15109. SUSPENSION OF TIME PERIODS
CEQA Statute and Guidelines (2025 consolidated text) · 2026 edition · updated 2026-10-05 · California
An unreasonable delay by an applicant in meeting requests by the Lead Agency necessary for the preparation of a Negative Declaration or an EIR shall suspend the running of the time periods described in Sections 15107 and 15108 for the period of the unreasonable delay. Alternatively, an agency may disapprove a project application where there is unreasonable delay in meeting requests. The agency may allow a renewed application to start at the same point in the process where the application was when it was disapproved.
Note: Authority cited: Section 21083, Public Resources Code; Reference: Sections 21100.2 and 21151.5, Public Resources Code; Carmel Valley View, Ltd. v. Maggini , 91 Cal. App. 3d 318.