Chapter 13 — FUEL GAS PIPING

1313.6 Purging Requirements. The purging of piping

California Mechanical Code (Title 24, Part 4) · 2019 edition · updated 2026-09-10 · California

Italicized text is a California amendment to the model code, as printed in the official publication.

shall be in accordance with Section 1313.6.1 through Section 1313.6.3. [NFPA 54:8.3] Purged Outdoors.1313.6.1 Piping Systems Required to be The purging of piping systems shall be in accordance with Section 1313.6.1.1 through Section 1313.6.1.4 where the piping system meets either of the following:

1313.6.1.3 Outdoor Discharge of PurgedGases. The open end of a piping system being pressure vented or purged shall discharge directly to an outdoor location. Purging operations shall comply with all of the following requirements:

The point of discharge shall be located at least

10 feet (3048 mm) from sources of ignition, at least 10 feet (3048 mm) from building openings, and at least 25 feet (7620 mm) from mechanical air intake openings.

During discharge, the open point of discharge

shall be continuously attended and monitored with a combustible gas indicator that complies with Section 1313.6.1.4.

(1) The point of discharge shall be controlled with

a shutoff valve.

(2) The point of discharge shall be located at least

10 feet (3048 mm) from sources of ignition, at

a shutoff valve.

(3) During discharge, the open point of discharge

shall be continuously attended and monitored

2019 CALIFORNIA MECHANICAL CODE 267

FUEL GAS PIPING any other purpose or distributed to any other persons or parti es.

FUEL GAS PIPING any other purpose

(4) Purging operations introducing fuel gas shall be

stopped when 90 percent fuel gas by volume is

After the piping system has been placed in operation, 1313.6.3 Purging Appliances and Equipment. appliances and equipment shall be purged before being placed into operation. [NFPA 54:8.3.3]

(4) Purging operations introducing fuel gas shall be

stopped when 90 percent fuel gas by volume is detected within the pipe. (5) Persons not involved in the purging operations

shall be evacuated from all areas within 10 feet

« ««
» » » »

(5) Persons not involved in the purging operations

shall be evacuated from all areas within 10 feet (3048 mm) of the point of discharge. [NFPA 54:8.3.1.3] 1313.6.1.4 Combustible Gas Indicator. Combustible gas indicators shall be listed and calibrated in accordance with the manufacturer’s instructions. Combustible gas indicators shall numerically display a volume scale from 0 percent to 100 percent in 1 percent or smaller increments. [NFPA 54:8.3.1.4] 1313.6.2 Piping Systems Allowed to be PurgedIndoors or Outdoors. The purging of piping systems shall be in accordance with the provisions of Section 1313.6.2.1 where the piping system meets both of the following: (1) The design operating pressure is 2 psig (14 kPag) or

less.

(5) The piping shall be purged by the gas supplier

in accordance with written procedures. [NFPA 54:8.3.2.1] 1313.6.2.2 Combustible Gas Detector. Combustible gas detectors shall be listed and calibrated or tested in accordance with the manufacturer’s instructions. Combustible gas detectors shall be capable of indicating the presence of fuel gas.

[NFPA 54:8.3.2.2]

(1) The pipe size of each section of the longest pipe run

from the point of delivery to the most remote outlet shall be determined using the longest run of piping and the load of the section. (2) The pipe size of each section of branch piping not

previously sized shall be determined using the length

Get a plain-English answer with a citation back to this text.

Ask AI about this code
Contents — California Mechanical Code (Title 24, Part 4)
California Mechanical Code (Title 24, Part 4)
  1. Chapter 1 — GENERAL CODE PROVISIONS
  2. Chapter 2 — DEFINITIONS
  3. Chapter 3 — GENERAL REGULATIONS
  4. Chapter 4 — VENTILATION AIR
  5. Chapter 5 — EXHAUST SYSTEMS
  6. Chapter 6 — DUCT SYSTEMS
  7. Chapter 7 — COMBUSTION AIR
  8. Chapter 8 — CHIMNEYS AND VENTS
  9. Chapter 9 — INSTALLATION OF SPECIFIC APPLIANCES
  10. Chapter 10 — BOILERS AND PRESSURE VESSELS
  11. Chapter 11 — REFRIGERATION
  12. Chapter 12 — HYDRONICS
  13. Chapter 13 — FUEL GAS PIPING
    Overview
    1. 1301.1 Applicability. 1301.0 Scope of Gas Piping. The regulati…
    2. 1302.1 General. 1302.0 Coverage of Piping System. Coverage of …
    3. 1302.2 Piping System Requirements. Requirements for
    4. 1302.3 Applications. This code shall not apply to the followin…
    5. 1303.2 Excavation. Excavations required for the installation o…
    6. 1303.3 Type of Inspections. The Authority Having Jurisdiction …
    7. 1303.4 Inspection Waived. In cases where the work
    8. 1304.1 Issuance. 1304.0 Certificate of Inspection. Where upon …
    9. 1304.2 Gas Supplier. A copy of the certificate of such final
    10. 1304.3 Unlawful. It shall be unlawful for a serving gas suppli…
    11. 1305.1 Authorized Personnel.1305.0 Authority to Render Gas Ser…
    12. 1305.2 Outlets. It shall be unlawful to turn on or connect gas
    13. 1306.2 Notice. Where such disconnection has been made, a
    14. 1306.3 Capped Outlets. It shall be unlawful to remove or
    15. 1308.1 Installation of Piping System.Components. Where required
    16. 1308.2 Provision for Location of Point of Delivery.
    17. 1308.3 Interconnections Between Gas Piping Sys-
    18. 1308.4 Sizing of Gas Piping Systems. Gas piping systems shall …
    19. 1308.6 Gas Meters. Gas meters shall be selected for the
    20. 1308.7 Gas Pressure Regulators. A line pressure regulator or g…
    21. 1308.9 Pressure Limitation Requirements. Where piping systems …
    22. 1308.10 Backpressure Protection. Protective devices
    23. 1308.10 Backpressure Protection. Protective devices
    24. 1308.8 Overpressure Protection. Where the serving gas
    25. 1308.11 Low-Pressure Protection. A protective device
    26. 1308.12 Shutoff Valves. Shutoff valves shall be approved
    27. 1308.13 Expansion and Flexibility. Piping systems shall
    28. 1309.1 General.1309.0 Excess Flow Valve. Where automatic exces…
    29. 1310.1 Piping Underground. 1310.0 Gas Piping Installation. Und…
    30. 1310.2 Installation of Piping. Piping installed aboveground sh…
    31. 1310.3 Concealed Piping in Buildings. Gas piping in
    32. 1310.4 Piping in Vertical Chases. Where gas piping
    33. 1310.6 Appliance Overpressure Protection. The maximum operatin…
    34. 1310.7 Gas Pipe Turns. Changes in direction of gas pipe
    35. 1310.5 Maximum Design Operating Pressure. The
    36. 1310.8 Drips and Sediment Traps. For other than dry gas
    37. 1310.9 Outlets. Outlets shall be located and installed in
    38. 1310.10 Branch Pipe Connection. When a branch outlet
    39. 1310.11 Manual Gas Shutoff Valves. An accessible gas
    40. 1310.12 Prohibited Devices. No device shall be placed
    41. 1312.1 Connecting Appliances and Equipment.
    42. 1311.4 Lightning Protection System. Where a lightning
    43. 1311.5 Electrical Circuits. Electrical circuits shall not util…
    44. 1311.6 Electrical Connections. All electrical connections
    45. 1311.1 Pipe and Tubing Other than CSST. 1311.0 Electrical Bond…
    46. 1311.2 Bonding of CSST Gas Piping. CSST gas piping
    47. 1311.3 Grounding Conductor of Electrode. Gas piping
    48. 1312.2 Suspended Low-Intensity Infrared Tube
    49. 1312.3 Use of Gas Hose Connectors. Listed gas hose
    50. 1312.7 Quick-Disconnect Devices. Quick-disconnect
    51. 1312.8 Gas Convenience Outlets. Appliances shall be
    52. 1312.4 Injection (Bunsen) Burners. Injection (Bunsen)
    53. 1312.9 Sediment Trap. Where a sediment trap is not incorporate…
    54. 1313.2 Test Preparation. Test preparation shall comply
    55. 1313.3 Test Pressure. This inspection shall include an air,
    56. 1312.10 Installation of Piping. Piping shall be installed in
    57. 1313.1 Piping Installations. 1313.0 Pressure Testing and Inspe…
    58. 1313.4 Detection of Leaks and Defects. The piping system shall…
    59. 1313.5 Piping System Leak Test. Leak checks using fuel
    60. 1313.6 Purging Requirements. The purging of piping
    61. 1314.0 Required Gas Supply. 1314.1 General. The following regu…
    62. 1314.2 Volume. The hourly volume of gas required at each
    63. 1314.3 Gas Appliances. Where the gas appliances to be
    64. 1314.4 Size of Piping Outlets. The size of the supply piping o…
    65. 1315.0 Required Gas Piping Size.1315.1 Pipe Sizing Methods. Wh…
    66. 1315.2 Tables for Sizing Gas Piping Systems. Table
    67. 1315.3 Sizing Equations. The inside diameter of smooth
    68. 1315.4 Sizing of Piping Sections. To determine the size
    69. 1315.5 Engineering Methods. For conditions other than
    70. 1315.6 Variable Gas Pressures. Where the supply gas
  14. Chapter 14 — PROCESS PIPING
  15. Chapter 15 — SOLAR ENERGY SYSTEMS
  16. Chapter 16 — STATIONARY POWER PLANTS
  17. Chapter 17 — REFERENCED STANDARDS
  18. Appendix A — RESIDENTIAL PLAN EXAMINER REVIEW FORM FOR HVAC SY…
  19. Appendix B — PROCEDURES TO BE FOLLOWED TO PLACE GAS EQUIPMENT …
  20. Appendix C — INSTALLATION AND TESTING OF OIL (LIQUID) FUEL-FIR…
  21. Appendix D — FUEL SUPPLY: MANUFACTURED/MOBILE HOME PARKS AND R…
  22. Appendix E — SUSTAINABLE PRACTICES
  23. Appendix F — SIZING OF VENTING SYSTEMS AND OUTDOOR COMBUSTION …
  24. Appendix G — EXAMPLE CALCULATION OF OUTDOOR AIR RATE

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.