1114.2 Design Requirements. Flaring devices shall be
California Mechanical Code (Title 24, Part 4) · 2022 edition · updated 2026-09-10 · California
Italicized text is a California amendment to the model code, as printed in the official publication.
designed to incinerate the entire discharge. The products of refrigerant incineration shall not pose health or environmental hazards. Incineration shall be automatic upon initiation of discharge, shall be designed to prevent blow-back, and shall not expose structures or materials to the threat of fire. Standby fuel, such as LP-Gas, and standby power shall have the capacity to operate for one and a half times the required time for complete incineration of the charge.
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸Contents — California Mechanical Code (Title 24, Part 4)
- Chapter 1 — GENERAL CODE PROVISIONS
- Chapter 2 — DEFINITIONS
- Chapter 3 — GENERAL REGULATIONS
- Chapter 4 — VENTILATION AIR
- Chapter 5 — EXHAUST SYSTEMS
- Chapter 6 — DUCT SYSTEMS
- Chapter 7 — COMBUSTION AIR
- Chapter 8 — CHIMNEYS AND VENTS
- Chapter 9 — INSTALLATION OF SPECIFIC APPLIANCES
- Chapter 10 — BOILERS AND PRESSURE VESSELS
▸Chapter 11 — REFRIGERATION
Overview- 1101.1 Applicability. Part I governs the design, installation,
- 1101.2 Equipment. Equipment for refrigerant recovery,
- 1102.1 General. Refrigeration systems using a refrigerant
- 1102.2 Ammonia Refrigeration Systems. Refrigeration
- 1102.3 Refrigerants. The refrigerant used shall be of a type
- 1103.1 Classification of Refrigerants. Refrigerants shall
- 1103.2 Classification of Refrigeration Systems.
- 1103.3 Higher Flammability Refrigerants. Group A3
- 1104.1 System Selection. Refrigeration systems shall be
- 1104.2 Refrigerant Concentration Limit. The concentration of r…
- 1104.3 Institutional Occupancies. The RCL value
- 1104.4 Industrial Occupancies and Refrigerated
- 1104.5 Flammable Refrigerants. The total of Group A2,
- 1104.6 Applications for Human Comfort and for Non-
- 1104.7 Refrigerant Type and Purity. Refrigerants shall
- 1104.8 Changing Refrigerants. A change in the type of
- 1105.1 Human Comfort. Cooling systems used for human
- 1105.2 Supports and Anchorage. Supports and anchorage for refr…
- 1105.3 Access. An unobstructed readily accessible opening and …
- 1105.4 Illumination and Service Receptacles. In addition to th…
- 1105.5 Ventilation of Rooms Containing Condensing
- 1105.6 Prohibited Locations. Refrigeration systems or
- 1105.7 Condensate. Condensate from air-cooling coils
- 1105.8 Defrost. Where defrost cycles are required for portions…
- 1105.9 Overflows. Where condensate or defrost liquids are
- 1105.10 Condensate, Defrost, and Overflow Dis-
- 1105.11 Refrigerant Port Protection. Air conditioning
- 1105.12 Storage. Refrigerants and refrigerant oils not
- 1106.1 Where Required. Refrigeration systems shall be
- 1106.2 Refrigeration Machinery Room, General
- 1106.4 Natural Ventilation. Where a refrigerating system
- 1106.5 Combustion Air. No open flames that use combustion air …
- 1106.6 Airflow. There shall be no airflow to or from an occupi…
- 1106.7 Ventilation Intake. Makeup air intakes to replace
- 1106.3 Normal Operation. A part of the refrigeration
- 1106.8 Maximum Temperature. Ventilation or mechanical cooling …
- 1106.9 Refrigerant Parts in Air Duct. Joints and refrigerant-c…
- 1106.10 Dimensions. Refrigeration machinery rooms shall
- 1106.11 Restricted Access. Access to the refrigeration
- 1106.12 Exits. Exits shall comply with the building code for
- 1107.1 General. In cases specified in the rules of Section
- 1108.1 General. Equipment, piping, ducts, vents, or similar
- 1108.2 Electrical. Electrical equipment and installations
- 1108.3 Emergency Shut-off. A clearly identified emergency shut…
- 1108.4 Installation, Maintenance, and Testing. Detection and a…
- 1108.5 Emergency Pressure Control System. Where
- 1109.1 Materials. Materials used in the construction and
- 1109.2 Joints. Iron or steel pipe joints shall be of approved
- 1109.3 Penetration of Piping. Refrigerant piping shall not
- 1109.4 Location of Refrigeration Piping. Refrigerant
- 1109.5 Underground Piping. Refrigerant piping placed
- 1109.6 Support. In addition to the requirements of Section
- 1109.7 Pipe Enclosure. Refrigerant piping and tubing
- 1109.8 Visual Inspection. Refrigerant piping and joints
- 1109.9 Condensation. Piping and fittings that convey
- 1109.10 Identification. Piping shall be in accordance with
- 1110.1 More than 6.6 Pounds of Refrigerant. Systems
- 1110.2 More than 110 Pounds of Refrigerant. Systems
- 1110.3 Support. Stop valves installed in copper refrigerant
- 1110.4 Access. Stop valves required by Section 1110.0 shall
- 1110.5 Identification. Stop valves shall be identified by tagg…
- 1111.1 Where Required. Pressure-limiting devices complying wit…
- 1111.2 Setting. Pressure limiting devices shall be set in
- 1111.3 Location. Stop valves shall not be installed between
- 1111.4 Emergency Stop. Activation of a pressure-limiting
- 1112.1 General. Refrigeration systems shall be protected by
- 1112.2 Positive Displacement Compressor. A positive
- 1112.3 Liquid-Containing Portions of Systems. Liquid-containin…
- 1112.4 Evaporators. Heat exchanger coils located downstream, o…
- 1112.5 Hydrostatic Expansion. Pressure rise resulting
- 1112.6 Actuation. Pressure-relief devices shall be directpress…
- 1112.7 Stop Valves Prohibited. Stop valves shall not be
- 1112.8 Location. Pressure-relief devices shall be connected
- 1112.9 Materials. The seats and discs of pressure-relief
- 1112.10 Pressure-Relief Device Settings. Pressurerelief valves…
- 1112.11 Discharge from Pressure-Relief Devices.
- 1112.12 Discharge Piping. The piping used for pressurerelief d…
- 1112.13 Rating of Pressure-Relief Device. The rated
- 1112.14 Rating of Rupture Members and Fusible
- 1113.1 General. Pressure vessels shall be provided with
- 1113.2 Type of Protection. Pressure vessels with an internal g…
- 1113.3 Discharging into Lowside of System. For pressure-relief…
- 1113.4 Parallel Pressure-Relief Devices. Two or more
- 1113.5 Discharge Capacity. The minimum required discharge capa…
- 1113.6 Three-Way Valve. Pressure vessels of 10 cubic feet
- 1114.1 General. Systems containing other than Group A1 or
- 1114.2 Design Requirements. Flaring devices shall be
- 1114.3 Testing. Flaring systems shall be tested to demonstrate…
- 1115.1 General. In addition to labels required elsewhere in
- 1115.2 Volume and Type. A condenser, receiver, absorber,
- 1115.3 Permanent Sign. In a refrigeration machinery room
- 1115.4 Marking of Pressure-Relief Devices. Pressurerelief valv…
- 1116.1 Factory Tests. Refrigerant-containing parts of unit
- 1116.2 Field Tests. Refrigerant-containing parts of a system t…
- 1116.3 Test Gases. Tests shall be performed with dry nitrogen …
- 1116.4 Declaration. A dated declaration of test shall be provi…
- 1116.5 Brine Systems. Brine-containing portions of a system sh…
- 1117.1 Inside Dimensions 6 Inches or Less. Pressure
- 1117.2 Inside Dimensions More than 6 Inches. Pressure vessels …
- 1117.3 Pressure Vessels for 15 psig or Less. Pressure
- 1118.1 General. Refrigeration systems shall be operated and
- 1119.1 Applicability. Cooling towers, evaporative condensers, …
- 1120.1 General. Cooling towers, evaporative condensers,
- 1121.1 General. Drains, overflows, and blow-down provisions sh…
- 1122.1 General. Chemical treatment systems shall comply
- 1122.2 Automated Control of Cycles of Concentra-
- 1123.1 General. Cooling towers, evaporative condensers,
- 1124.1 General. Electrical systems shall be in accordance
- 1125.1 General. Equipment containing refrigerants as a part
- 1126.1 General. Cooling towers, evaporative condensers,
- Chapter 12 — HYDRONICS
- Chapter 13 — FUEL GAS PIPING
- Chapter 14 — PROCESS PIPING
- Chapter 15 — SOLAR ENERGY SYSTEMS
- Chapter 16 — STATIONARY POWER PLANTS
- Chapter 17 — REFERENCED STANDARDS
- Appendix A — RESIDENTIAL PLAN EXAMINER REVIEW FORM FOR HVAC SY…
- Appendix B — PROCEDURES TO BE FOLLOWED TO PLACE GAS EQUIPMENT …
- Appendix C — INSTALLATION AND TESTING OF OIL (LIQUID) FUEL-FIR…
- Appendix D — FUEL SUPPLY: MANUFACTURED/MOBILE HOME PARKS AND R…
- Appendix E — SUSTAINABLE PRACTICES
- Appendix F — GEOTHERMAL ENERGY SYSTEMS
- Appendix G — SIZING OF VENTING SYSTEMS AND OUTDOOR COMBUSTION …
- Appendix H — EXAMPLE CALCULATION OF OUTDOOR AIR RATE