108A.3 Inspection requests.
San Francisco Building Inspection Commission Codes · 2022 edition · ingested 2026-07-08 · San Francisco
108A.3 Inspection requests. It shall be the duty of the person doing the work authorized by a permit to notify the building official that such work is ready for inspection. The building official may require that every request for inspection be filed at least one working day before such inspection is desired. Such request may be in writing or by telephone at the option of the building official.
It shall be the duty of the person requesting any inspections required by this code to provide access to and means for inspections of such work.
108A.3.1 Off-hour inspections. Those desiring inspections outside normal business hours (7:30 a.m. to 4:00 p.m., Monday through Friday, excluding legal holidays) may avail themselves of this service by prior arrangement and prepayment. See Section 110A, Table 1A-G – Inspections, Surveys and Reports – for applicable fee.
108A.3.2 Permits by other departments. Those applying for permits issued by other City departments which require an inspection, certification or report by the Department as a condition of issuance of said permits shall apply to the Department for said inspection, certification or report and pay a fee at the Department of Building Inspection. See Section 110A, Table 1A-G – Inspections, Surveys and Reports – for applicable fee.