CALGreen’s voluntary tiers (Appendix A4/A5/A6) let jurisdictions or owners adopt Tier 1 or Tier 2 performance paths—Tier 1 follows Savings By Design procedures and Tier 2 requires at least a 15% improvement plus specified prerequisites and electives.
Last reviewed: July 6, 2026
Overview
CALGreen’s voluntary tiers provide an optional, higher-performance path above the mandatory green building provisions—intended for jurisdictions or owners that want to push energy, water, materials and indoor-environment performance beyond the baseline code. The voluntary tier framework is introduced in Chapter 3 (see §304 Voluntary Tiers) and the specific CALGreen Tier 1 and Tier 2 requirements are set out in §305 and Appendix A5 (Div. A5.6: A5.601–A5.602) for nonresidential projects; residential tiers appear in Appendix A4 (Div. A4.6) and health‑facility voluntary standards in Appendix A6 (Div. A6.2).
Practically, Tier 1 and Tier 2 pair energy performance targets with a package of prerequisite and elective measures across planning/design, energy, water, materials and environmental quality. For example, energy performance for CALGreen Tier 1 requires compliance with the latest “Savings By Design, Healthcare Modeling Procedures,” and Tier 2 requires exceeding that same modeling benchmark by at least 15 percent; these provisions are explicitly noted for health facilities and in the Tier sections.
The appendices include verification checklists and the detailed elective/prerequisite lists used to document compliance (see Appendix A5.602 and the Tier 1/Tier 2 checklists). Voluntary tiers are optional unless a local government elects to adopt them (see §304 and cross‑reference to local amendment procedures at §101.7).
In this section
Code references
Grounded in the retrieved California Green Building Standards Code (CALGreen) — click a citation to read the verbatim passage:
CALGreen § 304.1 High relevance — show source text
SECTION 304—VOLUNTARY TIERS
304.1 Purpose. Voluntary tiers are intended to further encourage building practices that improve public health, safety and general welfare by promoting the use of building concepts which minimize the building’s impact on the environment and promote a more sustainable design.
304.1.1 Tiers. The provisions of Divisions A4.6 and A5.6 outline means, in the form of voluntary tiers, for achieving enhanced construction levels by incorporating additional measures for residential and nonresidential new construction. Voluntary tiers may be adopted by local governments and, when adopted, enforced by local enforcing agencies. Buildings complying with tiers specified for each occupancy contain additional prerequisite and elective green building measures necessary to meet the threshold of each tier. See Section 101.7 of this code for procedures and requirements related to local amendments, additions or deletions, including changes to energy standards.
[BSC & HCD] Where there are practical difficulties involved in complying with the threshold levels of a tier, the enforcing agency may grant modifications for individual cases. The enforcing agency shall first find that a special individual reason makes the strict letter of the tier impractical and that modification is in conformance with the intent and purpose of the measure. The details of any action granting modification shall be recorded and entered in the files of the enforcing agency.
SECTION 305 [OSHPD 1]— CALGreen TIER 1 AND CALGreen TIER 2
305.1 CALGreen Tier 1 and CALGreen Tier 2 buildings contain voluntary green building measures necessary to meet the threshold of each level.
305.1.1 CALGreen Tier 1. To achieve CALGreen Tier 1, buildings must comply with the latest edition of “Savings By Design, Healthcare Modeling Procedures” found online at http://www.energysoft.com/main/page_ downloads_ sbd_healthcare.html.
305.1.2 CALGreen Tier 2. To achieve CALGreen Tier 2, buildings must exceed the latest edition of “Savings By Design, Healthcare Modeling Procedures” by a minimum of 15 percent.
SECTION 306 [DSA-SS]—VOLUNTARY MEASURES
306.1 Purpose. For public schools and community colleges, voluntary measures further encourage building practices that improve public health, safety and general welfare by promoting the use of building concepts which minimize the building’s impact on the environment and promote a more sustainable design.
306.1.1 Appendix A5, Divisions A5.1 through A5.5, outline means of achieving enhanced sustainable design and construction by incorporating voluntary measures that exceed the mandatory measures.
306.1.2 Chapter 5 Nonresidential Mandatory Measures that are not adopted as mandatory measures by DSA-SS are voluntary measures recommended and encouraged for the design, construction, verification and maintenance of non-energy systems.
Note: The building commissioning requirements for energy efficiency specified in the California Energy Code are required.
3-4 2025 CALIFORNIA GREEN BUILDING STANDARDS CODE
on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.
CALIFORNIA GREEN BUILDING STANDARDS CODE – MATRIX ADOPTION TABLE
CHAPTER 4 – RESIDENTIAL MANDATORY MEASURES
(Matrix Adoption Tables are nonregulatory, intended only as an aid to the code user. See Chapter 1 for state agency authority and building applications.)
CALGreen § 1-1 High relevance — show source text
2025 CALIFORNIA GREEN BUILDING STANDARDS CODE APPENDIX A6.1-1
on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.
APPENDIX A6.1-2 2025 CALIFORNIA GREEN BUILDING STANDARDS CODE
on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.
A6 VOLUNTARY STANDARDS FOR HEALTH FACILITIES [OSHPD 1, 2 & 4]
DIVISION A6.1 – SITE PLANNING AND DESIGN
SECTION A6.106—SITE DEVELOPMENT
A6.106.9 Building orientation. Locate and orient the building as follows:
- When site and location permit, orient the building with the long sides facing north and south.
- Protect the building from thermal loss, drafts and degradation of the building envelope caused by wind and wind-driven materials such as dust, sand, snow and leaves, with building orientation and landscape features. Note: For information on sun angles and shading, visit: http://www2.aud.ucla.edu/energy-design-tools/.
Calculations may be made using the Solar-2 tool.
DIVISION A6.2 – ENERGY EFFICIENCY
SECTION A6.202—DEFINITIONS
A6.202.1 Definitions. The following words and terms shall, for the purposes of this chapter and as used elsewhere in this code, have the meanings shown herein.
ENERGY STAR. A joint program of the US Environmental Protection Agency and the US Department of Energy. ENERGY STAR is a voluntary program designed to identify and promote energy-efficient products and practices.
SECTION A6.203—PERFORMANCE APPROACH
A6.203.2 Energy performance. It is the intent of this code to encourage green buildings to achieve exemplary performance in the area of energy efficiency.
A6.203.2.1 CALGreen Tier 1. [OSHPD 1] To achieve CALGreen [Tier 1, buildings must comply with the latest edition of “Savings By](http://www.energysoft.com/ep/ 2007SBDHProcedures.pdf) Design, Healthcare Modeling Procedures” found online at http://www.energysoft.com/ep/ 2007SBDHProcedures.pdf.
A6.203.2.2 CALGreen Tier 2. [OSHPD 1] To achieve CALGreen Tier 2, buildings must exceed the latest edition of “Savings By Design, Healthcare Modeling Procedures” by a minimum of 15 percent.
SECTION A6.204—PRESCRIPTIVE APPROACH
A6.204.1 ENERGY STAR equipment and appliances. All equipment and appliances provided by the builder shall be ENERGY STAR labeled if ENERGY STAR is applicable to that equipment or appliance.
A6.204.4 Commissioning. [OSHPD 1 & 4] Building commissioning shall be included in the design and construction processes of the building project to verify that the building’s energy related systems are installed, calibrated and perform according to the owner’s project requirements, basis of design and construction documents.
The owner and designer shall designate an individual as the Commissioning Authority (CxA) to lead, review and oversee the completion of the commissioning process activities. The owner shall document the Owner’s Project Requirements (OPR).
CALGreen § 602.1 High relevance — show source text
VOLUNTARY MEASURES. . . . . . . . . . . . . . . . . APPENDIX A5-3
A5.1 Planning and Design . . . . . . . . . . . . . . . . . APPENDIX A5-3 A5.2 Energy Efficiency . . . . . . . . . . . . . . . . . . . APPENDIX A5-13 A5.3 Water Efficiency and Conservation . . . APPENDIX A5-19 A5.4 Material Conservation and Resource Efficiency . . . . . . . . . . . . . . . . . . . . . . . . APPENDIX A5-25 A5.5 Environmental Quality . . . . . . . . . . . . . . APPENDIX A5-35 A5.6 Voluntary Tiers . . . . . . . . . . . . . . . . . . . . . APPENDIX A5-41 A5.601 CALGren Tier 1 and Tier 2. . . . . . . . . . APPENDIX A5-41
A5.602 CALGreen Verification Guidelines Mandatory Measures Checklist . . . . . . . . . . . . . . . APPENDIX A5-44
A5.602.1 CALGreen Verification Guidelines
Tier 1 Checklist . . . . . . . . . . . . . . . . . APPENDIX A5-48
A5.602.2 CALGreen Verification Guidelines
Tier 2 Checklist . . . . . . . . . . . . . . . . . APPENDIX A5-55
APPENDIX A6 VOLUNTARY STANDARDS FOR HEALTH
FACILITIES [OSHPD 1, 2 & 4] . . . . . . . . . . . APPENDIX A6.1-3 A6.1 Site Planning and Design . . . . . . . . . . . APPENDIX A6.1-3 A6.2 Energy Efficiency . . . . . . . . . . . . . . . . . . APPENDIX A6.1-3 A6.4 Material Conservation and Resource Efficiency . . . . . . . . . . . . . APPENDIX A6.1-32 A6.5 Environmental Quality . . . . . . . . . . . . APPENDIX A6.1-33
INDEX . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . INDEX-1
HISTORY NOTE. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . HIST-1
2025 CALIFORNIA GREEN BUILDING STANDARDS CODE vii
on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.
viii 2025 CALIFORNIA GREEN BUILDING STANDARDS CODE
on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.
CALIFORNIA GREEN BUILDING STANDARDS CODE – MATRIX ADOPTION TABLE
CHAPTER 1 – ADMINISTRATION
(Matrix Adoption Tables are nonregulatory, intended only as an aid to the code user. See Chapter 1 for state agency authority and building applications.)
|Adopting
CALGreen § 405.4 High relevance — show source text
- From Division A5.4,
a. Comply with recycled content of 10 percent of materials based on estimated total cost, or use two products from Table A5.405.4 for at least 75 percent by cost in Section A5.405.4. b. Comply with the 65-percent reduction in construction and demolition waste in Section A5.408.3.1. c. Comply with one elective measure selected from this division.
- From Division A5.5,
a. Comply with resilient flooring systems for 90 percent of resilient flooring in Section A5.504.4.7. b. Comply with thermal insulation meeting 2009 CHPS low-emitting materials list in Section A5.504.4.8. c. Comply with one elective measure selected from this division. 6. Comply with one additional elective measure selected from any division.
1 Cool roof is required for compliance with Tiers 1 and 2 and may be used to meet energy standards in Part 6, exceed energy standards and to mitigate heat island effect.
A5.601.3 CALGreen Tier 2.
A5.601.3.1 Prerequisites. To achieve CALGreen tier status, a project must meet all of the mandatory measures in Chapter 5 and, in addition, meet the provisions of this section.
A5.601.3.2 Energy performance. For the purposes of mandatory energy efficiency standards in this code, the California Energy Commission will continue to adopt mandatory standards.
A5.601.3.3 Tier 2. Comply with the energy efficiency requirements in Section A5.203.1.1 and Section A5.203.1.2.2.
A5.601.3.4 Voluntary measures for Tier 2. In addition to the provisions of Sections A5.601.3.1 and A5.601.3.3 above, compliance with the following voluntary measures from Appendix A5 is required for Tier 2:
- From Division A5.1, a. Comply with the designated parking requirements for fuel efficient vehicles for a minimum of 50 percent of parking capacity per Section A5.106.5.1. b. Electric vehicle (EV) charging [N] and Table A5.106.5.3.2 with footnotes. c. Comply with thermal emittance, solar reflectance or SRI values for cool roofs in Section A5.106.11.2 and Table A5.106.11.2.3. [1]
d. Comply with three elective measures selected from this division.
APPENDIX A5-42 2025 CALIFORNIA GREEN BUILDING STANDARDS CODE
on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.
APPENDIX A5 — NONRESIDENTIAL VOLUNTARY MEASURES
From Division A5.2 comply with TWO of the following:
Outdoor lighting as described in A5.203.1.1.1.
Service water heating in restaurants as described in A5.203.1.1.2.
Warehouse Dock Seal Doors A5.203.1.1.3.
Daylight Design Power Adjustments 5.203.1.1.4.
Exhaust Air Heat Recovery A5.203.1.1.5.
From Division A5.3,
CALGreen § 602.1 High relevance — show source text
2025 CALIFORNIA GREEN BUILDING STANDARDS CODE APPENDIX A5-39
on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.
APPENDIX A5-40 2025 CALIFORNIA GREEN BUILDING STANDARDS CODE
on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.
A5 NONRESIDENTIAL VOLUNTARY MEASURES
DIVISION A5.6 – VOLUNTARY TIERS
SECTION A5.601—CALGreen TIER 1 AND TIER 2 Col2 Col3 Col4 TABLE A5.601 NONRESIDENTIAL BUILDINGS: Green Building Standards Code Proposed Performance Approach
Note: This table is intended only as an aid in illustrating the nonresidential tier structure (Refer to Checklists A5.602, A5.602.1 and A5.602.2 for
CALGreen verification guidelines for Mandatory Checklist, Tier 1 Checklist and Tier 2 Checklist.)TABLE A5.601 NONRESIDENTIAL BUILDINGS: Green Building Standards Code Proposed Performance Approach
Note: This table is intended only as an aid in illustrating the nonresidential tier structure (Refer to Checklists A5.602, A5.602.1 and A5.602.2 for
CALGreen verification guidelines for Mandatory Checklist, Tier 1 Checklist and Tier 2 Checklist.)TABLE A5.601 NONRESIDENTIAL BUILDINGS: Green Building Standards Code Proposed Performance Approach
Note: This table is intended only as an aid in illustrating the nonresidential tier structure (Refer to Checklists A5.602, A5.602.1 and A5.602.2 for
CALGreen verification guidelines for Mandatory Checklist, Tier 1 Checklist and Tier 2 Checklist.)TABLE A5.601 NONRESIDENTIAL BUILDINGS: Green Building Standards Code Proposed Performance Approach
Note: This table is intended only as an aid in illustrating the nonresidential tier structure (Refer to Checklists A5.602, A5.602.1 and A5.602.2 for
CALGreen verification guidelines for Mandatory Checklist, Tier 1 Checklist and Tier 2 Checklist.)CATEGORY ENVIRONMENTAL
PERFORMANCE GOALTIER 1 TIER 2 All Minimum Mandatory
(See Mandatory Checklist)Meet all of the provisions
of Chapter 5 (See Tier 1 Checklist)Meet all of the provisions
of Chapter 5 (See Tier 2 Checklist)DIVISION 5.1
Planning and DesignReuse of existing building See Section A5.105.1 and Section
A5.105.2 requirementsSee Section A5.105.1 and Section
A5.105.2 requirementsDIVISION 5.1
Planning and DesignDesignated Parking for
Fuel Efficient Vehicles
(Tier 1 and Tier 2 only)Approx. 35% of total spaces Approx. 50% of total spaces DIVISION 5.1
Planning and DesignElectric Vehicle Charging Approx. 30% of total spaces Approx. 45% of total spaces **DIVISION 5. CALGreen § 405.4 Medium relevance — show source text
- From Division A5.4,
a. Comply with recycled content of 15 percent of materials based on estimated total cost, or use two products from Table A5.405.4 for at least 75 percent by cost in Section A5.405.4.1. b. Comply with the 80-percent reduction in construction and demolition waste in Section A5.408.3.1. c. Comply with three elective measures selected from this division.
- From Division A5.5,
a. Comply with resilient flooring systems for 100 percent of resilient flooring in Section A5.504.4.7.1. Exception: Allowance may be permitted in Tier 2 for up to 5-percent specialty purpose flooring. b. Comply with thermal insulation meeting 2009 CHPS low-emitting materials list and no added formaldehyde in Section A5.504.4.8.1.
c. Comply with three elective measures selected from this division. 6. Comply with three additional elective measures selected from any division.
1 Cool roof is required for compliance with Tiers 1 and 2 and may be used to meet energy standards in Part 6, exceed energy standards and to mitigate heat island effect.
A5.601.4 Compliance verification. Compliance with Section A5.601.2 or A5.601.3 shall be as required in Chapter 7 of this code. Compliance documentation shall be made part of the project record as required in Section 5.410.2 or 5.410.3.
2025 CALIFORNIA GREEN BUILDING STANDARDS CODE APPENDIX A5-43
on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.
APPENDIX A5 — NONRESIDENTIAL VOLUNTARY MEASURES
A5.602
CALGreen VERIFICATION GUIDELINES MANDATORY MEASURES CHECKLIST
Application: This checklist shall be used for nonresidential projects that meet one of the following: new construction, building additions of 1,000 square feet or greater, or building alterations with a permit valuation of $200,000 or more pursuant to Section 301.3 AND do not trigger a Tier 1 or Tier 2 requirement:
Y = Yes (section has been selected and/or included)
— N/A = Not Applicable (code section does not apply to the project mainly used for additions and alterations) O = Other (provide explanation)
[N] = New construction pursuant to Section 301.3
[A ] = Additions and/or Alterations pursuant to Section 301.3
CHAPTER 5
DIVISIONSCol2 SECTION TITLE CODE
SECTIONY N/A O PLAN SHEET,
SPEC OR
ATTACHDIVISION 5.1
Planning and
DesignMandatory Deconstruction and reuse of existing structures,
Scope with Exception5.105.1 DIVISION 5.1
Planning and
DesignMandatory Reuse of existing building & Verification of compliance with
note5.105.2 and
5.105.2.1DIVISION 5.1
Planning and
DesignMandatory Storm water pollution prevention for projects that disturb less
than 1 acre of land5.106. CALGreen § 106.9 Medium relevance — show source text
FEATURE OR MEASURE COMPLIANCE LEVELS Col3 Col4 NOTES FEATURE OR MEASURE Mandatory
CALGreenVOLUNTARY
CALGreenVOLUNTARY
CALGreenVOLUNTARY
CALGreenFEATURE OR MEASURE Mandatory
CALGreenTier 1 Tier 2 Tier 2 DIVISION A6.1 – PLANNING AND DESIGN SECTION Site Development SECTION Site Development SECTION Site Development SECTION Site Development SECTION Site Development **A6.106.9 Building orientation.**Locate and orient the building as follows:
1. When site and location permit, orient the building with the long sides facing north and
south.
2. Protect the building from thermal loss, drafts and degradation of the building envelope
caused by wind and wind-driven materials such as dust. DIVISION A6.2 – ENERGY EFFICIENCY SECTION A6.203 Performance Measures SECTION A6.203 Performance Measures SECTION A6.203 Performance Measures SECTION A6.203 Performance Measures SECTION A6.203 Performance Measures A6.203.1 Energy performance. [OSHPD 1]
**A6.203.1.1 CALGreen Tier 1. [OSHPD 1]**Buildings must comply with the latest edition of
“Savings By Design, Healthcare Modeling Procedures.”
A.5.203.1.2 CALGreen Tier 2. [OSHPD 1] Buildings must exceed the latest edition of “Savings
By Design, Healthcare Modeling Procedures” by 15 percent. SECTION A6.204 Prescriptive Measures **A6.204.1 ENERGY STAR equipment and appliances.**All equipment and appliances provided
by the builder shall be ENERGY STAR labeled if ENERGY STAR is applicable to that equipment
or appliance. A6.204.4 Commissioning. Building commissioning for all building systems covered by T24,
Part 6, process systems and renewable energy systems shall be included in the design and
construction processes of the building project. Commissioning requirements shall include as
a minimum items listed in Section A6.204.4.
**A6.204.4.1 Owner’s Project Requirements (OPR).**Documented before the design phase of
the project begins the OPR shall include items listed in Section A6.204.4.
**A6.204.4.2 Basis of Design (BOD).**A written explanation of how the design of the building
systems meets the OPR shall be completed at the design phase of the building project and
updated periodically to cover the systems listed in Section A6.204.4.2.
**A6.204.4.3 Commissioning plan.CALGreen § 301.5 Medium relevance — show source text
301.5 Health Facilities. [OSHPD 1, 2 & 4] Health facilities under the jurisdiction of the Office of Statewide Health Planning and Development (OSHPD) are required to comply with the mandatory measures prescribed in Section 5.304, Outdoor Water Use. Compliance with Section 5.304, as adopted by the Building Standards Commission, is enforced by the local agency having jurisdiction. Evidence of local approval shall be submitted to OSHPD prior to issuance of plan approval or a building permit.
2025 CALIFORNIA GREEN BUILDING STANDARDS CODE 3-3
on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.
GREEN BUILDING
SECTION 302—MIXED OCCUPANCY BUILDINGS
302.1 Mixed occupancy buildings. In mixed occupancy buildings, each portion of a building shall comply with the specific green building measures applicable to each specific occupancy.
Exceptions:
- [HCD] Accessory structures and accessory occupancies serving residential buildings shall comply with Chapter 4 and Appendix A4, as applicable.
- [HCD] For the purposes of CALGreen, live/work units, complying with Section 508.5 of the California Building Code, shall not be considered mixed occupancies. Live/work units shall comply with Chapter 4 and Appendix A4, as applicable.
SECTION 303—PHASED PROJECTS
303.1 Phased projects. For shell buildings and others constructed for future tenant improvements, only those code measures relevant to the building components and systems considered to be new construction (or newly constructed) shall apply.
303.1.1 Initial tenant improvements. The provisions of this code shall apply only to the initial tenant improvements to a project. Subsequent tenant improvements shall comply with the scoping provisions in Section 301.3 nonresidential additions and alterations.
SECTION 304—VOLUNTARY TIERS
304.1 Purpose. Voluntary tiers are intended to further encourage building practices that improve public health, safety and general welfare by promoting the use of building concepts which minimize the building’s impact on the environment and promote a more sustainable design.
304.1.1 Tiers. The provisions of Divisions A4.6 and A5.6 outline means, in the form of voluntary tiers, for achieving enhanced construction levels by incorporating additional measures for residential and nonresidential new construction. Voluntary tiers may be adopted by local governments and, when adopted, enforced by local enforcing agencies. Buildings complying with tiers specified for each occupancy contain additional prerequisite and elective green building measures necessary to meet the threshold of each tier. See Section 101.7 of this code for procedures and requirements related to local amendments, additions or deletions, including changes to energy standards.
[BSC & HCD] Where there are practical difficulties involved in complying with the threshold levels of a tier, the enforcing agency may grant modifications for individual cases. The enforcing agency shall first find that a special individual reason makes the strict letter of the tier impractical and that modification is in conformance with the intent and purpose of the measure. The details of any action granting modification shall be recorded and entered in the files of the enforcing agency.
SECTION 305 [OSHPD 1]— CALGreen TIER 1 AND CALGreen TIER 2
305.1 CALGreen Tier 1 and CALGreen Tier 2 buildings contain voluntary green building measures necessary to meet the threshold of each level.
CALGreen § 601.2.4 Medium relevance — show source text
A5.601.2.4 Voluntary measures for Tier 1. In addition to the provisions of Sections A5.601.2.1 and A5.601.2.3 above, compliance with the following voluntary measures from Appendix A5 is required for Tier 1:
- From Division A5.1, a. Comply with the designated parking requirements for high-efficiency vehicles for a minimum of 35 percent of parking capacity per Section A5.106.5.1. b. Electric vehicle (EV) charging [N] and Table A5.106.5.3.1 w/ footnotes. c. Comply with thermal emittance, solar reflectance or SRI values for cool roofs in Section A5.106.11.2 and Table A5.106.11.2.2. [1]
d. Comply with one elective measure selected from this division. 2. From Division A5.2 comply with ONE of the following:
Outdoor lighting as described in A5.203.1.1.1.
Service water heating in restaurants as described in A5.203.1.1.2.
Warehouse Dock Seal Doors A5.203.1.1.3.
Daylight Design Power Adjustments 5.203.1.1.4.
Exhaust Air Heat Recovery A5.203.1.1.5.
From Division A5.3,
a. Comply with the 12-percent reduction for indoor potable water use in Section A5.303.2.3.1. b. Comply with one elective measure selected from this division.
- From Division A5.4,
a. Comply with recycled content of 10 percent of materials based on estimated total cost, or use two products from Table A5.405.4 for at least 75 percent by cost in Section A5.405.4. b. Comply with the 65-percent reduction in construction and demolition waste in Section A5.408.3.1. c. Comply with one elective measure selected from this division.
- From Division A5.5,
a. Comply with resilient flooring systems for 90 percent of resilient flooring in Section A5.504.4.7. b. Comply with thermal insulation meeting 2009 CHPS low-emitting materials list in Section A5.504.4.8. c. Comply with one elective measure selected from this division. 6. Comply with one additional elective measure selected from any division.
1 Cool roof is required for compliance with Tiers 1 and 2 and may be used to meet energy standards in Part 6, exceed energy standards and to mitigate heat island effect.
A5.601.3 CALGreen Tier 2.
A5.601.3.1 Prerequisites. To achieve CALGreen tier status, a project must meet all of the mandatory measures in Chapter 5 and, in addition, meet the provisions of this section.
A5.601.3.2 Energy performance. For the purposes of mandatory energy efficiency standards in this code, the California Energy Commission will continue to adopt mandatory standards.
A5.601.3.3 Tier 2. Comply with the energy efficiency requirements in Section A5.203.1.1 and Section A5.203.1.2.2.
CALGreen § 3-4 Medium relevance — show source text
302 Mixed Occupancy Buildings . . . . . . . . . . . . . . . . . . . . . . .3-4 303 Phased Projects. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3-4 304 Voluntary Tiers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3-4 305 CALGreen Tier 1 and CALGreen Tier 2 . . . . . . . . . . . . . .3-4
306 Voluntary Measures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3-4
CHAPTER 4 RESIDENTIAL MANDATORY MEASURES . . . . . . 4-3
4.1 Planning and Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4-3 4.2 Energy Efficiency . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4-7 4.3 Water Efficiency and Conservation . . . . . . . . . . . . . . . . .4-9 4.4 Material Conservation and Resource Efficiency . . . . 4-11 4.5 Environmental Quality . . . . . . . . . . . . . . . . . . . . . . . . . . 4-13
CHAPTER 5 NONRESIDENTIAL MANDATORY MEASURES . . 5-3
5.1 Planning and Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .5-3 5.2 Energy Efficiency . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-15 5.3 Water Efficiency and Conservation . . . . . . . . . . . . . . . 5-19 5.4 Material Conservation and Resource Efficiency . . . . 5-23 5.5 Environmental Quality . . . . . . . . . . . . . . . . . . . . . . . . . . 5-31
CHAPTER 6 REFERENCED ORGANIZATIONS
AND STANDARDS. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-3
601 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-3
CHAPTER 7 INSTALLER AND SPECIAL
INSPECTOR QUALIFICATIONS . . . . . . . . . . . . . . . . . . . . . . 7-3 701 General (Reserved) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .7-3 702 Qualifications. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .7-3
CALGreen § 203.1.1 Medium relevance — show source text
[OSHPD 1]**
**A6.203.1.1 CALGreen Tier 1. [OSHPD 1]**Buildings must comply with the latest edition of
“Savings By Design, Healthcare Modeling Procedures.”
A.5.203.1.2 CALGreen Tier 2. [OSHPD 1] Buildings must exceed the latest edition of “Savings
By Design, Healthcare Modeling Procedures” by 15 percent.||||| |SECTION A6.204 Prescriptive Measures||||| |**A6.204.1 ENERGY STAR equipment and appliances.**All equipment and appliances provided
by the builder shall be ENERGY STAR labeled if ENERGY STAR is applicable to that equipment
or appliance.||||| |A6.204.4 Commissioning. Building commissioning for all building systems covered by T24,
Part 6, process systems and renewable energy systems shall be included in the design and
construction processes of the building project. Commissioning requirements shall include as
a minimum items listed in Section A6.204.4.
**A6.204.4.1 Owner’s Project Requirements (OPR).**Documented before the design phase of
the project begins the OPR shall include items listed in Section A6.204.4.
**A6.204.4.2 Basis of Design (BOD).**A written explanation of how the design of the building
systems meets the OPR shall be completed at the design phase of the building project and
updated periodically to cover the systems listed in Section A6.204.4.2.
**A6.204.4.3 Commissioning plan.**A commissioning plan describing how the project will be
commissioned shall be started during the design phase of the building project and shall
include as a minimum items listed in Section A6.204.4.3.
A6.204.4.4 Functional performance testingshall demonstrate the correct installation and
operation of each component, system and system-to-system interface in accordance with
the approved plans and specifications.
**A6.204.4.5 Post construction documentation and training.**A systems manual and
systems operations training are required.
**A6.204.4.5.1 Systems manual.**The systems manual shall be delivered to the building
owner and facilities operator and shall include the items listed in Section A6.204.4.5.1.
A6.204.4.5.2 Systems operations training. The training of the appropriate maintenance
staff for each equipment type and/or system shall include as a minimum items listed in
Section A6.204.4.5.2.
**A6.204.4.6 Commissioning report.**A complete report of commissioning process activities
undertaken through the design, construction and postconstruction phases of the building
project shall be completed and provided to the owner.||
|
|| |**A6.204.6 Building orientation and shading.CALGreen § 8-40 Medium relevance — show source text
. . . . . . . . . . . . . 8-40
APPENDIX A4 RESIDENTIAL
VOLUNTARY MEASURES. . . . . . . . . . . . . . . . . APPENDIX A4-3
A4.1 Planning and Design . . . . . . . . . . . . . . . . . APPENDIX A4-3 A4.2 Energy Efficiency . . . . . . . . . . . . . . . . . . . . APPENDIX A4-9 A4.3 Water Efficiency and Conservation . . . APPENDIX A4-13 A4.4 Material Conservation and Resource Efficiency . . . . . . . . . . . . . . . . . . . . . . . . APPENDIX A4-15 A4.5 Environmental Quality . . . . . . . . . . . . . . APPENDIX A4-19 A4.6 Tier 1 and Tier 2 . . . . . . . . . . . . . . . . . . . . APPENDIX A4-21
Division A4.6—Residential Occupancies Application Checklist . . . . . . . . . . . . . APPENDIX A4-23 A4.7 Residential Model Ordinance . . . . . . . . . APPENDIX A4-31
APPENDIX A5 NONRESIDENTIAL
VOLUNTARY MEASURES. . . . . . . . . . . . . . . . . APPENDIX A5-3
A5.1 Planning and Design . . . . . . . . . . . . . . . . . APPENDIX A5-3 A5.2 Energy Efficiency . . . . . . . . . . . . . . . . . . . APPENDIX A5-13 A5.3 Water Efficiency and Conservation . . . APPENDIX A5-19 A5.4 Material Conservation and Resource Efficiency . . . . . . . . . . . . . . . . . . . . . . . . APPENDIX A5-25 A5.5 Environmental Quality . . . . . . . . . . . . . . APPENDIX A5-35 A5.6 Voluntary Tiers . . . . . . . . . . . . . . . . . . . . . APPENDIX A5-41 A5.601 CALGren Tier 1 and Tier 2. . . . . . . . . . APPENDIX A5-41
A5.602 CALGreen Verification Guidelines Mandatory Measures Checklist . . . . . . . . . . . . . . . APPENDIX A5-44
A5.602.1 CALGreen Verification Guidelines
Tier 1 Checklist . . . . . . . . . . . . . . . . . APPENDIX A5-48
A5.602.2 CALGreen Verification Guidelines
Tier 2 Checklist . . . . . . . . . . . . . . . . . APPENDIX A5-55
APPENDIX A6 VOLUNTARY STANDARDS FOR HEALTH
Frequently asked questions
Are the CALGreen Tier 1 and Tier 2 requirements mandatory statewide?
No — the voluntary tiers are optional statewide; they only become mandatory in a given jurisdiction if adopted locally. See §304 and the scope language in Appendix A5 (A5.601.1) and the note on local adoption and amendment procedures (see §101.7).
What are the energy thresholds for Tier 1 and Tier 2?
Tier 1 energy compliance ties to the latest “Savings By Design, Healthcare Modeling Procedures.” Tier 2 requires exceeding that Savings By Design benchmark by a minimum of 15 percent (expressly referenced in the CALGreen Tier sections and in the A6 performance rules for health facilities).
Where do I find the verification checklists and the elective/prerequisite lists?
Verification guidance and the mandatory/Tier 1/Tier 2 checklists are in Appendix A5 — see A5.602 (Mandatory Checklist), A5.602.1 (Tier 1 Checklist) and A5.602.2 (Tier 2 Checklist) for the forms and documentation requirements.
More in California Green Building Standards Code (CALGreen)
- Administration (Chapter 1)
- Nonresidential Voluntary Measures (Appendix A5 — divisions A5.1–A5.6, electives & verification)
- Residential Mandatory Measures — Planning & Design; Energy; Water; Materials; Environmental Quality (Chapter 4)
- Definitions (Chapter 2)
- Voluntary Standards for Health Facilities (Appendix A6 / OSHPD guidance)
- Green Building – scope, mixed occupancies, phased projects (Chapter 3)
- Residential Voluntary Measures (Appendix A4 — divisions A4.1–A4.6, tiers & model ordinance)
- Nonresidential Mandatory Measures — Planning & Design; Energy; Water; Materials; Environmental Quality (Chapter 5)
- Compliance verification, construction documents & checklists (Section 102, Chapter 7, Appendix checklists)
- Referenced Organizations and Standards (Chapter 6)
- Voluntary Tiers and CALGreen Tier 1 / Tier 2 (performance tiers, thresholds)
- Installer and Special Inspector Qualifications (Chapter 7)
Ask about the CALGreen
Get cited, plain-English answers on the California Green Building Standards Code (CALGreen) for your project — any code section, any scenario.
Start Free TrialRelated in the CALGreen
Administration (Chapter 1)
Definitions (Chapter 2)
Green Building – scope, mixed occupancies, phased projects (Chapter 3)
Nonresidential Mandatory Measures — Planning & Design; Energy; Water; Materials; Environmental Quality (Chapter 5)
Residential Mandatory Measures — Planning & Design; Energy; Water; Materials; Environmental Quality (Chapter 4)
Residential Voluntary Measures (Appendix A4 — divisions A4.1–A4.6, tiers & model ordinance)
Nonresidential Voluntary Measures (Appendix A5 — divisions A5.1–A5.6, electives & verification)
Voluntary Standards for Health Facilities (Appendix A6 / OSHPD guidance)
California Green Building Standards Code (CALGreen)