15188. FOCUSED EIR FOR POLLUTION CONTROL EQUIPMENT
CEQA Statute and Guidelines (2025 consolidated text) · 2026 edition · updated 2026-10-05 · California
This section applies to projects consisting solely of the installation of pollution control equipment and other components necessary to the installation of that equipment which are undertaken for the purpose of complying with a rule or regulation which was the subject of an environmental analysis as described in Section 15187.
(a) The lead agency for the compliance project may prepare a focused EIR to analyze the effects of that project when the following occur:
(1) the agency which promulgated the rule or regulation certified an EIR on that rule or regulation, or reviewed it pursuant to an environmental analysis prepared under a certified regulatory program and, in either case, the review included an assessment of growth inducing impacts and cumulative impacts of, and alternatives to, the project;
(2) the focused EIR for the compliance project is certified within five years of the certified EIR or environmental analysis required by subdivision (a)(1) ; and
(3) the EIR prepared in connection with the adoption of the rule or regulation need not be updated through the preparation of a subsequent EIR or supplemental EIR pursuant to section 15162 or section 15163.
(b) The discussion of significant environmental effects in the focused EIR shall be limited to projectspecific, potentially significant effects which were not discussed in the environmental analysis required under Section 15187. No discussion of growth-inducing or cumulative impacts is required. Discussion of alternatives shall be limited to alternative means of compliance, if any, with the rule or regulation.
Note: Authority: Section 21083, Public Resources Code; Reference: Section 21159.1, Public Resources Code.