Chapter 17 — GEOTHERMAL ENERGY SYSTEMS AND AMBIENT TEMPERATURE LOOPS
1710.6 Vertical Bores. Vertical bores shall be drilled to a
California Mechanical Code (Title 24, Part 4) · 2025 edition · updated 2026-09-10 · California
Italicized text is a California amendment to the model code, as printed in the official publication.
depth to provide complete insertion of the u-bend pipe to its specified depth. The borehole diameter shall be sized for the installation and placement of the heat exchange u-bend and the tremie used to place the grouting material. ANSI/ CSA/IGSHPA C448 shall be used for vertical loop depth and borehole diameter sizing guidance. The u-bend joint and pipe shall be visually inspected for integrity in accordance with the manufacturer’s installation instructions. The u-bend joint and pipe shall be pressurized to not less than 100 psi (689 kPa), not to exceed the pressure rating of the pipe at the test temperature, for 1 hour to check for leaks before insertion into the borehole.
1710.6.1 Backfill. Bentonite grout and thermallyenhanced bentonite grout, where used to seal and backfill each borehole, shall comply with NSF/ANSI/CAN 60. Boreholes shall be backfilled in accordance with the Authority Having Jurisdiction.
1710.6.2 U-Bends and Headers. Headers, u-bends and ground loop pipes shall be pressure-tested in accordance with ANSI/ CSA/IGSHPA C448, or as required by the Authority Having Jurisdiction. Before testing, heat fusion joints shall be cooled to ambient temperature. Mechanical joints shall be completely assembled. Flushing and purging to remove air and debris shall be completed before testing. The assembly shall be filled with water (or water/antifreeze solution) and purged at a minimum flow rate of 2 feet per second (0.6 m/s) to remove air, but not more than the maximum flow velocity recommended by the pipe and fittings manufacturer to remove debris.
1710.6.2.1 Test Pressure. The maximum test pressure shall be 1.5 times the system design pressure, as determined by Section 1710.6.2.3, or Section 1710.6.2.4, not to exceed 100 psi (689 kPa). Components or devices with lower pressure-ratings than the pipe shall be protected from excessive pressure during testing by removing or isolating from the test section.
Exception: Where lower pressure-rated components or devices cannot be removed or isolated from the test section, the maximum test pressure shall not exceed the pressure rating of the component or device.
1710.6.2.2 Testing Procedure. The test section and the test liquid shall be at the same temperature. The test section shall be filled with liquid and purged of air. The test section shall be brought to the specified test pressure. Test pressure shall be maintained for 4 hours, with additional fluid added as needed. The test pressure shall be reduced by 10 psi (69 kPa) and monitored for 1 hour with no addition of pres
sure or additional fluid. A passing test is indicated where after a period of 1 hour no visual leakage is observed, and pressure remains equal to or greater than 95 percent of the original pressure.
1710.6.2.3 Calculation of Static Pressure (Water). For water, the static pressure applied shall be equivalent to 0.43 psig (2.96 kPa) per foot (305 mm) of elevation.
1710.6.2.4 Calculation of Static Pressure (Other Fluids). For fluids of different density, the static pressure shall be calculated using the density of the system fluid.
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸Contents — California Mechanical Code (Title 24, Part 4)
- Chapter 1 — GENERAL CODE PROVISIONS
- Chapter 2 — DEFINITIONS
- Chapter 3 — GENERAL REGULATIONS
- Chapter 4 — VENTILATION AIR
- Chapter 5 — EXHAUST SYSTEMS
- Chapter 6 — DUCT SYSTEMS
- Chapter 7 — COMBUSTION AIR
- Chapter 8 — CHIMNEYS AND VENTS
- Chapter 9 — INSTALLATION OF SPECIFIC APPLIANCES
- Chapter 10 — BOILERS AND PRESSURE VESSELS
- Chapter 11 — REFRIGERATION
- Chapter 12 — HYDRONICS
- Chapter 13 — FUEL GAS PIPING
- Chapter 14 — PROCESS PIPING
- Chapter 15 — SOLAR ENERGY SYSTEMS
- Chapter 16 — STATIONARY POWER PLANTS
▸Chapter 17 — GEOTHERMAL ENERGY SYSTEMS AND AMBIENT TEMPERATURE…
Overview- 1701.1 Applicability. Part I of this chapter shall apply to
- 1701.2 Construction Documents. The construction doc
- 1701.3 Site Survey. A site survey shall be conducted prior
- 1701.4 Used Materials. The installation of used pipe, fittings…
- 1701.5 Contact with Building Material. A ground source
- 1701.6 Strains and Stresses. Piping shall be installed so
- 1701.7 Flood Hazard. Piping located in a flood hazard area
- 1701.8 Pipe Support. Pipe shall be supported in accordance wit…
- 1701.9 Velocities. Ground source heat pump ground-loop
- 1701.10 Chemical Compatibility. Antifreeze and other
- 1701.11 Heat Transfer Fluid. The heat transfer fluid shall
- 1702.1 General. The potable water supply connected to a
- 1703.3 Fittings. For water-based systems, fittings for
- 1703.4 Underground Piping and Submerged Materi-
- 1703.1 Ground-Heat Exchanger Design. The groundheat exchanger …
- 1703.2 Piping and Tubing Materials Standards. For
- 1703.5 Indoor Piping. Indoor piping, fittings, and accessories…
- 1704.1 Heat Pump Distribution System. The heat pump
- 1704.2 Circulating Pumps. The circulating pump shall be
- 1705.1 Where Required. Shutoff valves shall be installed
- 1705.2 Heat Exchangers. Shutoff valves shall be installed
- 1705.3 Central Systems. Shutoff valves shall be installed
- 1705.4 Pressure Vessels. Shutoff valves shall be installed
- 1705.5 Pressure-Reducing Valves. Shutoff valves shall
- 1705.6 Equipment and Appliances. Shutoff valves shall
- 1705.7 Expansion Tanks. Shutoff valves shall be installed
- 1705.8 Reduced Pressure. A pressure relief valve shall
- 1706.1 General. Heat pumps shall be in compliance with
- 1706.2 Heat Exchangers. Heat exchangers used for heat
- 1706.3 Heat-Transfer Medium. The heat-transfer medium
- 1706.4 Insulation. The temperature of surfaces within
- 1707.1 Prior to Construction. Documents for permits
- 1707.2 Equipment, Accessories, Components, and
- 1707.3 Construction Documents. The construction documents for …
- 1707.4 Site Survey Requirements. The site survey shall
- 1707.5 Subsurface Investigation. A subsurface investigation sh…
- 1707.6 Subsurface Conditions. The water well logs and
- 1707.7 Ground-Heat Exchanger Installation Prac-
- 1707.13 Steel Nail Plates. Steel nail plates shall be
- 1707.14 Exterior Piping Protection. Exterior piping shall
- 1707.15 Heat Pump and Distribution System Instal-
- 1707.16 Pressurizing During Installation. Ground
- 1707.17 Horizontal Geothermal Piping - Materials
- 1707.18 Trenches, Excavation, and Backfill. Excavation
- 1707.8 Trenching, Excavation, and Backfill. Prior to
- 1707.9 Trenches, Tunneling, and Driving. Trenches shall
- 1707.10 Excavations and Open Trenches. Excavations
- 1707.11 Protection of Piping, Materials, and Struc-
- 1707.12 Sleeves. In exterior walls, annular space between
- 1708.1 General. The following requirements shall be verified p…
- 1708.2 Operation and Maintenance Manual. An operation and main…
- 1708.3 Labeling and Marking. Ground source heat pump
- 1708.4 Documentation. The ground source heat pump system as-bu…
- 1708.5 Maintenance. The periodic maintenance required,
- 1708.6 Records. The ground source heat pump system constructio…
- 1708.7 System Start-Up. System start-up shall be in accordance…
- 1708.8 Contaminants. Particulate contaminants shall be
- 1709.1 General. Decommissioning of geothermal systems
- 1710.1 Applicability. Part II of this chapter shall apply to
- 1710.2 Piping and Tubing. Piping and tubing for closedloop sys…
- 1710.3 Borehole Piping and Tubing. Borehole piping or
- 1710.4 Underground Fittings. Underground fittings for
- 1710.5 Verification. For closed-loop systems, the system
- 1710.6 Vertical Bores. Vertical bores shall be drilled to a
- 1711.1 Testing. Pressure-testing of the ground-heat
- 1711.2 Individual Loop Pressure Testing. Individual
- 1711.3 Field Pressure Testing – Final. The ground-heat
- 1711.4 Field Flow Testing – Final. Final field flow testing
- 1712.1 Applicability. Part III of this chapter shall apply to
- 1712.2 Test Wells. Test wells drilled to investigate subsurfac…
- 1712.3 Installation of Water Wells. Water supply,
- 1712.4 Setbacks. Open-loop ground-heat exchangers shall
- 1713.1 General. The installation and use of water wells
- 1713.2 Open-Loop Water Well Drilling Logs. The water
- 1713.3 Design Considerations. A groundwater heat
- 1713.4 Water Wells and Injection Wells. Water wells
- 1713.5 Testing and Sampling. Pumping tests and water
- 1713.6 Disinfection. Water wells shall be disinfected upon
- 1714.1 Pumping Test. Water supply wells and injection
- 1714.2 Retesting. Where sediment is present, the problem
- 1714.3 Variable Rate Pump Test. The operating conditions of th…
- 1714.4 Constant Rate Pump Test. The sustainable well
- 1714.5 Water Level Monitoring. Water levels shall be
- 1714.6 Injection Wells. Injection testing shall be performed
- 1714.7 Re-Injected Water. The water quality of re-injected
- 1715.1 General. The installation and use of Direct
- 1715.2 Applicability. Part IV of this chapter shall apply to
- 1715.3 DX Systems. Copper pipe and tubing installed for
- 1715.4 DX System Testing. For direct exchange (DX) systems, ea…
- 1715.5 Indoor Piping. For DX systems, joints shall be
- 1715.6 On Site Storage. For DX systems, copper piping
- 1715.7 System Start-Up. DX system start-up shall be in
- 1715.8 DX Piping. DX Piping should be installed in accordance …
- 1716.1 General. An Ambient Temperature Loop (ATL) distributed …
- 1716.2 Permitting. Permits required for the installation and
- 1716.3 Ambient Loop Temperature Range. The operating loop temp…
- 1716.4 Shutoff Valve. An automatic shutoff valve shall be
- 1716.5 Bypass. The ATL distributed energy system shall
- 1716.6 Metering. Where meters are required by the system
- 1717.1 Thermal Resources. The ambient temperature loop
- 1717.2 District Load Profiles. The district load profile of
- Chapter 18 — REFERENCED STANDARDS
- Appendix A — RESIDENTIAL PLAN EXAMINER REVIEW FORM FOR HVAC SY…
- Appendix B — PROCEDURES TO BE FOLLOWED TO PLACE GAS EQUIPMENT …
- Appendix C — INSTALLATION AND TESTING OF OIL (LIQUID) FUEL-FIR…
- Appendix D — FUEL SUPPLY: MANUFACTURED/MOBILE HOME PARKS AND R…
- Appendix E — SUSTAINABLE PRACTICES
- Appendix F — SIZING OF VENTING SYSTEMS AND OUTDOOR COMBUSTION …
- Appendix G — EXAMPLE CALCULATION OF OUTDOOR AIR RATE
- Appendix H — PROFESSIONAL QUALIFICATIONS
- Appendix I — INDOOR HORTICULTURAL FACILITIES
- Appendix J — CLEAN AIR DELIVERY