1308.10 Backpressure Protection. Protective devices
California Mechanical Code (Title 24, Part 4) · 2019 edition · updated 2026-09-10 · California
Italicized text is a California amendment to the model code, as printed in the official publication.
shall be installed as close to the equipment as practical where the design of the equipment connected is such that air, oxygen, or standby gases are capable of being forced into the gas supply system. Gas and air combustion mixers incorporating double diaphragm “zero” or “atmosphere” governors or regulators shall require no further protection unless connected directly to compressed air or oxygen at pressures of 5 psi (34 kPa) or more. [NFPA 54:5.10.1]
»
(2) Discharge stacks or vents shall be designed to pre vent the entry of water, insects, or other foreign material that could cause blockage. The discharge stack or vent line shall be at least the same size as the outlet of the pressure-relieving device. [NFPA 54:5.9.8.1, 5.9.8.2] 1308.7.7 Bypass Piping. Valved and regulated bypasses shall be permitted to be placed around gas line pressure regulators where continuity of service is imperative. [NFPA 54:5.8.6] 1308.7.8 Identification. Line pressure regulators at multiple regulator installations shall be marked by a metal tag or other permanent means designating the building or the part of the building being supplied.
[NFPA 54:5.8.7]
(1) The line pressure regulator for which the relief valve
is providing overpressure protection has failed wide open. (2) The gas pressure at the inlet of the line pressure reg ulator for which the relief valve is providing over
ulator for which the relief valve is providing over bypasses shall be permitted to be placed around gas line
pressure protection is not less than the regulator’s
pressure regulators where continuity of service is imper normal operating inlet pressure. [NFPA 54:5.9.2.5]
ative. [NFPA 54:5.8.6]
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸Contents — California Mechanical Code (Title 24, Part 4)
- Chapter 1 — GENERAL CODE PROVISIONS
- Chapter 2 — DEFINITIONS
- Chapter 3 — GENERAL REGULATIONS
- Chapter 4 — VENTILATION AIR
- Chapter 5 — EXHAUST SYSTEMS
- Chapter 6 — DUCT SYSTEMS
- Chapter 7 — COMBUSTION AIR
- Chapter 8 — CHIMNEYS AND VENTS
- Chapter 9 — INSTALLATION OF SPECIFIC APPLIANCES
- Chapter 10 — BOILERS AND PRESSURE VESSELS
- Chapter 11 — REFRIGERATION
- Chapter 12 — HYDRONICS
▸Chapter 13 — FUEL GAS PIPING
Overview- 1301.1 Applicability. 1301.0 Scope of Gas Piping. The regulati…
- 1302.1 General. 1302.0 Coverage of Piping System. Coverage of …
- 1302.2 Piping System Requirements. Requirements for
- 1302.3 Applications. This code shall not apply to the followin…
- 1303.2 Excavation. Excavations required for the installation o…
- 1303.3 Type of Inspections. The Authority Having Jurisdiction …
- 1303.4 Inspection Waived. In cases where the work
- 1304.1 Issuance. 1304.0 Certificate of Inspection. Where upon …
- 1304.2 Gas Supplier. A copy of the certificate of such final
- 1304.3 Unlawful. It shall be unlawful for a serving gas suppli…
- 1305.1 Authorized Personnel.1305.0 Authority to Render Gas Ser…
- 1305.2 Outlets. It shall be unlawful to turn on or connect gas
- 1306.2 Notice. Where such disconnection has been made, a
- 1306.3 Capped Outlets. It shall be unlawful to remove or
- 1308.1 Installation of Piping System.Components. Where required
- 1308.2 Provision for Location of Point of Delivery.
- 1308.3 Interconnections Between Gas Piping Sys-
- 1308.4 Sizing of Gas Piping Systems. Gas piping systems shall …
- 1308.6 Gas Meters. Gas meters shall be selected for the
- 1308.7 Gas Pressure Regulators. A line pressure regulator or g…
- 1308.9 Pressure Limitation Requirements. Where piping systems …
- 1308.10 Backpressure Protection. Protective devices
- 1308.10 Backpressure Protection. Protective devices
- 1308.8 Overpressure Protection. Where the serving gas
- 1308.11 Low-Pressure Protection. A protective device
- 1308.12 Shutoff Valves. Shutoff valves shall be approved
- 1308.13 Expansion and Flexibility. Piping systems shall
- 1309.1 General.1309.0 Excess Flow Valve. Where automatic exces…
- 1310.1 Piping Underground. 1310.0 Gas Piping Installation. Und…
- 1310.2 Installation of Piping. Piping installed aboveground sh…
- 1310.3 Concealed Piping in Buildings. Gas piping in
- 1310.4 Piping in Vertical Chases. Where gas piping
- 1310.6 Appliance Overpressure Protection. The maximum operatin…
- 1310.7 Gas Pipe Turns. Changes in direction of gas pipe
- 1310.5 Maximum Design Operating Pressure. The
- 1310.8 Drips and Sediment Traps. For other than dry gas
- 1310.9 Outlets. Outlets shall be located and installed in
- 1310.10 Branch Pipe Connection. When a branch outlet
- 1310.11 Manual Gas Shutoff Valves. An accessible gas
- 1310.12 Prohibited Devices. No device shall be placed
- 1312.1 Connecting Appliances and Equipment.
- 1311.4 Lightning Protection System. Where a lightning
- 1311.5 Electrical Circuits. Electrical circuits shall not util…
- 1311.6 Electrical Connections. All electrical connections
- 1311.1 Pipe and Tubing Other than CSST. 1311.0 Electrical Bond…
- 1311.2 Bonding of CSST Gas Piping. CSST gas piping
- 1311.3 Grounding Conductor of Electrode. Gas piping
- 1312.2 Suspended Low-Intensity Infrared Tube
- 1312.3 Use of Gas Hose Connectors. Listed gas hose
- 1312.7 Quick-Disconnect Devices. Quick-disconnect
- 1312.8 Gas Convenience Outlets. Appliances shall be
- 1312.4 Injection (Bunsen) Burners. Injection (Bunsen)
- 1312.9 Sediment Trap. Where a sediment trap is not incorporate…
- 1313.2 Test Preparation. Test preparation shall comply
- 1313.3 Test Pressure. This inspection shall include an air,
- 1312.10 Installation of Piping. Piping shall be installed in
- 1313.1 Piping Installations. 1313.0 Pressure Testing and Inspe…
- 1313.4 Detection of Leaks and Defects. The piping system shall…
- 1313.5 Piping System Leak Test. Leak checks using fuel
- 1313.6 Purging Requirements. The purging of piping
- 1314.0 Required Gas Supply. 1314.1 General. The following regu…
- 1314.2 Volume. The hourly volume of gas required at each
- 1314.3 Gas Appliances. Where the gas appliances to be
- 1314.4 Size of Piping Outlets. The size of the supply piping o…
- 1315.0 Required Gas Piping Size.1315.1 Pipe Sizing Methods. Wh…
- 1315.2 Tables for Sizing Gas Piping Systems. Table
- 1315.3 Sizing Equations. The inside diameter of smooth
- 1315.4 Sizing of Piping Sections. To determine the size
- 1315.5 Engineering Methods. For conditions other than
- 1315.6 Variable Gas Pressures. Where the supply gas
- Chapter 14 — PROCESS PIPING
- Chapter 15 — SOLAR ENERGY SYSTEMS
- Chapter 16 — STATIONARY POWER PLANTS
- Chapter 17 — REFERENCED STANDARDS
- Appendix A — RESIDENTIAL PLAN EXAMINER REVIEW FORM FOR HVAC SY…
- Appendix B — PROCEDURES TO BE FOLLOWED TO PLACE GAS EQUIPMENT …
- Appendix C — INSTALLATION AND TESTING OF OIL (LIQUID) FUEL-FIR…
- Appendix D — FUEL SUPPLY: MANUFACTURED/MOBILE HOME PARKS AND R…
- Appendix E — SUSTAINABLE PRACTICES
- Appendix F — SIZING OF VENTING SYSTEMS AND OUTDOOR COMBUSTION …
- Appendix G — EXAMPLE CALCULATION OF OUTDOOR AIR RATE