Skip to content

15108. COMPLETION AND CERTIFICATION OF EIR

CEQA Statute and Guidelines (2025 consolidated text) · 2026 edition · updated 2026-10-05 · California

With a private project, the Lead Agency shall complete and certify the final EIR as provided in Section 15090 within one year after the date when the Lead Agency accepted the application as complete. Lead Agency procedures may provide that the one-year time limit may be extended once for a period of not more than 90 days upon consent of the Lead Agency and the applicant.

Note: Authority cited: Section 21083, Public Resources Code; Reference: Sections 21100.2 and 21151.5, Public Resources Code; Government Code Section 65950.

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — CEQA Statute and Guidelines (2025 consolidated text)

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.