1308.14 Pressure Regulator and Pressure Control
California Mechanical Code (Title 24, Part 4) · 2025 edition · updated 2026-09-10 · California
Italicized text is a California amendment to the model code, as printed in the official publication.
Venting. The venting of the atmospheric side of diaphragms in line pressure regulators, gas appliance regulators, and gas pressure limit controls shall be in accordance with all of the following:
(1) An independent vent pipe to the outdoors, sized in accordance with the device manufacturer’s instructions, shall be provided where the location of a device is such that a discharge of fuel gas will cause a hazard. For devices other than appliance regulators, vents are not required to be independent where the vents are connected to a common manifold designed in accordance with engineering methods to minimize backpressure in the event of diaphragm failure and such design is approved.
»
»
»
»
»
»
sure relieving valve or pressure limiting device inoperative, one of the following shall be accomplished:
(1) The valve shall be locked in the open position. Instruct authorized personnel in the importance of leaving the shutoff valve open and of being present while the shutoff valve is closed so that it can be locked in the open position before leaving the premises.
(2) Duplicate relief valves shall be installed, each having adequate capacity to protect the system, and arrange the isolating valves or three-way valve so that only one relief valve can be rendered inoperative at a time.
[NFPA 54:5.8.7] 1308.9.6 Discharge of Vents. The discharge stacks, vents, or outlet parts of all pressure relieving and pressure limiting devices shall be located so that gas is safely discharged to the outdoors. Discharge stacks or vents shall be designed to prevent the entry of water, insects, or other foreign material that could cause blockage. The discharge stack or vent line shall be at least the same size as the outlet of the pressure relieving device. [NFPA 54:5.8.8.1, 5.8.8.2] 1308.9.7 Size of Fittings, Pipe, and Openings. The fittings, pipe, and openings located between the system to be protected and the pressure relieving device shall be sized to prevent hammering of the valve and to prevent impairment of relief capacity. [NFPA 54:5.8.9]
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸Contents — California Mechanical Code (Title 24, Part 4)
- Chapter 1 — GENERAL CODE PROVISIONS
- Chapter 2 — DEFINITIONS
- Chapter 3 — GENERAL REGULATIONS
- Chapter 4 — VENTILATION AIR
- Chapter 5 — EXHAUST SYSTEMS
- Chapter 6 — DUCT SYSTEMS
- Chapter 7 — COMBUSTION AIR
- Chapter 8 — CHIMNEYS AND VENTS
- Chapter 9 — INSTALLATION OF SPECIFIC APPLIANCES
- Chapter 10 — BOILERS AND PRESSURE VESSELS
- Chapter 11 — REFRIGERATION
- Chapter 12 — HYDRONICS
▸Chapter 13 — FUEL GAS PIPING
Overview- 1301.1 Applicability. The regulations of this chapter shall
- 1302.1 General. Coverage of piping systems shall extend
- 1302.2 Piping System Requirements. Requirements for
- 1302.3 Applications. This chapter shall not apply to the
- 1303.1 Inspection Notification. Upon completion of the
- 1303.2 Excavation. Excavations required for the installation o…
- 1303.3 Type of Inspections. The Authority Having Jurisdiction …
- 1303.4 Inspection Waived. In cases where the work authorized b…
- 1304.1 Issuance. Whereupon final piping inspection, the
- 1304.2 Gas Supplier. A copy of the certificate of such final
- 1304.3 Unlawful. It shall be unlawful for a serving gas suppli…
- 1305.1 Authorized Personnel. It shall be unlawful for a
- 1305.2 Outlets. It shall be unlawful to turn on or connect gas
- 1306.1 Disconnection. The Authority Having Jurisdiction
- 1306.2 Notice. Where such disconnection has been made, a
- 1306.3 Capped Outlets. It shall be unlawful to remove or
- 1307.1 General. Where temporary use of gas is desired, and
- 1308.1 Installation of Piping System. Where required
- 1308.2 Interconnections Supplying Separate Users.
- 1308.3 Sizing of Gas Piping Systems. Gas piping systems shall …
- 1308.4 Acceptable Piping Materials and Joining
- 1308.5 Gas Meters. Gas meters shall be selected for the
- 1308.6 Gas Pressure Regulators. A line pressure regulator shal…
- 1308.7 Overpressure Protection. Where the serving gas
- 1308.8 Pressure Limitation Requirements. Where piping systems …
- 1308.9 Overpressure Protection Devices. Overpressure protectio…
- 1308.13 Expansion and Flexibility. Piping systems shall
- 1308.14 Pressure Regulator and Pressure Control
- 1308.10 Backpressure Protection. Protective devices
- 1308.11 Low-Pressure Protection. A protective device
- 1308.12 Shutoff Valves. Shutoff valves shall be selected in
- 1309.1 General. Where automatic excess flow valves are
- 1310.1 Piping Underground. Underground gas piping shall
- 1310.2 CSST Piping Systems. CSST piping systems shall
- 1310.3 Installation of Aboveground Piping. Piping
- 1310.4 Concealed Piping in Buildings. Gas piping in
- 1310.5 Piping in Vertical Chases. Where gas piping
- 1310.6 Maximum Operating Pressure in Buildings.
- 1310.7 Appliance Overpressure Protection. The maximum operatin…
- 1310.8 Gas Pipe Turns. Changes in direction of gas pipe
- 1310.9 Drips and Sediment Traps. For other than dry gas
- 1310.10 Outlets. Outlets shall be located and installed in
- 1310.11 Manual Gas Shutoff Valves. An accessible gas
- 1310.12 Prohibited Devices. Devices shall not be placed
- 1310.13 Systems Containing Gas-Air Mixtures Out-
- 1310.14 Systems Containing Flammable Gas-Air
- 1311.1 Pipe and Tubing Other than CSST. Each aboveground porti…
- 1311.2 Bonding of CSST Gas Piping. CSST gas piping
- 1311.3 Arc-Resistant Jacketed CSST. CSST listed with
- 1311.4 Prohibited Use. Gas piping shall not be used as a
- 1311.5 Lightning Protection System. Where a lightning
- 1311.6 Electrical Circuits. Electrical circuits shall not util…
- 1311.7 Electrical Connections. All electrical connections
- 1312.1 Connecting Appliances and Equipment.
- 1312.3 Use of Nonmetallic Gas Hose Connectors.
- 1312.4 Injection (Bunsen) Burners. Injection (Bunsen)
- 1312.5 Connection of Portable and Mobile Industrial
- 1312.2 Suspended Low-Intensity Infrared Tube
- 1312.6 Appliance Shutoff Valves and Connections.
- 1312.7 Quick-Disconnect Devices. Quick-disconnect
- 1312.8 Gas Convenience Outlets. Appliances shall be
- 1312.9 Sediment Trap. Where a sediment trap is not incorporate…
- 1312.10 Installation of Piping. Piping shall be installed in
- 1312.11 Liquefied Petroleum Gas (LP-Gas) Facilities
- 1313.1 Piping Installations. Prior to acceptance and initial o…
- 1313.2 Test Preparation. Test preparation shall comply
- 1313.3 Test Pressure. This inspection shall include an air,
- 1313.4 Detection of Leaks and Defects. The piping system shall…
- 1313.5 Piping System Leak Test. Leak checks using fuel
- 1313.6 Purging Requirements. The purging of piping
- 1314.1 General. The following regulations, shall comply
- 1314.2 Volume. The hourly volume of gas required at each
- 1314.3 Gas Appliances. Where the gas appliances to be
- 1314.4 Size of Piping Outlets. The size of the supply piping o…
- 1315.1 Pipe Sizing Methods. Where the pipe size is to be
- 1315.2 Sizing of Gas Piping Systems. Sizing of piping
- 1315.3 Sizing Equations. The inside diameter of smooth
- 1315.4 Sizing of Piping Sections. To determine the size
- 1315.5 Engineering Methods. For conditions other than
- 1315.6 Variable Gas Pressures. Where the supply gas
- Chapter 14 — PROCESS PIPING
- Chapter 15 — SOLAR ENERGY SYSTEMS
- Chapter 16 — STATIONARY POWER PLANTS
- Chapter 17 — GEOTHERMAL ENERGY SYSTEMS AND AMBIENT TEMPERATURE…
- Chapter 18 — REFERENCED STANDARDS
- Appendix A — RESIDENTIAL PLAN EXAMINER REVIEW FORM FOR HVAC SY…
- Appendix B — PROCEDURES TO BE FOLLOWED TO PLACE GAS EQUIPMENT …
- Appendix C — INSTALLATION AND TESTING OF OIL (LIQUID) FUEL-FIR…
- Appendix D — FUEL SUPPLY: MANUFACTURED/MOBILE HOME PARKS AND R…
- Appendix E — SUSTAINABLE PRACTICES
- Appendix F — SIZING OF VENTING SYSTEMS AND OUTDOOR COMBUSTION …
- Appendix G — EXAMPLE CALCULATION OF OUTDOOR AIR RATE
- Appendix H — PROFESSIONAL QUALIFICATIONS
- Appendix I — INDOOR HORTICULTURAL FACILITIES
- Appendix J — CLEAN AIR DELIVERY