408.1 General. Filter efficiencies shall be certified by the
California Mechanical Code (Title 24, Part 4) · 2025 edition · updated 2026-09-10 · California
Italicized text is a California amendment to the model code, as printed in the official publication.
manufacturer and shall be based on ASHRAE 52.2 Method of Testing General Ventilation Air-Cleaning Devices for Removal Efficiency by Particle Size when specifically set forth in these standards.
408.1.1 A filter gauge shall be installed across each fil- ter bank serving central air systems. The gauge shall be red lined or a filter alarm light installed to signal when the recommended maximum static pressure drop has been reached.
408.1.2 Central air-handling systems are defined as any unit requiring duct work on the supply or inlet side that serve more than one room.
408.1.3 Filter banks shall be visually inspected for torn media and bypass in filter frames by means of a flashlight or equivalent, both with fans in operation and stopped. Tears in media and bypass in filter frames shall be elim- inated in accordance with the manufacturer’s directions and the requirements of the enforcing agency prior to commencing operation of the system.
408.1.4 Central air-handling systems shall be maintained in a reasonably clean condition during construction and shall be cleaned as necessary prior to replacement of tem- porary filter used during construction to ensure that clean air will be delivered to the occupied spaces.
408.1.5 Filter bank No. 1 shall be located upstream of the air-conditioning equipment. Filter bank No. 2 and additional filter banks shall be located downstream of the supply fan and all cooling and humidification equipment with efficiencies as indicated in Table 4-B or Table 4-C.
Exception: Humidifiers for local room humidity control may be installed in the supply air duct downstream of the final filter bank where designs are specifically approved by the enforcing agency. Humidification shall be in accor- dance with 320.1.1.
408.1.6 Filter bank No. 2 and additional filter bank media shall be rigid or supported (noncollapsing type) and shall operate on the principles of impingement, straining, and diffusion. Filter bank No. 2 shall have sealing interface surfaces.
408.1.7 HEPA filtration shall be provided in the air ter- minal device where required by Table 4-B.
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸Contents — California Mechanical Code (Title 24, Part 4)
- Chapter 1 — GENERAL CODE PROVISIONS
- Chapter 2 — DEFINITIONS
- Chapter 3 — GENERAL REGULATIONS
▸Chapter 4 — VENTILATION AIR
Overview- 401.1 Applicability. This chapter contains requirements for
- 401.2 Indoor Swimming Pools. The design of ventilation
- 401.3 Filters. [BSC-CG & DSA-SS] In mechanically ven-
- 402.1 Occupiable Spaces. Occupiable spaces listed in
- 402.2 Natural Ventilation Procedure. [Not permitted
- 402.3 Mechanical Ventilation. [Not permitted for
- 402.4 Outdoor Air Intakes. Ventilation system outdoor
- 403.1 General. The design outdoor air intake flow rate for
- 403.2 Zone Calculations. Ventilation zone parameters
- 403.3 Single-Zone Systems. For ventilation systems
- 403.4 One Hundred Percent Outdoor Air Systems.
- 403.5 Multiple-Zone Recirculating Systems. For ventilation sys…
- 403.6 Design for Varying Operating Conditions. Ventilation sys…
- 403.7 Exhaust Ventilation. Exhaust airflow shall be provided i…
- 403.8 Dynamic Reset. The system shall be permitted to be
- 403.9 Air Classification and Recirculation. Air shall be
- 403.10 Air Balance. All mechanical ventilation systems
- 404.1 System Ventilation Efficiency. The system ventilation ef…
- 404.2 Average Outdoor Air Fraction. The average outdoor air fr…
- 404.3 Zone Ventilation Efficiency. The zone ventilation
- 405.1 General. Rooms or occupied spaces within residential occ…
- 405.2 Ventilation Air Rate. The required mechanical ventilatio…
- 405.3 Bathroom Exhaust. A mechanical exhaust directly
- 405.4 Kitchen Exhaust. A mechanical exhaust system that
- 405.5 Ventilation Openings. Occupiable spaces shall be
- 406.0 Evaporative Cooling System for Health Care
- 407.1 General.
- 407.2 Outdoor Air Intakes and Exhaust Outlets.
- 407.3 Air Balance.
- 407.4 Air Circulation.
- 407.5 Variable Air Volume.
- 407.6 Economizers.
- 407.7 Unoccupied Turndown.
- 408.3 Filters for Skilled Nursing Facilities, Intermedi-
- 408.4 Filters for Outpatient Facilities.
- 408.5 Filters for Recirculating Room Units.
- 409.1 Ducts which penetrate construction, intended for X-
- 409.2 Duct linings and their use shall meet the requirements
- 409.3 The anchorage and supporting structural elements for
- 410.1 Laboratory Ventilating Systems. Laboratory ven-
- 410.2 Exhaust Hoods and Safety Cabinets. Hoods and
- 410.3 Laboratory Fume Hoods. Laboratory fume hoods
- 407.8 Building Pressurization.
- 408.1 General. Filter efficiencies shall be certified by the
- 408.2 Filters for Hospitals.
- 411.1 The air from dining areas may be used to ventilate the
- 412.1 Boiler, heater and electrical equipment rooms shall be
- 412.2 Floor surfaces in occupied spaces above such rooms
- 413.1 Rooms in areas where excessive heat or moisture is
- 413.2 Kitchen, morgues and laundries located inside a hos-
- 414.1 Exhaust Systems. A separate, dedicated exhaust
- 414.2 Air Distribution. The supply outlets and exhaust
- 415.1 Air Distribution. The supply outlets and exhaust and
- 416.1 An alarm system which is based on static pressure con-
- 416.2 Other acceptable alarm systems will be allowed when
- 416.3 [OSHPD 4] For correctional treatment centers, the
- 416.4 Prior to acceptance of the rooms, the alarm system
- 417.0 Testing and Balancing Airborne Infection Isola-
- 418.1 Air Changes. The ETO sterilization equipment room
- 418.2 Exhaust Requirements.
- 418.3 Ventilation Requirements.
- 418.4 Gas Valves. Installation of gas line hand valves at the
- 418.5 Alarm Systems. An Audible and visual alarm system
- 419.1 Formula Preparation Area. Air shall be supplied
- 419.2 Treatment Area/Room. Air shall be supplied over
- Chapter 5 — EXHAUST SYSTEMS
- Chapter 6 — DUCT SYSTEMS
- Chapter 7 — COMBUSTION AIR
- Chapter 8 — CHIMNEYS AND VENTS
- Chapter 9 — INSTALLATION OF SPECIFIC APPLIANCES
- Chapter 10 — BOILERS AND PRESSURE VESSELS
- Chapter 11 — REFRIGERATION
- Chapter 12 — HYDRONICS
- Chapter 13 — FUEL GAS PIPING
- Chapter 14 — PROCESS PIPING
- Chapter 15 — SOLAR ENERGY SYSTEMS
- Chapter 16 — STATIONARY POWER PLANTS
- Chapter 17 — GEOTHERMAL ENERGY SYSTEMS AND AMBIENT TEMPERATURE…
- Chapter 18 — REFERENCED STANDARDS
- Appendix A — RESIDENTIAL PLAN EXAMINER REVIEW FORM FOR HVAC SY…
- Appendix B — PROCEDURES TO BE FOLLOWED TO PLACE GAS EQUIPMENT …
- Appendix C — INSTALLATION AND TESTING OF OIL (LIQUID) FUEL-FIR…
- Appendix D — FUEL SUPPLY: MANUFACTURED/MOBILE HOME PARKS AND R…
- Appendix E — SUSTAINABLE PRACTICES
- Appendix F — SIZING OF VENTING SYSTEMS AND OUTDOOR COMBUSTION …
- Appendix G — EXAMPLE CALCULATION OF OUTDOOR AIR RATE
- Appendix H — PROFESSIONAL QUALIFICATIONS
- Appendix I — INDOOR HORTICULTURAL FACILITIES
- Appendix J — CLEAN AIR DELIVERY