1313.6 Purging Requirements. The purging of piping
California Mechanical Code (Title 24, Part 4) · 2025 edition · updated 2026-09-10 · California
Italicized text is a California amendment to the model code, as printed in the official publication.
shall be in accordance with Section 1313.6.1 through Section 1313.6.3. [NFPA 54:8.3]
1313.6.1 Piping Systems Required to be Purged Outdoors. The purging of piping systems shall be in accordance with Section 1313.6.1.1 through Section 1313.6.1.4 where the piping system meets either of the following:
(1) The design operating gas pressure is greater than 2 psig (14 kPag).
(2) The piping being purged contains one or more sections of pipe or tubing meeting the size and length criteria of Table 1313.6.1. [NFPA 54:8.3.1]
292 2025 CALIFORNIA MECHANICAL CODE
FUEL GAS PIPING
TABLE 1313.6.1
SIZE AND LENGTH OF PIPING
[NFPA 54: TABLE 8.3.1]*
| NOMINAL PIPING SIZE (inches) | LENGTH OF PIPING (feet) |
|---|---|
≥ 21⁄2 < 3 |
> 50 |
≥ 3 < 4 |
> 30 |
≥ 4 < 6 |
> 15 |
≥ 6 < 8 |
> 10 |
≥ 8 |
Any length |
For SI units: 1 inch = 25 mm; 1 foot = 304.8 mm
***** CSST EHD size of 62 is equivalent to 2 inch (50 mm) nominal size pipe or tubing.
1313.6.1.1 Removal from Service. Where existing gas piping is opened, the section that is opened shall be isolated from the gas supply and the line pressure vented in accordance with Section 1313.6.1.3. Where gas piping meeting the criteria of Table 1313.6.1 is removed from service, the residual fuel gas in the piping shall be displaced with an inert gas.
[NFPA 54:8.3.1.1] 1313.6.1.2 Placing in Operation. Where gas piping containing air and meeting the criteria of Table 1313.6.1 is placed in operation, the air in the piping shall first be displaced with an inert gas. The inert gas shall then be displaced with fuel gas in accordance with Section 1313.6.1.3. [NFPA 54:8.3.1.2] 1313.6.1.3 Outdoor Discharge of Purged Gases. The open end of a piping system being pressure vented or purged shall discharge directly to an outdoor location. Purging operations shall comply with all of the following requirements: (1) The point of discharge shall be controlled with a shutoff valve.
(2) The point of discharge shall be located at least 10 feet (3048 mm) from sources of ignition, at least 10 feet (3048 mm) from building openings and at least 25 feet (7620 mm) from mechanical air intake openings. (3) During discharge, the open point of discharge shall be continuously attended and monitored with a combustible gas indicator that complies with Section 1313.6.1.4.
(4) Purging operations introducing fuel gas shall be stopped when 90 percent fuel gas by volume is detected within the pipe. (5) Persons not involved in the purging operations shall be evacuated from all areas within 10 feet (3048 mm) of the point of discharge. [NFPA 54:8.3.1.3]
1313.6.1.4 Combustible Gas Indicator. Combustible gas indicators shall be listed and calibrated in accordance with the manufacturer’s instructions. Combustible gas indicators shall numerically display a volume scale from 0 percent to 100 percent in 1 percent or smaller increments. [NFPA 54:8.3.1.4]
1313.6.2 Piping Systems Allowed to be Purged Indoors or Outdoors. The purging of piping systems shall be in accordance with the provisions of Section 1313.6.2.1 where the piping system meets both of the following: (1) The design operating pressure is 2 psig (14 kPag) or less.
(2) The piping being purged is constructed entirely from pipe or tubing not meeting the size and length criteria of Table 1313.6.1. [NFPA 54:8.3.2] 1313.6.2.1 Purging Procedure. The piping system shall be purged in accordance with one or more of the following: (1) The piping shall be purged with fuel gas and shall discharge to the outdoors. (2) The piping shall be purged with fuel gas and shall discharge to the indoors or outdoors through an appliance burner not located in a combustion chamber. Such burner shall be provided with a continuous source of ignition. (3) The piping shall be purged with fuel gas and shall discharge to the indoors or outdoors through a burner that has a continuous source of ignition and that is designed for such purpose. (4) The piping shall be purged with fuel gas that is discharged to the indoors or outdoors, and the point of discharge shall be monitored with a listed combustible gas detector in accordance with Section 1313.6.2.2. Purging shall be stopped when fuel gas is detected. (5) The piping shall be purged by the gas supplier in accordance with written procedures. [NFPA 54:8.3.2.1] 1313.6.2.2 Combustible Gas Detector. Combustible gas detectors shall be listed and calibrated or tested in accordance with the manufacturer’s instructions. Combustible gas detectors shall be capable of indicating the presence of fuel gas. [NFPA 54:8.3.2.2] 1313.6.3 Purging Appliances and Equipment. After the piping system has been placed in operation, appliances and equipment shall be purged before being placed into operation. [NFPA 54:8.3.3]
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸Contents — California Mechanical Code (Title 24, Part 4)
- Chapter 1 — GENERAL CODE PROVISIONS
- Chapter 2 — DEFINITIONS
- Chapter 3 — GENERAL REGULATIONS
- Chapter 4 — VENTILATION AIR
- Chapter 5 — EXHAUST SYSTEMS
- Chapter 6 — DUCT SYSTEMS
- Chapter 7 — COMBUSTION AIR
- Chapter 8 — CHIMNEYS AND VENTS
- Chapter 9 — INSTALLATION OF SPECIFIC APPLIANCES
- Chapter 10 — BOILERS AND PRESSURE VESSELS
- Chapter 11 — REFRIGERATION
- Chapter 12 — HYDRONICS
▸Chapter 13 — FUEL GAS PIPING
Overview- 1301.1 Applicability. The regulations of this chapter shall
- 1302.1 General. Coverage of piping systems shall extend
- 1302.2 Piping System Requirements. Requirements for
- 1302.3 Applications. This chapter shall not apply to the
- 1303.1 Inspection Notification. Upon completion of the
- 1303.2 Excavation. Excavations required for the installation o…
- 1303.3 Type of Inspections. The Authority Having Jurisdiction …
- 1303.4 Inspection Waived. In cases where the work authorized b…
- 1304.1 Issuance. Whereupon final piping inspection, the
- 1304.2 Gas Supplier. A copy of the certificate of such final
- 1304.3 Unlawful. It shall be unlawful for a serving gas suppli…
- 1305.1 Authorized Personnel. It shall be unlawful for a
- 1305.2 Outlets. It shall be unlawful to turn on or connect gas
- 1306.1 Disconnection. The Authority Having Jurisdiction
- 1306.2 Notice. Where such disconnection has been made, a
- 1306.3 Capped Outlets. It shall be unlawful to remove or
- 1307.1 General. Where temporary use of gas is desired, and
- 1308.1 Installation of Piping System. Where required
- 1308.2 Interconnections Supplying Separate Users.
- 1308.3 Sizing of Gas Piping Systems. Gas piping systems shall …
- 1308.4 Acceptable Piping Materials and Joining
- 1308.5 Gas Meters. Gas meters shall be selected for the
- 1308.6 Gas Pressure Regulators. A line pressure regulator shal…
- 1308.7 Overpressure Protection. Where the serving gas
- 1308.8 Pressure Limitation Requirements. Where piping systems …
- 1308.9 Overpressure Protection Devices. Overpressure protectio…
- 1308.13 Expansion and Flexibility. Piping systems shall
- 1308.14 Pressure Regulator and Pressure Control
- 1308.10 Backpressure Protection. Protective devices
- 1308.11 Low-Pressure Protection. A protective device
- 1308.12 Shutoff Valves. Shutoff valves shall be selected in
- 1309.1 General. Where automatic excess flow valves are
- 1310.1 Piping Underground. Underground gas piping shall
- 1310.2 CSST Piping Systems. CSST piping systems shall
- 1310.3 Installation of Aboveground Piping. Piping
- 1310.4 Concealed Piping in Buildings. Gas piping in
- 1310.5 Piping in Vertical Chases. Where gas piping
- 1310.6 Maximum Operating Pressure in Buildings.
- 1310.7 Appliance Overpressure Protection. The maximum operatin…
- 1310.8 Gas Pipe Turns. Changes in direction of gas pipe
- 1310.9 Drips and Sediment Traps. For other than dry gas
- 1310.10 Outlets. Outlets shall be located and installed in
- 1310.11 Manual Gas Shutoff Valves. An accessible gas
- 1310.12 Prohibited Devices. Devices shall not be placed
- 1310.13 Systems Containing Gas-Air Mixtures Out-
- 1310.14 Systems Containing Flammable Gas-Air
- 1311.1 Pipe and Tubing Other than CSST. Each aboveground porti…
- 1311.2 Bonding of CSST Gas Piping. CSST gas piping
- 1311.3 Arc-Resistant Jacketed CSST. CSST listed with
- 1311.4 Prohibited Use. Gas piping shall not be used as a
- 1311.5 Lightning Protection System. Where a lightning
- 1311.6 Electrical Circuits. Electrical circuits shall not util…
- 1311.7 Electrical Connections. All electrical connections
- 1312.1 Connecting Appliances and Equipment.
- 1312.3 Use of Nonmetallic Gas Hose Connectors.
- 1312.4 Injection (Bunsen) Burners. Injection (Bunsen)
- 1312.5 Connection of Portable and Mobile Industrial
- 1312.2 Suspended Low-Intensity Infrared Tube
- 1312.6 Appliance Shutoff Valves and Connections.
- 1312.7 Quick-Disconnect Devices. Quick-disconnect
- 1312.8 Gas Convenience Outlets. Appliances shall be
- 1312.9 Sediment Trap. Where a sediment trap is not incorporate…
- 1312.10 Installation of Piping. Piping shall be installed in
- 1312.11 Liquefied Petroleum Gas (LP-Gas) Facilities
- 1313.1 Piping Installations. Prior to acceptance and initial o…
- 1313.2 Test Preparation. Test preparation shall comply
- 1313.3 Test Pressure. This inspection shall include an air,
- 1313.4 Detection of Leaks and Defects. The piping system shall…
- 1313.5 Piping System Leak Test. Leak checks using fuel
- 1313.6 Purging Requirements. The purging of piping
- 1314.1 General. The following regulations, shall comply
- 1314.2 Volume. The hourly volume of gas required at each
- 1314.3 Gas Appliances. Where the gas appliances to be
- 1314.4 Size of Piping Outlets. The size of the supply piping o…
- 1315.1 Pipe Sizing Methods. Where the pipe size is to be
- 1315.2 Sizing of Gas Piping Systems. Sizing of piping
- 1315.3 Sizing Equations. The inside diameter of smooth
- 1315.4 Sizing of Piping Sections. To determine the size
- 1315.5 Engineering Methods. For conditions other than
- 1315.6 Variable Gas Pressures. Where the supply gas
- Chapter 14 — PROCESS PIPING
- Chapter 15 — SOLAR ENERGY SYSTEMS
- Chapter 16 — STATIONARY POWER PLANTS
- Chapter 17 — GEOTHERMAL ENERGY SYSTEMS AND AMBIENT TEMPERATURE…
- Chapter 18 — REFERENCED STANDARDS
- Appendix A — RESIDENTIAL PLAN EXAMINER REVIEW FORM FOR HVAC SY…
- Appendix B — PROCEDURES TO BE FOLLOWED TO PLACE GAS EQUIPMENT …
- Appendix C — INSTALLATION AND TESTING OF OIL (LIQUID) FUEL-FIR…
- Appendix D — FUEL SUPPLY: MANUFACTURED/MOBILE HOME PARKS AND R…
- Appendix E — SUSTAINABLE PRACTICES
- Appendix F — SIZING OF VENTING SYSTEMS AND OUTDOOR COMBUSTION …
- Appendix G — EXAMPLE CALCULATION OF OUTDOOR AIR RATE
- Appendix H — PROFESSIONAL QUALIFICATIONS
- Appendix I — INDOOR HORTICULTURAL FACILITIES
- Appendix J — CLEAN AIR DELIVERY