Chapter 1 — GENERAL CODE PROVISIONS
104.2 Exempt Work. A permit shall not be required for the
California Mechanical Code (Title 24, Part 4) · 2019 edition · updated 2026-09-10 · California
Italicized text is a California amendment to the model code, as printed in the official publication.
following: (1) A portable heating appliance, portable ventilating equip ment, a portable cooling unit, or a portable evaporative
(1) A portable heating appliance, portable ventilating equip ment, a portable cooling unit, or a portable evaporative cooler. (2) A closed system of steam, hot, or chilled water piping
within heating or cooling equipment regulated by this
(2) A closed system of steam, hot, or chilled water piping
within heating or cooling equipment regulated by this code. (3) Replacement of a component part that does not alter its
original approval and is in accordance with other appli
The issuance of a permit upon construction documents shall not prevent the Authority Having Jurisdiction from thereafter requiring the correction of errors in said construction documents or from preventing construction operations being carried on thereunder where in violation of this code or of other pertinent ordinance or from revoking a certificate of approval where issued in error.
(3) Replacement of a component part that does not alter its
original approval and is in accordance with other applicable requirements of this code. (4) Refrigerating equipment that is part of the equipment for
which a permit has been issued pursuant to the require
103.3.1 Licensing. Provision for licensing shall be determined by the Authority Having Jurisdiction.
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸Contents — California Mechanical Code (Title 24, Part 4)
▸Chapter 1 — GENERAL CODE PROVISIONS
Overview- 101.1 Title.101.0 General. This document shall be known as the…
- 101.2 Scope. The provisions of this code shall apply to the
- 101.3 Purpose. This code is an ordinance providing minimum req…
- 101.4 Unconstitutional. Where a section, subsection, sentence,…
- 101.5 Validity. Where a provision of this code, or the applica…
- 102.1 Conflicts Between Codes.102.0 Applicability. Where the r…
- 102.2 Existing Installations. Mechanical systems lawfully in e…
- 102.3 Maintenance. Mechanical systems, materials, and
- 102.4 Additions, Alterations, Renovations, orRepairs. Addition…
- 102.5 Health and Safety. Where compliance with the provisions …
- 102.6 Changes in Building Occupancy. Mechanical
- 102.7 Moved Structures. Parts of the mechanical system of
- 102.8 Appendices. The provisions in the appendices are
- 103.0 Duties and Powers of the Authority Having
- 103.2 Liability. The Authority Having Jurisdiction charged
- 103.3 Applications and Permits. The Authority Having
- 104.1 Permits Required. 104.0 Permits. It shall be unlawful fo…
- 104.2 Exempt Work. A permit shall not be required for the
- 103.4 Right of Entry. Where it is necessary to make an
- 104.3 Application for Permit. To obtain a permit, the
- 104.4 Permit Issuance. The application, construction documents…
- 105.2 Required Inspections. New mechanical system
- 104.5 Fees. Fees shall be assessed in accordance with the
- 105.4 Connection to Service Utilities. No person shall
- 106.2 Notices of Correction or Violation. Notices of
- 106.3 Penalties. A person, firm, or corporation violating a
- 106.4 Stop Orders. Where work is being done contrary to
- 105.3 Testing of Systems. Mechanical systems shall be
- 106.6 Authority to Condemn. Where the Authority Having Jurisdi…
- 107.0 Board of Appeals.107.1 General. In order to hear and dec…
- 107.2 Limitations of Authority. The Board of Appeals
- Chapter 2 — DEFINITIONS
- Chapter 3 — GENERAL REGULATIONS
- Chapter 4 — VENTILATION AIR
- Chapter 5 — EXHAUST SYSTEMS
- Chapter 6 — DUCT SYSTEMS
- Chapter 7 — COMBUSTION AIR
- Chapter 8 — CHIMNEYS AND VENTS
- Chapter 9 — INSTALLATION OF SPECIFIC APPLIANCES
- Chapter 10 — BOILERS AND PRESSURE VESSELS
- Chapter 11 — REFRIGERATION
- Chapter 12 — HYDRONICS
- Chapter 13 — FUEL GAS PIPING
- Chapter 14 — PROCESS PIPING
- Chapter 15 — SOLAR ENERGY SYSTEMS
- Chapter 16 — STATIONARY POWER PLANTS
- Chapter 17 — REFERENCED STANDARDS
- Appendix A — RESIDENTIAL PLAN EXAMINER REVIEW FORM FOR HVAC SY…
- Appendix B — PROCEDURES TO BE FOLLOWED TO PLACE GAS EQUIPMENT …
- Appendix C — INSTALLATION AND TESTING OF OIL (LIQUID) FUEL-FIR…
- Appendix D — FUEL SUPPLY: MANUFACTURED/MOBILE HOME PARKS AND R…
- Appendix E — SUSTAINABLE PRACTICES
- Appendix F — SIZING OF VENTING SYSTEMS AND OUTDOOR COMBUSTION …
- Appendix G — EXAMPLE CALCULATION OF OUTDOOR AIR RATE