701.4 Indoor Combustion Air. The required volume of
California Mechanical Code (Title 24, Part 4) · 2025 edition · updated 2026-09-10 · California
Italicized text is a California amendment to the model code, as printed in the official publication.
indoor air shall be determined in accordance with the method
in Section 701.4.1 or Section 701.4.2 except that where the air infiltration rate is known to be less than 0.40 ACH (air change per hour), the method in Section 701.4.2 shall be used. The total required volume shall be the sum of the required volume calculated for appliances located within the space. Rooms communicating directly with the space in which the appliances are installed through openings not furnished with doors, and through combustion air openings sized and located in accordance with Section 701.5, are considered a part of the required volume. [NFPA 54:9.3.2]
701.4.1 Standard Method. The minimum required volume shall be 50 cubic feet per 1000 British thermal units per hour (Btu/h) (4.83 m [3] /kW). [NFPA 54:9.3.2.1]
701.4.2 Known Air Infiltration Rate Method. Where
the air infiltration rate of a structure is known, the minimum required volume shall be determined as follows
[NFPA 54:9.3.2.2]:
(1) For appliances other than fan-assisted, calculate using the following Equation 701.4.2(1). [NFPA 54:9.3.2.2(1)]
[Equation 701.4.2(1)]
I other
Required Volume other ≥ [21 ft] ACH [3] 1000 Btu/h
( )
(2) For fan-assisted appliances, calculate using the following Equation 701.4.2(2). [NFPA 54:9.3.2.2(2)]
[Equation 701.4.2(2)]
15 ft [3] I
fan
Required Volume fan ≥ ACH 1000 Btu/h
( )
Where:
I other = All appliances other than fan-assisted input (Btu/h) (kW) I = Fan-assisted appliance input (Btu/h) (kW) fan ACH = Air change per hour (percent of volume of space exchanged per hour, expressed as a decimal)
Required Volume other ≥ [21 ft] [3]
ACH
(
I other
[21 ft] [3]
ACH 1000 Btu/h
( )
15 ft [3] Required Volume fan ≥ ACH
(
15 ft [3] I
fan ACH 1000 Btu/h
( )
For SI units: 1 cubic foot = 0.0283 m [3], 1000 British thermal units per
hour = 0.293 kW
(3) For purposes of these calculations, an infiltration rate greater than 0.60 ACH shall not be used in Equation 701.4.2(1) and Equation 701.4.2(2). [NFPA 54:9.3.2.2(3)]
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸Contents — California Mechanical Code (Title 24, Part 4)
- Chapter 1 — GENERAL CODE PROVISIONS
- Chapter 2 — DEFINITIONS
- Chapter 3 — GENERAL REGULATIONS
- Chapter 4 — VENTILATION AIR
- Chapter 5 — EXHAUST SYSTEMS
- Chapter 6 — DUCT SYSTEMS
▸Chapter 7 — COMBUSTION AIR
Overview- 701.1 Applicability. Air for combustion, ventilation, and
- 701.2 Pressure Difference. Where used, a draft hood or a
- 701.3 Makeup Air. Where exhaust fans, clothes dryers, and
- 701.4 Indoor Combustion Air. The required volume of
- 701.5 Indoor Opening Size and Location. Openings
- 701.6 Outdoor Combustion Air. Outdoor combustion air
- 701.7 Combination Indoor and Outdoor Combustion
- 701.8 Engineered Installations. Engineered combustion
- 701.9 Mechanical Combustion Air Supply. Where all
- 701.10 Louvers, Grilles, and Screens. The required size
- 701.11 Combustion Air Ducts. Combustion air ducts shall
- 701.12 Dampers Prohibited. Combustion air ducts or
- 702.1 General. No device or attachment shall be installed
- Chapter 8 — CHIMNEYS AND VENTS
- Chapter 9 — INSTALLATION OF SPECIFIC APPLIANCES
- Chapter 10 — BOILERS AND PRESSURE VESSELS
- Chapter 11 — REFRIGERATION
- Chapter 12 — HYDRONICS
- Chapter 13 — FUEL GAS PIPING
- Chapter 14 — PROCESS PIPING
- Chapter 15 — SOLAR ENERGY SYSTEMS
- Chapter 16 — STATIONARY POWER PLANTS
- Chapter 17 — GEOTHERMAL ENERGY SYSTEMS AND AMBIENT TEMPERATURE…
- Chapter 18 — REFERENCED STANDARDS
- Appendix A — RESIDENTIAL PLAN EXAMINER REVIEW FORM FOR HVAC SY…
- Appendix B — PROCEDURES TO BE FOLLOWED TO PLACE GAS EQUIPMENT …
- Appendix C — INSTALLATION AND TESTING OF OIL (LIQUID) FUEL-FIR…
- Appendix D — FUEL SUPPLY: MANUFACTURED/MOBILE HOME PARKS AND R…
- Appendix E — SUSTAINABLE PRACTICES
- Appendix F — SIZING OF VENTING SYSTEMS AND OUTDOOR COMBUSTION …
- Appendix G — EXAMPLE CALCULATION OF OUTDOOR AIR RATE
- Appendix H — PROFESSIONAL QUALIFICATIONS
- Appendix I — INDOOR HORTICULTURAL FACILITIES
- Appendix J — CLEAN AIR DELIVERY