15102. INITIAL STUDY

CEQA Statute and Guidelines (2025 consolidated text) · 2026 edition · updated 2026-10-05 · California

The Lead Agency shall determine within 30 days after accepting an application as complete whether it intends to prepare an EIR or a Negative Declaration or use a previously prepared EIR or Negative Declaration except as provided in Section 15111. The 30 day period may be extended 15 days upon the consent of the lead agency and the project applicant.

235

Association of Environmental Professionals 2025

CEQA Guidelines

Note: Authority cited: Section 21083, Public Resources Code; Reference: Section 21080.2, Public Resources Code.