on State and local law.
The FY 2001 Military Construction and FY 2000 Emergency Supplemental Appropriations law, Pub. L. No. 106-246, Section 2801 (July 13, 2000) amended the enhanced voucher statute passed in the FY 2000 Appropriations Act (USHA Section 8(t), 42 USC Sec. 1437f(t)) and reads: “...the assisted family may elect to remain in the same project in which the family was residing on the date of the eligibility event for the project ...” .
This protection continues if the project is offered as rental housing, absent good cause to terminate tenancy under Federal, State or local law and provided the PHA continues to find the rent reasonable, Owners must continually renew the lease of an enhanced voucher family.
C. Tenant-Based Eligibility. Only eligible families will receive enhanced vouchers at the time of an opt-out. While a family may be income eligible, they are not automatically eligible for admission to the tenant-based program.
- The tenant-based assistance program is administered through the Office of Public and Indian Housing (PIH). Some of the eligibility and admissions standards for PIH programs differ from those of project-based Section 8 programs. In some
Chapter Eleven – Published March 2023
3
cases, a tenant may be denied assistance under the tenant-based assistance program.
- a. The PHA will re-certify and screen potentially eligible families and may deny them access to the tenant-based assistance program based on the grounds outlined in the Regulations (24 CFR Part 982.552 and 24 CFR Part 982.553). HUD encourages PHAs to use maximum flexibility during this process, such as setting up repayment agreements for tenants who owe funds to the PHA. However, if a family is ultimately denied assistance, the PHA must give them prompt notice of this decision which includes a brief statement of the reasons for the decision. An informal review can be requested by the family (the process is described in the Regulations, 24 CFR Part 982.554).
xibility during this process, such as setting up repayment agreements for tenants who owe funds to the PHA. However, if a family is ultimately denied assistance, the PHA must give them prompt notice of this decision which includes a brief statement of the reasons for the decision. An informal review can be requested by the family (the process is described in the Regulations, 24 CFR Part 982.554).
- b. If the owner’s current income certification for a tenant is no more than six months old and the PHA determines it is acceptable (through reviewing a small sampling), the PHA may use the owner’s most recent tenant income certification in determining eligibility for enhanced vouchers.
In general, to be eligible to receive an enhanced voucher in the case of a regular opt-out (not proceeded by a prepayment) the family must be low-income (including very low-income) and residing in a unit covered by the expiring Section 8 contract. This includes families who may have moved into a vacated unit during the term of the one-year notification period.
a. Unlike in a preservation prepayment situation, a family with an income above 80 percent of area median income (AMI) is not eligible for tenantbased assistance because of the opt-out.
b. In cases of preservation prepayments, the user must follow the guidance in Notice 2004-17.
In instances when a new tenant, i.e., a tenant who was not residing in the project when the one-year notification was properly provided, moves into a unit during the one-year tenant notification period, owners are encouraged to add the following provisions, in the form of a lease addendum, to the required model lease: (1) “If the HAP contract terminates for any reason, the lease terminates automatically”; and (2) “tenants who move into a vacated unit during the one-year notification period are not entitled to one-year notice of contract expiration or termination”.
Tenants admitted to a PHA’s tenant-based voucher program because of a housing conversion action are not subject to the income targeting requirements of the tenant-based Section 8 program.
- D. Processing Delays. If there is any delay in processing the tenant-based assistance, HUD must ask the owner to consider a short-term renewal of the contract to provide HUD with enough time to get the vouchers in place.
Chapter Eleven – Published March 2023
4
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸ Contents — HUD Section 8 Renewal Policy Guidebook
- U.S. DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT
- SPECIAL ATTENTION OF
- TRANSMITTAL
- A. Purpose
- Explanation of Changes
- Section 8 Renewal Policy Guidebook
- Office of Multifamily Housing
- Table of Contents
- Chapter One
- Introduction
- Chapter 1: Introduction
- Chapter 2: Section 8 Renewals
- Chapter 3: Option One: Mark-Up-To-Market
- Chapter 4: Option Two: Contract Renewals For Other Projects wi…
- Chapter 5: Option Three: Referral to Recap
- Chapter 6: Option Four: Renewal of Projects Exempt from or not…
- Chapter 7: Option Five: Renewal of Portfolio Reengineering Dem…
- Chapter 8: Option Six: Opt-Outs
- Chapter 9: Rent Comparability Studies
- Chapter 10: Residual Receipts
- Chapter 11: Tenant Issues
- Chapter 12: Physical Condition of the Project
- Chapter 13: HUD’s Refusal to Renew Section 8 Contracts
- Chapter 14: Rural Housing Service (RHS) Section 515/8
- Chapter 15: Section 8 Preservation Efforts
- — Chapter 16: “Old Regulation” State Housing Finance Agency Pr…
- 1-2. LEGISLATIVE HISTORY
- 1-3. RULEMAKING
- 1-4. ADMINISTRATIVE POLICY
- 1-5. APPLICABILITY
- 1-6. PAPERWORK REDUCTION ACT
- Chapter Two
- Section 8 Renewals
- 2-1. INTRODUCTION
- 2-2. OWNER OPTIONS
- 2-3. TYPES OF RENEWALS
- 2-4. EARLY TERMINATION OF A CONTRACT
- 2-5. RENT COMPARABILITY STUDY (RCS)
- Note: The AE/CA shall not lower the comparable market rents in…
- Note: A RCS is not required at any subsequent renewal of an EL…
- 2-6. CONTRACTS
- 2-8. SHORT-TERM CONTRACT RENEWALS
- 2-10. COMBINING CONTRACTS
- 2-11. REQUEST FOR A CONTRACT EXTENSION
- 2-12. DISTRIBUTIONS
- Note: The conditions listed above for receiving access to incr…
- 2-13. RENT ADJUSTMENTS
- 2-14. OPERATING COST ADJUSTMENT FACTOR (OCAF)
- 2-15. BUDGET-BASED RENT ADJUSTMENT REQUESTS
- 2-16. INCREASES IN DEPOSITS TO THE RESERVE FOR REPLACEMENT
- 2-17. PROCESSING INSTRUCTIONS
- Note: If the project has a budget approved by the AE/CA less t…
- Note: HUD does not accept the RHS utility analysis. The owner …
- 2-18. WAIVERS
- 2-19. DUNS NUMBER
- Chapter Three
- 3-1. OVERVIEW
- 3-3. OPTION ONE-A ENTITLEMENT MARK-UP-TO-MARKET ELIGIBILITY
- Note: Nonprofit controlled for profit entities as described in…
- 3-4. 150 PERCENT RENT CAP FOR OPTION ONE-A
- 3-5. EXCEEDING THE 150 PERCENT OF FMR CAP
- 3-6. OPTION ONE-B DISCRETIONARY MUTM ELIGIBILITY
- Note: Non-profit owned projects that meet one of the three cri…
- 3-7. RENEWAL REQUESTS
- 3-8. PROCESSING INSTRUCTIONS
- 3-9. ANNUAL RENT ADJUSTMENTS DURING A MULTIYEAR CONTRACT
- Chapter Four
- 4-1. ELIGIBILITY
- Note: Projects currently renewed under either Option Two or Op…
- 4-2. CONTRACT RENEWAL
- 4-3. ANNUAL RENT ADJUSTMENTS DURING A MULTIYEAR CONTRACT
- 4-4. PROCESSING INSTRUCTIONS
- Chapter Five
- Note: WAIVERS TO CHAPTER FIVE WILL BE IN ACCORDANCE WITH RECAP…
- Note: Risk Sharing Projects do not meet the definition of “eli…
- 5-2. BINDING COMMITMENT
- 5-3. ENTRY INTO RECAP
- Note: In cases where a CA makes the determination that contrac…
- 5-4. CONTRACT RENEWALS — RENT OR DEBT RESTRUCTURING
- 5-5. SUBSEQUENT RENEWALS
- 5-6. “WATCH LIST” MTM PROJECTS
- 5-7. GENERAL INFORMATION
- Chapter Six
- 6-1. ELIGIBILITY
- Note: State and local government financed projects that are no…
- Note: In cases where referral to Recap is necessary, CAs must …
- Note: Section 202 and 811 Capital Advance projects are not eli…
- Note: Projects financed under the risk-sharing loan programs u…
- 6-2. RENEWALS
- Reminder: For projects (including 202 projects) that are being…
- 6-3. RENT ADJUSTMENTS FOR MULTI-YEAR CONTRACTS
- 6-4. SECTION 202 REFINANCINGS
- Chapter Seven
- 7-1. ELIGIBILITY
- Portfolio Reengineering Demonstration Program Projects
- 7-2. RENEWAL OF PORTFOLIO REENGINEERING DEMONSTRATION PROJECTS
- FIVE
- Note: Owners can request that the existing Demo Program Use Ag…
- 7-4. PROCESSING INSTRUCTIONS FOR DEMONSTRATION PROJECTS
- 7-5. PRESERVATION PROJECTS (LIHPRHA AND ELIHPA)
- 7-6. OWNER’S SUBMISSION FOR PRESERVATION PROJECTS
- Note: Owners can request that the existing Preservation Use Ag…
- 7-7. PROCESSING INSTRUCTIONS FOR PRESERVATION PROJECTS
- 7-8. PROJECT SPECIFIC RENTS (PSRS)
- Chapter Eight
- 8-1. OVERVIEW
- 8-2. OWNER REQUIREMENTS FOR TENANT NOTIFICATION
- 8-3. PROCESSING INSTRUCTIONS
- Note: If proper notification was not provided, the owner must …
- Chapter Nine
- 9-1. BACKGROUND
- 9-2. APPLICABILITY OF CHAPTER NINE
- 9-3. ROAD MAP TO CHAPTER NINE
- 9-4. ALTERNATIVES TO RENT COMPARABILITY STUDY
- 9-6. METHOD TWO: COMPARING PROPOSED SECTION 8 RENTS WITH RENTS…
- 9-7. PREPARING A RENT COMPARABILITY STUDY
- 9-8. APPRAISER QUALIFICATIONS
- 9-9. ANALYZING THE SUBJECT PROJECT
- Note: Appraisers should not take into consideration demographi…
- Note: Government boundaries like state or county lines often d…
- 9-10. SELECTING COMPARABLE UNITS
- 9-11. COLLECTING AND DOCUMENTING DATA ON COMPARABLE UNITS
- 9-12. COMPUTING ADJUSTED RENTS FOR COMPARABLE UNITS
- 9-13. DERIVING ESTIMATED MARKET RENTS
- 9-14. PROCEDURE FOR MANDATORY MARKET RENT THRESHOLD
- Example Project in ZIP code 76469
- 9-15. HUD REVIEW OF RENT COMPARABILITY STUDY
- 9-16. INITIAL AND SUBSTANTIVE REVIEW OF OWNER’S RCS
- 9-17. COMMUNICATING RESULTS OF HUD/CA REVIEWS
- 9-18. OWNER APPEALS
- 9-19. IMPOSING SANCTIONS ON APPRAISERS
- APPENDICES
- - Instructions for Completing the HUD Form 92273 S8
- Part A: Rents Charged (lines 1 through 5)
- Part B. Design, Location, Condition (lines 6 through 10)
- Part C. Unit Equipment/Amenities (lines 11 through 23)
- Part D. Site Equipment/Amenities (lines 24 through 32)
- Part E. Utilities (lines 33 through 39)
- Part F. Adjustments Recap (lines 40 through 43)
- Part G. Adjusted Rents (lines 44 through 45)
- Required Contents of a Rent Comparability Study
-
▸ Comparable Project Profile
Overview- Address
- Place Photo Below:
- By my/our signature below, I/We certify that, to the best of m…
- Sample RCS Appraiser’s Transmittal Letter
- Re: Rent Comparability Study/[Project Name]
- Mandatory Market Rent Threshold Test
- Sample Owner’s Cover Letter
- RCS Submittal Cover Letter for [Project Name]
- Owner’s Materials
- RCS Materials
- Mandatory Market Rent Threshold Materials
- Owner’s Signature & Date
- Notes for Rent Grid Analysis and Triggers for Secondary Review
- Sample Issues Memo from Substantive Reviewer
- Special Project Types
- Forms Used in Preparation and Review of an RCS
- Chapter Ten
- Residual Recei pts
- Chapter Eleven
- 11-1. DEFINITIONS
- 11-2. HOUSING CONVERSION ACTIONS
- 11-3. TENANT PROTECTIONS
- 11-4. OWNER NOTIFICATION REQUIREMENTS
- Note: The one-year notification is not required when an owner …
- Note: Taping the Notice to the outside of each unit is not acc…
- 11-5. LIMITED ENGLISH PROFICIENCY ASSISTANCE
- 11-6. EFFECTIVE COMMUNICATIONS
- ( Date )
- THIS LETTER IS TO NOTIFY YOU THAT WE DO NOT INTEND TO RENEW TH…
- HUD Web
- ( Date )
- THIS LETTER IS TO NOTIFY YOU THAT WE INTEND TO RENEW THE CURRE…
- HUD Web
- ( Date )
- HUD Web
- Chapter Twelve
- 12-1. PHYSICAL CONDITION
- 12-2. EXIGENT HEALTH AND SAFETY (EH&S) DEFICIENCY NOTICE AND P…
- Note: hud@work is an internal site with no access for the publ…
- Chapter Thirteen
- 13-1. HUD’S REFUSAL TO RENEW A SECTION 8 HAP CONTRACT
- 13-2. HUD’S DECISION NOT TO RENEW THE EXPIRING CONTRACT
- 13-3. OWNER’S APPEAL OF HUD’S REFUSAL TO RENEW A SECTION 8 HAP…
- 13-4. HUD’S TENANT NOTIFICATION OF REFUSAL TO RENEW
- Chapter Fourteen
- 14-1. OVERVIEW
- 14-2. PROCESSING
- Note: HUD does not accept the RHS utility analysis. The owner …
- Note: If the owner of the project is a for profit who is not r…
- Note: RHS projects are exempted from debt restructuring under …
- Chapter Fifteen
- Section 8 Preservation Efforts
- 15-1. OVERVIEW
- PART ONE: DEFINITION OF NONPROFIT OWNER
- 15-2. NONPROFIT OWNER/PURCHASER
- 15-3. NONPROFIT CONTROLLED FOR PROFIT ENTITY (OWNER OR PURCHAS…
- PART TWO: GENERAL CRITERIA FOR BOTH CAPITAL REPAIRS AND TRANSF…
- 15-4. APPLICABILITY
- 15-5. BASIC REQUIREMENTS
- Note: HUD lacks the authority to allow a project to reduce ren…
- 15-6. RENT INCREASES
- 15-7. UNASSISTED UNITS IN A HUD PROJECT
- 15-8. CAP ON MARKET RENTS
- 15-9. PROJECT CAPITAL NEEDS ASSESSMENT AND INCREASED DEPOSITS …
- Note: For a non-insured project with an old regulation/LMSA/PD…
- PART THREE: CAPITAL REPAIRS PROGRAM
- 15-11. GENERAL
- 15-12. ADDITIONAL ACCEPTABILITY REQUIREMENTS FOR THE OWNER
- 15-13. PROJECT ELIGIBILITY
- Part Four: Transfer Program
- 15-14. GENERAL
- 15-15. ADDITIONAL PURCHASER REQUIREMENTS
- 15-16. PROJECT ELIGIBILITY
- 15-17. TRANSFER OF PHYSICAL ASSETS (TPA) FOR A HUD INSURED TRA…
- Chapter Sixteen
- 16-1. BACKGROUND, APPLICABILITY AND OVERVIEW
- 16-2. OWNER OPTIONS
- 16-3. TIMELINESS
- Rent Comparability Study (RCS) . See Comparability Study.