Chapter 3 — PROVISIONS FOR ALL COMPLIANCE METHODS

Section 319

California Existing Building Code (Title 24, Part 10) · 2022 edition · updated 2026-09-10 · California

Italicized text is a California amendment to the model code, as printed in the official publication.

SEISMIC CRITERIA SELECTION

FOR EXISTING BUILDINGS

319.1 Basis for evaluation and design. This section deter-

mines what technical approach is to be used for the seismic evaluation and design for existing buildings. For those build- ings or portions of buildings for which Section 317 requires action, the procedures and limitations for the evaluation of existing buildings and design of retrofit systems and/or repair thereof shall be implemented in accordance with this section.

One of the following approaches must be used:

1. Method A of Section 320;

2. Method B of Section 321, with independent review of a peer reviewer as required in Section 322; or

3. For state-owned buildings only, the use of one of the specific procedures listed in Section 319.1.1. When Method B is chosen it must be approved by the building official, and, where applicable, by the peer reviewer. All referenced standards in ASCE 41 shall be replaced by referenced standards listed in Chapter 35 of the California Building Code.

Exceptions:

1. [BSC] For buildings constructed to the require- ments of California Building Code, 2016 or later edition, as adopted by the governing jurisdiction, that code is permitted to be used in place of those specified in Section 319.1.

2. [DSA-SS & DSA-SS/CC] For the conversion of nonconforming buildings to conforming school buildings in accordance with Section 4-307 of the California Administrative Code, nonconforming buildings constructed to the requirements of Cal- ifornia Building Code, 2016 or later edition, that code as it was adopted by the governing jurisdic- tion is permitted to be used in place of those spec- ified in Section 319.1 provided the building complies with Seismic Design Category D or higher. 319.1.1 Specific procedures. [BSC] For state-owned buildings, the following specific procedures located in Appendix A may be used, without peer review, for their respective types of construction to comply with the seismic performance requirements for Risk Category I, II or III buildings:

1. Seismic Strengthening Provisions for Unreinforced Masonry Bearing Wall Buildings (Chapter A1).

2. Earthquake Hazard Reduction in Existing Rein- forced Concrete and Reinforced Masonry Wall Buildings with Flexible Diaphragms (Chapter A2).

319.1.2 When a design project is begun under Method B the selection of the peer reviewer is subject to the approval of the building official. Following approval by the peer reviewer, the seismic criteria for the project and the planned evaluation provisions must be approved by the

PROVISIONS FOR ALL COMPLIANCE METHODS

used, the project must have project peer review as prescribed in Section 322.

Get a plain-English answer with a citation back to this text.

Ask AI about this code
Contents — California Existing Building Code (Title 24, Part 10)

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.