Chapter 13 — HEALTH CARE FACILITIES AND MEDICAL GAS AND MEDICAL VACUUM SYSTEMS
1309.7 Brazing Dissimilar Metals. Flux shall only be
California Plumbing Code (Title 24, Part 5) · 2019 edition · updated 2026-09-10 · California
Italicized text is a California amendment to the model code, as printed in the official publication.
used when brazing dissimilar metals, such as copper and bronze or brass, using a silver (BAg series) brazing filler metal. [NFPA 99:5.1.10.4.4.1]
«
«
«
1309.6.1 Exterior Surfaces. The exterior surfaces of tube ends shall be cleaned prior to brazing to remove any surface oxides. When cleaning the exterior surfaces of tube ends, no matter shall be allowed to enter the tube.
[NFPA 99:5.1.10.4.3.2, 5.1.10.4.3.3] 1309.6.2 Interior Surfaces. If the interior surfaces of fitting sockets become contaminated prior to brazing, they shall be recleaned for oxygen in accordance with Section 1309.6.7 and be cleaned for brazing with a clean, oil-free wire brush. [NFPA 99:5.1.10.4.3.4] 1309.6.3 Abrasive Pads. Clean, nonshedding, abrasive pads shall be used to clean the exterior surfaces of the tube ends. [NFPA 99:5.1.10.4.3.5] 1309.6.4 Prohibited. The use of steel wool or sand cloth shall be prohibited. The cleaning process shall not result in grooving of the surfaces to be joined. [NFPA 99:5.1.10.4.3.6, 5.1.10.4.3.7] 1309.6.5 Wiped. After being abraded, the surfaces shall be wiped using a clean, lint-free white cloth. [NFPA 99:5.1.10.4.3.8] 1309.6.6 Examination. Tubes, fittings, valves, and other components shall be visually examined internally before being joined to verify that they have not become contaminated for oxygen service and that they are free of obstructions or debris. [NFPA 99:5.1.10.4.3.9] 1309.6.7 On-Site Recleaning. The interior surfaces of tube ends, fittings, and other components that were cleaned for oxygen service by the manufacturer, but that became contaminated prior to being installed, shall be permitted to be recleaned on-site by the installer by thoroughly scrubbing the interior surfaces with a clean, hot water–alkaline solution, such as sodium carbonate or trisodium phosphate, using a solution of 1 pound (0.5 kg) of sodium carbonate or trisodium phosphate to 3 gallons (11 L) of potable water and thoroughly rinsing them with clean, hot, potable water.
1309.7.1 Surface Cleaning. Surfaces shall be cleaned for brazing in accordance with Section 1309.6. [NFPA 99:5.1.10.4.4.2] 1309.7.2 Flux. Flux shall be applied sparingly to minimize contamination of the inside of the tube with flux. The flux shall be applied and worked over the cleaned surfaces to be brazed using a stiff bristle brush to ensure complete coverage and wetting of the surfaces with flux.
[NFPA 99:5.1.10.4.4.3, 5.1.10.4.4.4] 1309.7.3 Short Sections of Copper. Where possible, short sections of copper tube shall be brazed onto the non-copper component, and the interior of the subassembly shall be cleaned of flux prior to installation in the piping system. [NFPA 99:5.1.10.4.4.5] 1309.7.4 Flux-Coated Brazing Rods. On joints DN20 (NPS 3 ⁄4) ( 7 ⁄8 inch O.D.) size and smaller, fluxcoated brazing rods shall be permitted to be used in lieu of applying flux to the surfaces being joined. [NFPA 99:5.1.10.4.4.6]
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸Contents — California Plumbing Code (Title 24, Part 5)
- Chapter 1 — GENERAL CODE PROVISIONS
- Chapter 2 — DEFINITIONS
- Chapter 3 — GENERAL REGULATIONS
- Chapter 4 — PLUMBING FIXTURES AND FIXTURE FITTINGS
- Chapter 5 — WATER HEATERS
- Chapter 6 — WATER SUPPLY AND DISTRIBUTION
- Chapter 7 — SANITARY DRAINAGE
- Chapter 8 — INDIRECT WASTES
- Chapter 9 — VENTS
- Chapter 10 — TRAPS AND INTERCEPTORS
- Chapter 11 — STORM DRAINAGE
- Chapter 12 — FUEL GAS PIPING
▸Chapter 13 — HEALTH CARE FACILITIES AND MEDICAL GAS AND MEDICA…
Overview- 1301.0 General.1301.1 Applicability. This chapter applies to t…
- 1301.2 Where Not Applicable. This chapter does not apply
- 1301.3 Conflict of Requirements. The requirements of
- 1301.4 Terms. Where the terms medical gas or medical support g…
- 1301.5 Where Required. Construction and equipment
- 1301.6 Existing Systems. Only the altered, renovated, or
- 1302.2 Patient Care Spaces. The governing body of the
- 1302.3 Anesthesia. It shall be the responsibility of the gover…
- 1302.4 Wet Procedure Locations. It shall be the responsibility…
- 1303.2 Psychiatric Patient Rooms. Piping and drain
- 1303.3 Locations for Ice Storage. Ice makers or ice storage co…
- 1303.4 Sterilizers and Bedpan Steamers. Sterilizers
- 1303.5 Aspirators. Provisions for aspirators or other watersup…
- 1303.6 Drains. Drains shall be installed on dryers, aftercoole…
- 1303.7 Clinical Sinks. Clinical sinks shall be installed in
- 1303.8 Water Supply for Hospitals. Hospitals shall be
- 1304.0 Medical Gas and Medical Vacuum Piping Sys-
- 1304.2 Manufacturer’s Instructions. The installation of
- 1304.3 Category 2 Piped Medical Gas and MedicalVacuum. Categor…
- 1304.4 Category 3 Piped Medical Gas and MedicalVacuum. Categor…
- 1304.5 Certification of Systems. Certification of medical gas …
- 1304.6 Construction Documents. Before a medical gas
- 1305.2 Minimum Flow Rates. Medical gas and vacuum
- 1305.3 Minimum Station Outlets and Inlets. Station
- 1306.0 Qualifications of Installers.1306.1 General. The instal…
- 1306.2 Brazing. Brazing shall be performed by individuals
- 1306.3 Health Care Organization Personnel. Health
- 1307.2 Examination. Brazers shall be qualified by visual
- 1307.3 Brazing Procedure Specification. The brazing
- 1307.4 Documentation. The brazing procedure qualification reco…
- 1307.5 Procedures. Brazing procedures qualified by a technical…
- 1307.7 Qualifications. Performance qualifications of brazers s…
- 1307.6 Conditions of Acceptance. An employer shall be
- 1308.2 Cleaning. Tubes, valves, fittings, station outlets, and
- 1308.3 Delivery. Each length of tube shall be delivered
- 1308.4 Tubes for Medical Gas Systems. Tubes shall be
- 1308.5 Tubes for Medical Vacuum Systems. Piping for
- 1309.2 Changes in Direction. Positive pressure patient
- 1308.6 Category 3 Systems. Category 3 systems shall
- 1309.3 Medical Vacuum Systems. Vacuum systems shall
- 1309.4 Brazed Joints and Fittings. Fittings shall be
- 1309.5 Tube Ends. Tube ends shall be cut square using a
- 1309.6 Cleaning Procedures. The interior surfaces of
- 1309.7 Brazing Dissimilar Metals. Flux shall only be
- 1309.8 Nitrogen Purge. When brazing, joints shall be continuou…
- 1309.9 Assembling and Heating Brazed Joints. Tube
- 1309.10 Inspection of Brazed Joints. After brazing, the
- 1309.11 Memory Metal Fittings. Memory metal fittings
- 1309.12 Axially Swaged Fittings. Axially swaged, elastic strai…
- 1309.13 Threaded Fittings. Threaded fittings shall meet
- 1309.14 Dielectric Fittings. Dielectric fittings that comply
- 1309.15 Other Types of Fittings. Listed or approved
- 1309.16 Welded Joints. Welded joints for medical gas and
- 1310.2 Required Pipe Sizing. Piping systems shall be
- 1309.17 Welding for Stainless Tube. Stainless tube shall
- 1309.18 Prohibited Joints. The following joints shall be
- 1310.3 Pipe Protection. Piping shall be protected against
- 1310.4 Location of Piping. Piping risers shall be permitted to…
- 1310.5 Pipe Support. Piping shall be supported from the
- 1310.7 Connectors. Hose and flexible connectors, both
- 1310.6 Backfilling and Trenching. The installation procedure f…
- 1310.9 Changes in System Use. Where a positive-pressure medica…
- 1310.10 Breaching or Penetrating Medical Gas Pip-ing. Positive…
- 1310.11 Labeling, Identification and Operating Pres-sure. Colo…
- 1310.8 Prohibited System Interconnections. Two or
- 1311.0 Valves.1311.1 General. New or replacement valves shall …
- 1311.6 Zone Valves. All station outlets/inlets shall be suppli…
- 1311.7 In-Line Shutoff Valves. Optional in-line valves
- 1311.8 Emergency Shutoff Valves. Category 3 systems
- 1311.2 Source Valves. A shutoff valve shall be placed at
- 1311.3 Main Line Valve. A shutoff valve shall be provided
- 1311.4 Riser Valves. Each riser supplied from the main line
- 1311.5 Service Valves. Service valves shall be installed to
- 1311.9 Valves for Future Connections. Future connection valves…
- 1311.10 Identification of Shutoff Valves. Shutoff valves
- 1312.0 Central Supply Systems.1312.1 Permitted Locations for M…
- 1312.2 Materials. Materials used in central supply systems
- 1312.3 Pressure-Relief Valve Requirements. Central
- 1313.0 Medical Air Supply Systems.1313.1 Quality of Medical Ai…
- 1313.3 Category 2 Medical Air Supply Systems. Category 2 syste…
- 1313.2 Medical Air Compressors. Medical air compressors shall …
- 1313.4 Category 3 Systems. Category 3 dental air compressor su…
- 1313.5 Air Sources. Air sources for medical air compressors sh…
- 1313.6 Air Intakes. Compressor intake piping shall be permitte…
- 1314.2 Medical-Surgical Vacuum Sources. Medicalsurgical vacuum…
- 1313.7 Medical Air Receivers. Receivers for medical air
- 1314.3 Vacuum Pumps. Additional pumps shall automatically acti…
- 1314.4 Vacuum Receivers. Receivers for vacuum shall
- 1315.2 Pressure Relief Valves. All pressure relief valves
- 1314.5 Vacuum Source Exhausts. The medical-surgical
- 1315.3 Pressure and Vacuum Indicator Locations. Pressure/vacuu…
- 1316.2 Required Valves. Each station outlet shall consist
- 1316.3 Post Installation. After installation of the piping,
- 1316.4 Identification. Station outlets and inlets shall be
- 1317.0 Warning Systems.1317.1 Category 1. All master, area, an…
- 1317.2 Category 2 Systems. Warning systems associated
- 1317.3 Category 3 Systems. Category 3 warning systems
- 1318.3 Reports. The inspection and testing reports shall be
- 1318.4 Initial Piping Blowdown. Piping in medical gas
- 1318.5 Initial Pressure Tests – Medical Gas and Vac-uum System…
- 1317.4 Components. Functioning of alarm components
- 1318.2 Breached Systems. All systems that are breached
- 1318.6 Initial Pressure Test - Category 3 Copper PipingSystems…
- 1318.7 Initial Leak Test – Category 3 Plastic VacuumPiping Sys…
- 1318.8 Cross-Connection Tests – Medical Gas andVacuum Systems.…
- 1318.9 Standing Pressure Tests – for Positive Pres-sure Medica…
- 1318.10 Standing Pressure Tests – Medical VacuumPiping Systems…
- 1318.11 Standing Pressure Tests – for Category 3
- 1318.12 Medical Gas Piping System Purge Tests. The
- 1318.13 Category 3 Dental Air and Nitrogen Supply
- 1318.14 Operational Pressure Test. Operational pressure tests …
- 1318.15 Medical Gas Concentration Test. After purging
- 1319.2 Certification Tests. Certification tests, verified and
- 1319.3 Report Items. A report that includes the specific
- 1318.16 System Verification. Verification tests shall be
- Chapter 14 — FIRESTOP PROTECTION
- Chapter 15 — ALTERNATE WATER SOURCES FOR NONPOTABLE APPLICATIONS
- Chapter 16 — NONPOTABLE RAINWATER CATCHMENT SYSTEMS
- Chapter 17 — REFERENCED STANDARDS
- Appendix A — RECOMMENDED RULES FOR SIZING THE WATER SUPPLY SYS…
- Appendix B — EXPLANATORY NOTES ON COMBINATION WASTE AND VENT S…
- Appendix C — ALTERNATE PLUMBING SYSTEMS
- Appendix D — SIZING STORM WATER DRAINAGE SYSTEMS
- Appendix E — MANUFACTURED/MOBILE HOME PARKS AND RECREATIONAL V…
- Appendix F — FIREFIGHTER BREATHING AIR REPLENISHMENT SYSTEMS
- Appendix G — SIZING OF VENTING SYSTEMS
- Appendix H — PRIVATE SEWAGE DISPOSAL SYSTEMS
- Appendix I — INSTALLATION STANDARD FOR PEX TUBING SYSTEMS FOR …
- Appendix J — COMBINATION OF INDOOR AND OUTDOOR COMBUSTION AND …
- Appendix K — POTABLE RAINWATER CATCHMENT SYSTEMS
- Appendix L — SUSTAINABLE PRACTICES
- Appendix M — PEAK WATER DEMAND CALCULATOR