1310.11 Manual Gas Shutoff Valves. An accessible gas

California Mechanical Code (Title 24, Part 4) · 2019 edition · updated 2026-09-10 · California

Italicized text is a California amendment to the model code, as printed in the official publication.

shutoff valve shall be provided upstream of each gas pressure regulator. Where two gas pressure regulators are installed in series in a single gas line, a manual valve shall not be required at the second regulator. [NFPA 54:7.9.1]

« « « « « « « «

place.

Main gas shutoff valves controlling several gas piping 1310.11.1 Valves Controlling Multiple Systems. systems shall be readily accessible for operation and installed so as to be protected from physical damage. They shall be marked with a metal tag or other permanent means attached by the installing agency so that the gas piping systems supplied through them can be readily identified. [NFPA 54:7.9.2.1]

(2) Outlets shall not be located behind doors.

(3) Outlets shall be located far enough from floors, walls,

patios, slabs, and ceilings to permit the use of wrenches

Outlets shall be located far enough from floors, walls,

patios, slabs, and ceilings to permit the use of wrenches without straining, bending, or damaging the piping.

The unthreaded portion of gas piping outlets shall extend

not less than 1 inch (25.4 mm) through finished ceilings or indoor or outdoor walls.

The unthreaded portion of gas piping outlets shall extend

not less than 2 inches (51 mm) above the surface of floors or outdoor patios or slabs.

The provisions of Section 1310.9(4) and Section

1310.9(5) shall not apply to listed quick-disconnect devices of the flush-mounted type or listed gas convenience outlets. Such devices shall be installed in accordance with the manufacturer’s installation instructions.

[NFPA 54:7.7.1.1 – 7.7.1.6]

(4) The unthreaded portion of gas piping outlets shall extend

not less than 1 inch (25.4 mm) through finished ceilings

(5) The unthreaded portion of gas piping outlets shall extend

not less than 2 inches (51 mm) above the surface of floors

(6) The provisions of Section 1310.9(4) and Section

1310.9(5) shall not apply to listed quick-disconnect

Lines. 1310.11.1.1 Shutoff Valves for Multiple House In multiple-tenant buildings supplied through a master meter, through one service regulator where a meter is not provided, or where meters or service regulators are not readily accessible from the appliance or equipment location, an individual shutoff valve for each apartment or tenant line shall be provided at a convenient point of general accessibility. In a common system serving a number of individual buildings, shutoff valves shall be installed at each building. [NFPA 54:7.9.2.2] 1310.11.2 Emergency Shutoff Valves. An exterior shutoff valve to permit turning off the gas supply to each building in an emergency shall be provided. The emergency shutoff valves shall be plainly marked as such and their locations posted as required by the Authority Having Jurisdiction. [NFPA 54:7.9.2.3] 1310.11.3 Shutoff Valve for Laboratories. Each laboratory space containing two or more gas outlets installed on tables, benches, or in hoods in educational, research, commercial and industrial occupancies shall have a single shutoff valve through which all such gas outlets are supplied. The shutoff valve shall be accessible, located within the laboratory or adjacent to the laboratory’s egress door, and identified. [NFPA 54:7.9.2.4]

Get a plain-English answer with a citation back to this text.

Ask AI about this code
Contents — California Mechanical Code (Title 24, Part 4)
California Mechanical Code (Title 24, Part 4)
  1. Chapter 1 — GENERAL CODE PROVISIONS
  2. Chapter 2 — DEFINITIONS
  3. Chapter 3 — GENERAL REGULATIONS
  4. Chapter 4 — VENTILATION AIR
  5. Chapter 5 — EXHAUST SYSTEMS
  6. Chapter 6 — DUCT SYSTEMS
  7. Chapter 7 — COMBUSTION AIR
  8. Chapter 8 — CHIMNEYS AND VENTS
  9. Chapter 9 — INSTALLATION OF SPECIFIC APPLIANCES
  10. Chapter 10 — BOILERS AND PRESSURE VESSELS
  11. Chapter 11 — REFRIGERATION
  12. Chapter 12 — HYDRONICS
  13. Chapter 13 — FUEL GAS PIPING
    Overview
    1. 1301.1 Applicability. 1301.0 Scope of Gas Piping. The regulati…
    2. 1302.1 General. 1302.0 Coverage of Piping System. Coverage of …
    3. 1302.2 Piping System Requirements. Requirements for
    4. 1302.3 Applications. This code shall not apply to the followin…
    5. 1303.2 Excavation. Excavations required for the installation o…
    6. 1303.3 Type of Inspections. The Authority Having Jurisdiction …
    7. 1303.4 Inspection Waived. In cases where the work
    8. 1304.1 Issuance. 1304.0 Certificate of Inspection. Where upon …
    9. 1304.2 Gas Supplier. A copy of the certificate of such final
    10. 1304.3 Unlawful. It shall be unlawful for a serving gas suppli…
    11. 1305.1 Authorized Personnel.1305.0 Authority to Render Gas Ser…
    12. 1305.2 Outlets. It shall be unlawful to turn on or connect gas
    13. 1306.2 Notice. Where such disconnection has been made, a
    14. 1306.3 Capped Outlets. It shall be unlawful to remove or
    15. 1308.1 Installation of Piping System.Components. Where required
    16. 1308.2 Provision for Location of Point of Delivery.
    17. 1308.3 Interconnections Between Gas Piping Sys-
    18. 1308.4 Sizing of Gas Piping Systems. Gas piping systems shall …
    19. 1308.6 Gas Meters. Gas meters shall be selected for the
    20. 1308.7 Gas Pressure Regulators. A line pressure regulator or g…
    21. 1308.9 Pressure Limitation Requirements. Where piping systems …
    22. 1308.10 Backpressure Protection. Protective devices
    23. 1308.10 Backpressure Protection. Protective devices
    24. 1308.8 Overpressure Protection. Where the serving gas
    25. 1308.11 Low-Pressure Protection. A protective device
    26. 1308.12 Shutoff Valves. Shutoff valves shall be approved
    27. 1308.13 Expansion and Flexibility. Piping systems shall
    28. 1309.1 General.1309.0 Excess Flow Valve. Where automatic exces…
    29. 1310.1 Piping Underground. 1310.0 Gas Piping Installation. Und…
    30. 1310.2 Installation of Piping. Piping installed aboveground sh…
    31. 1310.3 Concealed Piping in Buildings. Gas piping in
    32. 1310.4 Piping in Vertical Chases. Where gas piping
    33. 1310.6 Appliance Overpressure Protection. The maximum operatin…
    34. 1310.7 Gas Pipe Turns. Changes in direction of gas pipe
    35. 1310.5 Maximum Design Operating Pressure. The
    36. 1310.8 Drips and Sediment Traps. For other than dry gas
    37. 1310.9 Outlets. Outlets shall be located and installed in
    38. 1310.10 Branch Pipe Connection. When a branch outlet
    39. 1310.11 Manual Gas Shutoff Valves. An accessible gas
    40. 1310.12 Prohibited Devices. No device shall be placed
    41. 1312.1 Connecting Appliances and Equipment.
    42. 1311.4 Lightning Protection System. Where a lightning
    43. 1311.5 Electrical Circuits. Electrical circuits shall not util…
    44. 1311.6 Electrical Connections. All electrical connections
    45. 1311.1 Pipe and Tubing Other than CSST. 1311.0 Electrical Bond…
    46. 1311.2 Bonding of CSST Gas Piping. CSST gas piping
    47. 1311.3 Grounding Conductor of Electrode. Gas piping
    48. 1312.2 Suspended Low-Intensity Infrared Tube
    49. 1312.3 Use of Gas Hose Connectors. Listed gas hose
    50. 1312.7 Quick-Disconnect Devices. Quick-disconnect
    51. 1312.8 Gas Convenience Outlets. Appliances shall be
    52. 1312.4 Injection (Bunsen) Burners. Injection (Bunsen)
    53. 1312.9 Sediment Trap. Where a sediment trap is not incorporate…
    54. 1313.2 Test Preparation. Test preparation shall comply
    55. 1313.3 Test Pressure. This inspection shall include an air,
    56. 1312.10 Installation of Piping. Piping shall be installed in
    57. 1313.1 Piping Installations. 1313.0 Pressure Testing and Inspe…
    58. 1313.4 Detection of Leaks and Defects. The piping system shall…
    59. 1313.5 Piping System Leak Test. Leak checks using fuel
    60. 1313.6 Purging Requirements. The purging of piping
    61. 1314.0 Required Gas Supply. 1314.1 General. The following regu…
    62. 1314.2 Volume. The hourly volume of gas required at each
    63. 1314.3 Gas Appliances. Where the gas appliances to be
    64. 1314.4 Size of Piping Outlets. The size of the supply piping o…
    65. 1315.0 Required Gas Piping Size.1315.1 Pipe Sizing Methods. Wh…
    66. 1315.2 Tables for Sizing Gas Piping Systems. Table
    67. 1315.3 Sizing Equations. The inside diameter of smooth
    68. 1315.4 Sizing of Piping Sections. To determine the size
    69. 1315.5 Engineering Methods. For conditions other than
    70. 1315.6 Variable Gas Pressures. Where the supply gas
  14. Chapter 14 — PROCESS PIPING
  15. Chapter 15 — SOLAR ENERGY SYSTEMS
  16. Chapter 16 — STATIONARY POWER PLANTS
  17. Chapter 17 — REFERENCED STANDARDS
  18. Appendix A — RESIDENTIAL PLAN EXAMINER REVIEW FORM FOR HVAC SY…
  19. Appendix B — PROCEDURES TO BE FOLLOWED TO PLACE GAS EQUIPMENT …
  20. Appendix C — INSTALLATION AND TESTING OF OIL (LIQUID) FUEL-FIR…
  21. Appendix D — FUEL SUPPLY: MANUFACTURED/MOBILE HOME PARKS AND R…
  22. Appendix E — SUSTAINABLE PRACTICES
  23. Appendix F — SIZING OF VENTING SYSTEMS AND OUTDOOR COMBUSTION …
  24. Appendix G — EXAMPLE CALCULATION OF OUTDOOR AIR RATE

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.