1211.2 Bonding of CSST Gas Piping. CSST gas piping
California Plumbing Code (Title 24, Part 5) · 2019 edition · updated 2026-09-10 · California
Italicized text is a California amendment to the model code, as printed in the official publication.
systems, and gas piping systems containing one or more segments of CSST, shall be bonded to the electrical service grounding electrode system or, where provided, lightning protection grounding electrode system. [NFPA 54:7.13.2]
1211.2.1 Bonding Jumper Connection. The bonding jumper shall connect to a metallic pipe, pipe fitting, or CSST fitting. [NFPA 54:7.13.2.1] 1211.2.2 Bonding Jumper Size. The bonding jumper shall not be smaller than 6 AWG copper wire or equivalent. [NFPA 54:7.13.2.2] 1211.2.3 Bonding Jumper Length. The length of the jumper between the connection to the gas piping system and the grounding electrode system shall not exceed 75 feet (22 875 mm). Any additional electrodes shall be bonded to the electrical service grounding electrode system or, where provided, lightning protection grounding electrode system. [NFPA 54:7.13.2.3] 1211.2.4 Bonding Connections. Bonding connections shall be in accordance with NFPA 70 . [NFPA 54:7.13.2.4] 1211.2.5 Devices Used for Bonding. Devices used for the bonding connection shall be listed for the application in accordance with UL 467. [NFPA 54:7.13.2.5]
2019 CALIFORNIA PLUMBING CODE 233
FUEL GAS PIPING any other purpose or distributed to any other persons or parti es.
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸Contents — California Plumbing Code (Title 24, Part 5)
- Chapter 1 — GENERAL CODE PROVISIONS
- Chapter 2 — DEFINITIONS
- Chapter 3 — GENERAL REGULATIONS
- Chapter 4 — PLUMBING FIXTURES AND FIXTURE FITTINGS
- Chapter 5 — WATER HEATERS
- Chapter 6 — WATER SUPPLY AND DISTRIBUTION
- Chapter 7 — SANITARY DRAINAGE
- Chapter 8 — INDIRECT WASTES
- Chapter 9 — VENTS
- Chapter 10 — TRAPS AND INTERCEPTORS
- Chapter 11 — STORM DRAINAGE
▸Chapter 12 — FUEL GAS PIPING
Overview- 1201.0 General.1201.1 Applicability. The regulations of this c…
- 1202.0 Coverage of Piping System.1202.1 General. Coverage of p…
- 1202.2 Piping System Requirements. Requirements for
- 1202.3 Applications. This code shall not apply to the followin…
- 1203.2 Excavation. Excavations required for the installation o…
- 1203.3 Type of Inspections. The Authority Having Jurisdiction …
- 1203.4 Inspection Waived. In cases where the work
- 1204.2 Gas Supplier. A copy of the certificate of such final
- 1204.3 Unlawful. It shall be unlawful for a serving gas suppli…
- 1205.2 Outlets. It shall be unlawful to turn on or connect gas
- 1206.2 Notice. Where such disconnection has been made, a
- 1206.3 Capped Outlets. It shall be unlawful to remove or
- 1208.0 Gas Piping System Design, Materials, and
- 1208.2 Provision for Location of Point of Delivery. The locati…
- 1208.3 Interconnections Between Gas Piping Sys-tems. Where two…
- 1208.4 Sizing of Gas Piping Systems. Gas piping systems shall …
- 1208.5 Maximum Design Operating Pressure. The
- 1208.6 Acceptable Piping Materials and JoiningMethods. Materia…
- 1208.7 Gas Meters. Gas meters shall be selected for the
- 1208.8 Gas Pressure Regulators. A line pressure regulator or g…
- 1208.9 Overpressure Protection Devices. Where the
- 1208.10 Pressure Limitation Requirements. Where
- 1208.11 Backpressure Protection. Protective devices
- 1208.12 Low-Pressure Protection. A protective device
- 1208.13 Shutoff Valves. Shutoff valves shall be approved
- 1208.14 Expansion and Flexibility. Piping systems shall
- 1210.0 Gas Piping Installation.1210.1 Piping Underground. Unde…
- 1210.2 Installation of Piping. Piping installed aboveground sh…
- 1210.3 Concealed Piping in Buildings. Gas piping in
- 1210.4 Piping in Vertical Chases. Where gas piping
- 1210.6 Drips and Sediment Traps. For other than dry gas
- 1210.7 Outlets. Outlets shall be located and installed in
- 1210.5 Gas Pipe Turns. Changes in direction of gas pipe
- 1210.10 Prohibited Devices. No device shall be placed
- 1210.11 Systems Containing Gas-Air Mixtures Out-side the Flamm…
- 1210.12 Systems Containing Flammable Gas-AirMixtures. Systems …
- 1210.8 Branch Pipe Connection. Where a branch outlet
- 1210.9 Manual Gas Shutoff Valves. An accessible gas
- 1211.2 Bonding of CSST Gas Piping. CSST gas piping
- 1211.3 Prohibited Use. Gas piping shall not be used as a
- 1211.4 Lightning Protection System. Where a lightning
- 1211.5 Electrical Circuits. Electrical circuits shall not util…
- 1211.6 Electrical Connections. All electrical connections
- 1211.7 Earthquake-Actuated Gas Shutoff Valves. Earth-
- 1212.2 Suspended Low-Intensity Infrared TubeHeaters. Suspended…
- 1212.3 Use of Nonmetallic Gas Hose Connectors. Listed gas hose…
- 1212.1 Connecting Appliances and Equipment.
- 1212.4 Injection (Bunsen) Burners. Injection (Bunsen)
- 1212.5 Connection of Portable and Mobile Industrial
- 1212.5 Connection of Portable and Mobile Industrial
- 1212.9 Sediment Trap. Where a sediment trap is not incorporate…
- 1212.6 Appliance Shutoff Valves and Connections.
- 1212.7 Quick-Disconnect Devices. Quick-disconnect
- 1212.8 Gas Convenience Outlets. Appliances shall be
- 1212.10 Installation of Piping. Piping shall be installed in
- 1212.11 Liquefied Petroleum Gas Facilities and Pip-
- 1213.0 Pressure Testing, Inspection, and Purging.1213.1 Piping…
- 1213.2 Test Preparation. Test preparation shall comply
- 1213.3 Test Pressure. This inspection shall include an air,
- 1213.4 Detection of Leaks and Defects. The piping system shall…
- 1213.5 Piping System Leak Test. Leak checks using fuel
- 1213.6 Purging Requirements. The purging of piping
- 1215.2 Tables for Sizing Gas Piping Systems. Table
- 1215.3 Sizing Equations. The inside diameter of smoothwall pip…
- 1214.2 Volume. The hourly volume of gas required at each
- 1214.3 Gas Appliances. Where the gas appliances to be
- 1214.4 Size of Piping Outlets. The size of the supply piping o…
- 1215.0 Required Gas Piping Size.1215.1 Pipe Sizing Methods. Wh…
- 1215.5 Engineering Methods. For conditions other than
- 1215.6 Variable Gas Pressure. Where the supply gas
- 1215.4 Sizing of Piping Sections. To determine the size
- Chapter 13 — HEALTH CARE FACILITIES AND MEDICAL GAS AND MEDICA…
- Chapter 14 — FIRESTOP PROTECTION
- Chapter 15 — ALTERNATE WATER SOURCES FOR NONPOTABLE APPLICATIONS
- Chapter 16 — NONPOTABLE RAINWATER CATCHMENT SYSTEMS
- Chapter 17 — REFERENCED STANDARDS
- Appendix A — RECOMMENDED RULES FOR SIZING THE WATER SUPPLY SYS…
- Appendix B — EXPLANATORY NOTES ON COMBINATION WASTE AND VENT S…
- Appendix C — ALTERNATE PLUMBING SYSTEMS
- Appendix D — SIZING STORM WATER DRAINAGE SYSTEMS
- Appendix E — MANUFACTURED/MOBILE HOME PARKS AND RECREATIONAL V…
- Appendix F — FIREFIGHTER BREATHING AIR REPLENISHMENT SYSTEMS
- Appendix G — SIZING OF VENTING SYSTEMS
- Appendix H — PRIVATE SEWAGE DISPOSAL SYSTEMS
- Appendix I — INSTALLATION STANDARD FOR PEX TUBING SYSTEMS FOR …
- Appendix J — COMBINATION OF INDOOR AND OUTDOOR COMBUSTION AND …
- Appendix K — POTABLE RAINWATER CATCHMENT SYSTEMS
- Appendix L — SUSTAINABLE PRACTICES
- Appendix M — PEAK WATER DEMAND CALCULATOR