707.9 Clearance — 2025 California Plumbing Code
California Plumbing Code (Title 24, Part 5) · 2025 edition · updated 2026-09-25 · California
CBSC: official editions, supplements and errata
Italicized text is a California amendment to the model code, as printed in the official publication.
Cite as: 2025 California Plumbing Code (Title 24, Part 5) § 707.9 · Effective January 1, 2026 · Official source: Building Standards Commission
Each cleanout in piping 2 inches (50 mm) or less in size shall be so installed that there is a clearance of not less than 18 inches (457 mm) by 18 inches (457 mm) in front of the cleanout. Cleanouts in piping exceeding 2 inches (50 mm) shall have a clearance of not less than 24 inches (610 mm) by 24 inches (610 mm) in front of the cleanout. Cleanouts in under-floor piping shall be extended to or above the finished floor or shall be extended outside the building where there is less than 18 inches (457 mm) vertical overall, allowing for obstructions such as ducts, beams, and piping, and 30 inches of (762 mm) horizontal clearance from the means of access to such cleanout. No under-floor cleanout shall be located exceeding 5 feet (1524 mm) from an access door, trap door, or crawl hole.
Get a plain-English answer with a citation back to this text.
Ask AI about this code