[BS] A107.1 Pointing. Preparation and mortar pointing shall be performed with special inspection.
Exception: At the discretion of the code official, incidental pointing may be performed without special inspection.
[BS] A107.2 Masonry shear tests. In-place masonry shear tests shall comply with Section A106.2.3.1. Testing of masonry for determination of splitting tensile strength shall comply with Section A106.2.3.3.
[BS] A107.3 Existing wall anchors. Existing wall anchors used as all or part of the required tension anchors shall be tested in pullout according to Section A107.5.1. Not fewer than four anchors tested per floor shall be tested in pullout, with not fewer than two tests at walls with joists framing into the wall and two tests at walls with joists parallel to the wall, but not less than 10 percent of the total number of existing tension anchors at each level.
[BS] A107.4 New wall anchors. New wall anchors embedded in URM walls shall be subject to special inspection prior to placement of the anchor and grout or adhesive in the drilled hole. Five percent of all anchors that do not extend through the wall shall be subject to a direct-tension test, and an additional 20 percent shall be tested using a calibrated torque wrench. Testing shall be performed in accordance with Section A107.5.
New wall anchors embedded in URM walls resisting tension forces or a combination of tension and shear forces shall be subject to special inspection, prior to placement of the anchor and grout or adhesive in the drilled hole. Five percent of all anchors resisting tension forces shall be subject to a direct-tension test, and an additional 20 percent shall be tested using a calibrated torque wrench. Testing shall be performed in accordance with Section A107.5.
Exception: New bolts that extend through the wall with steel plates on the far side of the wall need not be tested.
[BS] A107.5 Tests of anchors in unreinforced masonry walls. Tests of anchors in unreinforced masonry walls shall be in accordance with Sections A107.5.1 through A107.5.3. Results of all tests shall be reported to the authority having jurisdiction. The report shall include the test results of maximum load for each test; pass-fail results; corresponding anchor size and type; orientation of loading; details of the anchor installation, testing apparatus and embedment; wall thickness; and joist orientation and proximity to the tested anchor.
[BS] A107.5.1 Direct tension testing of existing anchors and new anchors. The test apparatus shall be supported by the masonry wall. The test procedure for prequalification of tension and shear anchors shall comply with ASTM E488. Existing wall anchors shall be given a preload of 300 pounds (1335 N) before establishing a datum for recording elongation. The tension test load reported shall be recorded at [1] / 8 inch (3.2 mm) relative movement between the existing anchor and the adjacent masonry surface. New embedded tension anchors shall be subject to a direct tension load of not less than 2.5 times the design load but not less than 1,500 pounds (6672 N) for 5 minutes.
of 300 pounds (1335 N) before establishing a datum for recording elongation. The tension test load reported shall be recorded at [1] / 8 inch (3.2 mm) relative movement between the existing anchor and the adjacent masonry surface. New embedded tension anchors shall be subject to a direct tension load of not less than 2.5 times the design load but not less than 1,500 pounds (6672 N) for 5 minutes.
Exception: Where obstructions occur, the distance between the anchor and the test apparatus support shall be not less than one-half the wall thickness for existing anchors and 75 percent of the embedment length for new embedded anchors.
[BS] A107.5.2 Torque testing of new anchors. Anchors embedded in unreinforced masonry walls shall be tested using a torquecalibrated wrench to the following minimum torques:
1 / 2 -inch-diameter (12.7 mm) bolts: 40 foot pounds (54.2 N-m).
5 / 8 -inch-diameter (15.9 mm) bolts: 50 foot pounds (67.8 N-m).
3 / 4 -inch-diameter (19.1 mm) bolts: 60 foot pounds (81.3 N-m).
[BS] A107.5.3 Prequalification test for bolts and other types of anchors. ASTM E488 or the test procedure in Section A107.5.1 is permitted to be used to determine tension or shear strength values for anchors greater than those permitted by Table A108.1(2). Anchors shall be installed in the same manner and using the same materials as will be used in the actual construction. Not fewer than five tests for each bolt size and type shall be performed for each class of masonry in which they are proposed to be used. The tension and shear strength values for such anchors shall be the lesser of the average ultimate load divided by 5.0 or the average load at which [1] / 8 inch (3.2 mm) elongation occurs for each size and type of anchor and class of masonry.
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸ Contents — 2025 California Existing Building Code (Title 24, Part 10)
- 104.11 for consideration of alternative means of compliance.
- Chapter 1 — ADMINISTRATION
- Chapter 2 — DEFINITIONS
- Chapter 3 — PROVISIONS FOR ALL COMPLIANCE METHODS
- Chapter 3A — PROVISIONS FOR ALL COMPLIANCE METHODS
- Chapter 4 — REPAIRS
- Chapter 4A — REPAIRS
- Chapter 5 — PRESCRIPTIVE COMPLIANCE METHOD
- Chapter 5A — PRESCRIPTIVE COMPLIANCE METHOD
- Chapter 6 — CLASSIFICATION OF WORK
- Chapter 7 — ALTERATIONS—LEVEL 1
- Chapter 8 — ALTERATIONS—LEVEL 2
- Chapter 9 — ALTERATIONS—LEVEL 3
- Chapter 10 — CHANGE OF OCCUPANCY
- Chapter 11 — ADDITIONS
- Chapter 12 — HISTORIC BUILDINGS
- Chapter 13 — PERFORMANCE COMPLIANCE METHODS
- Chapter 14 — RELOCATED OR MOVED BUILDINGS
- Chapter 15 — CONSTRUCTION SAFEGUARDS
- Chapter 16 — REFERENCED STANDARDS
-
▸ Appendix A — GUIDELINES FOR THE SEISMIC RETROFIT OF EXISTING B…
Overview- Section A100 — APPLICATION
- Section A101 — PURPOSE
- Section A102 — SCOPE
- Section A103 — DEFINITIONS
- Section A104 — SYMBOLS AND NOTATIONS
- Section A105 — GENERAL REQUIREMENTS
- Section A106 — MATERIALS REQUIREMENTS
- Section A107 — QUALITY CONTROL
- Section A108 — DESIGN STRENGTHS
- Section A109 — ANALYSIS AND DESIGN PROCEDURE
- Section A110 — GENERAL PROCEDURE
- Section A111 — SPECIAL PROCEDURE
- Section A112 — ANALYSIS AND DESIGN
- Section A113 — DETAILED BUILDING SYSTEM DESIGN REQUIREMENTS
- Section A114 — WALLS OF UNBURNED CLAY, ADOBE OR STONE MASONRY
- Section A201 — PURPOSE
- Section A202 — SCOPE
- Section A203 — DEFINITIONS
- Section A204 — SYMBOLS AND NOTATIONS
- Section A205 — GENERAL REQUIREMENTS
- Section A206 — ANALYSIS AND DESIGN
- Section A207 — MATERIALS OF CONSTRUCTION
- Section A301 — GENERAL
- Section A302 — DEFINITIONS
- Section A303 — STRUCTURAL WEAKNESSES
- Section A304 — STRENGTHENING REQUIREMENTS
- Section A401 — GENERAL
- Section A402 — DEFINITIONS
- Section A403 — ANALYSIS AND DESIGN
- Section A404 — PRESCRIPTIVE MEASURES FOR WEAK STORY
- Section A405 — MATERIALS OF CONSTRUCTION
- Section A406 — CONSTRUCTION DOCUMENTS
- Section A407 — QUALITY CONTROL
- Section A501 — REFERENCED STANDARDS
- Appendix B — SUPPLEMENTARY ACCESSIBILITY REQUIREMENTS FOR EXIS…
- Appendix C — GUIDELINES FOR THE WIND RETROFIT OF EXISTING BUIL…
- Appendix D — BOARD OF APPEALS
- Appendix E — TEMPORARY EMERGENCY USES
- Appendix A — GUIDELINES ON FIRE RATINGS OF ARCHAIC MATERIALS A…