Appendix A — GUIDELINES FOR THE SEISMIC RETROFIT OF EXISTING BUILDINGS

Section A206 — ANALYSIS AND DESIGN

2025 California Existing Building Code (Title 24, Part 10) · 2025 edition · updated 2026-07-27 · California

Italicized text is a California amendment to the model code, as printed in the official publication.

[BS] A206.1 Reinforced concrete and reinforced masonry wall anchorage. Concrete and masonry walls shall be anchored to all floors and roofs that provide lateral support for the wall in accordance with Section 12.11.2 of ASCE 7. The anchorage shall provide a direct connection capable of resisting 75 percent of the forces specified in Section 12.11.2.1 of ASCE 7.

Exceptions:

  1. Existing walls need not be evaluated or retrofitted for bending between anchors.
  2. Work required by this chapter need not consider shrinkage, thermal changes or differential settlement.

A206.1.1 Seismicity parameters, site class and geologic hazards. For any site designated as Site Class E, the value of F a shall be taken as 1.2. Site-specific procedures are not required for compliance with this chapter. Mitigation of existing geologic site hazards such as liquefiable soil, fault rupture or landslide is not required for compliance with this chapter.

[BS] A206.2 Additional requirements for wall anchorage systems. The wall anchorage system shall comply with the requirements of this section and Section 12.11.2.2 of ASCE 7.

The maximum spacing between wall anchors shall be 8 feet (2438 mm), and each wall segment shall have at least two wall anchors.

The wall anchorage system, excluding subdiaphragms and existing roof or floor framing members, shall be designed and installed to limit the relative movement between the wall and the diaphragm to no more than [1] / 8 inch before engagement of the anchors. Wall anchors shall be provided to resist out-of-plane forces, independent of existing shear anchors.

Where new members are added as crossties, they shall be spaced no more than 24 feet (7315 mm) apart. Where existing girders are used as crossties, their actual spacing shall be deemed adequate even where the spacing exceeds 24 feet (7315 mm), as long as the girders are provided with continuity connectors as required.

Wall anchorage shall not be provided by fastening the edge of plywood sheathing to steel ledgers. Wall anchorage shall not be provided solely by fastening the edge of steel decking to steel ledgers unless analysis demonstrates acceptable capacity. The existing connections shall be subject to field verification and the new connections shall be subject to special inspection.

New wall anchors shall be provided to resist the full wall anchorage design force independent of existing shear or tension anchors.

Exception: Existing cast-in-place anchors shall be permitted as part of the wall anchorage system if the tie element can be readily attached to the anchors, and if the anchors are capable of resisting the total vertical and lateral shear load (including dead load) while being acted on by the maximum wall anchorage tension force caused by an earthquake. Acceptable tension values for the existing anchors shall be established by testing in accordance with Section A205.4.

[BS] A206.3 Development of anchor forces into the diaphragm. Development of the required anchorage forces into roof and floor diaphragms shall comply with the requirements of this section and Section 12.11.2.2 of ASCE 7.

Lengths of development of anchor loads in wood diaphragms shall be based on existing field nailing of the sheathing unless existing edge nailing is positively identified on the original construction plans or at the site.

[BS] A206.4 Anchorage at pilasters. Where pilasters are present, the wall anchorage system shall comply with the requirements of this section and Section 12.11.2.2.7 of ASCE 7. The pilasters or the walls immediately adjacent to the pilasters shall be anchored directly to the roof framing such that the existing vertical anchor bolts at the top of the pilasters are bypassed without permitting tension or shear failure at the top of the pilasters.

Exception: If existing vertical anchor bolts at the top of the pilasters are used for the anchorage, additional exterior confinement shall be provided as required to resist the total anchorage force.

[BS] A206.5 Combination of anchor types. New anchors used in combination on a single framing member shall be of compatible behavior and stiffness.

[BS] A206.6 Anchorage at interior walls. Existing interior reinforced concrete or reinforced masonry walls that extend to the floor above or to the roof diaphragm shall be anchored for out-of-plane forces per Sections A206.1 and A206.3. Walls extending through

APPENDIX A-22 2025 CALIFORNIA EXISTING BUILDING CODE

on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.

APPENDIX A—GUIDELINES FOR THE SEISMIC RETROFIT OF EXISTING BUILDINGS

the roof diaphragm shall be anchored for out-of-plane forces on both sides, and continuity ties shall be spliced across or continuous through the interior wall to provide diaphragm continuity.

[BS] A206.7 Collectors. Collectors designed in accordance with this section shall be provided at reentrant corners and at interior shear walls. Existing or new collectors shall have the capacity to develop into the diaphragm a force equal to the lesser of the rocking or shear capacity of the reentrant wall or the tributary shear based on 75 percent of the diaphragm design forces specified in Section 12.10 of ASCE 7. The capacity of the collector need not exceed the capacity of the diaphragm to deliver loads to the collector. A connection shall be provided from the collector to the reentrant wall to transfer the full collector internal force. If a truss or beam other than a rafter or purlin is supported by the reentrant wall or by a column integral with the reentrant wall, then an independent secondary column is required to support the roof or floor members whenever rocking or shear capacity of the reentrant wall is less than the tributary shear.

[BS] A206.8 Mezzanines. Existing mezzanines relying on reinforced concrete or reinforced masonry walls for vertical or lateral support shall be anchored to the walls for the tributary mezzanine load. Walls depending on the mezzanine for lateral support shall be anchored per Sections A206.1, A206.2 and A206.3.

Exception: Existing mezzanines that have independent lateral and vertical support need not be anchored to the walls.

Get a plain-English answer with a citation back to this text.

Ask AI about this code
Contents — 2025 California Existing Building Code (Title 24, Part 10)
2025 California Existing Building Code (Title 24, Part 10)
  1. 104.11 for consideration of alternative means of compliance.
  2. Chapter 1 — ADMINISTRATION
  3. Chapter 2 — DEFINITIONS
  4. Chapter 3 — PROVISIONS FOR ALL COMPLIANCE METHODS
  5. Chapter 3A — PROVISIONS FOR ALL COMPLIANCE METHODS
  6. Chapter 4 — REPAIRS
  7. Chapter 4A — REPAIRS
  8. Chapter 5 — PRESCRIPTIVE COMPLIANCE METHOD
  9. Chapter 5A — PRESCRIPTIVE COMPLIANCE METHOD
  10. Chapter 6 — CLASSIFICATION OF WORK
  11. Chapter 7 — ALTERATIONS—LEVEL 1
  12. Chapter 8 — ALTERATIONS—LEVEL 2
  13. Chapter 9 — ALTERATIONS—LEVEL 3
  14. Chapter 10 — CHANGE OF OCCUPANCY
  15. Chapter 11 — ADDITIONS
  16. Chapter 12 — HISTORIC BUILDINGS
  17. Chapter 13 — PERFORMANCE COMPLIANCE METHODS
  18. Chapter 14 — RELOCATED OR MOVED BUILDINGS
  19. Chapter 15 — CONSTRUCTION SAFEGUARDS
  20. Chapter 16 — REFERENCED STANDARDS
  21. Appendix A — GUIDELINES FOR THE SEISMIC RETROFIT OF EXISTING B…
  22. Appendix B — SUPPLEMENTARY ACCESSIBILITY REQUIREMENTS FOR EXIS…
  23. Appendix C — GUIDELINES FOR THE WIND RETROFIT OF EXISTING BUIL…
  24. Appendix D — BOARD OF APPEALS
  25. Appendix E — TEMPORARY EMERGENCY USES
  26. Appendix A — GUIDELINES ON FIRE RATINGS OF ARCHAIC MATERIALS A…

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.