Skip to content

Chapter 31F — MARINE OIL TERMINALS

Section 3102F

California Building Code (Title 24, Part 2) · 2022 edition · updated 2026-09-12 · California

Italicized text is a California amendment to the model code, as printed in the official publication.

3102F.1 General.

Division 2

3102F.1.1 Purpose. Section 3102F defines minimum requirements for audit, inspection and evaluation of the structural, mechanical and electrical components and sys- tems.

3102F.1.2 Audit and inspections types. The audit and inspections described in this Chapter (31F) are:

1. Annual compliance inspection

2. Audits

3. Post-event inspection

Each has a distinct purpose and is conducted either at a defined interval (see Table 31F-2-1 and Section 3102F.3.3), for a significant change in operations, or as a result of a significant, potentially damage-causing event. In the time between audits and inspections, operators are expected to conduct periodic walk-down examinations of the MOT to detect potentially unsafe conditions.

3102F.1.3 Berthing systems. For the purpose of assigning structural ratings and documenting the condition of mechanical and electrical systems, an MOT shall be divided into independent “berthing systems.” A berthing system consists of the wharf and supporting structure, mechanical and electrical components that serve the berth and pipeline systems.

For example, a MOT consisting of wharves with three berths adjacent to the shoreline could contain three inde- pendent “berthing systems” if the piping does not route through adjacent berths. Therefore, a significant defect that would restrict the operation of one berth would have

no impact on the other two berths. Conversely, if a T-head Pier, with multiple berths sharing a trestle that supports all piping to the shoreline, had a significant deficiency on the common trestle, the operation of all berths could be adversely impacted. This configuration is classified as a single berthing system.

The physical boundaries of a berthing system may exclude unused sections of a structure. Excluded sections must be physically isolated from the berthing system. Expansion joints may provide this isolation.

3102F.1.4 Records. All MOTs shall have records reflect- ing current, “as-built” conditions for all berthing systems. Records shall include, but not be limited to modifications and/or replacement of structural components, electrical or mechanical equipment or relevant operational changes, new construction including design drawings, calculations, engineering analyses, soil borings, equipment manuals, specifications, shop drawings, technical and maintenance manuals and documents.

Chronological records and reports of annual inspec- tions, audits and post-event inspections and documenta- tion of equipment or structural changes shall be maintained.

Records shall be indexed and be readily accessible to the Division (see 2 CCR Section 2320 (c) (2)) [2.1].

3102F.1.5 Baseline assessment. If “as-built” or subse- quent modification drawings are not available, incomplete or inaccurate, a baseline inspection is required to gather data in sufficient detail for adequate evaluation.

The level of detail required shall be such that structural member sizes, connection and reinforcing details are doc- umented, if required in the structural analysis. In addition,

TABLE 31F-2-1 MAXIMUM INTERVAL BETWEEN UNDERWATER INSPECTIONS (YEARS) 1

INSPECTION
CONDITION
ASSESSMENT
RATING (ICAR)6
CONSTRUCTION MATERIAL CHANNEL BOTTOM
OR MUDLINE—SCOUR4
INSPECTION
CONDITION
ASSESSMENT
_RATING (ICAR)6 _
Unwrapped Timber or Unprotected Steel
(no coating or cathodic protection)4
Unwrapped Timber or Unprotected Steel
(no coating or cathodic protection)4
Concrete, Wrapped Timber, Protected Steel
or Composite Materials (FRP, plastic, etc.)4
Concrete, Wrapped Timber, Protected Steel
or Composite Materials (FRP, plastic, etc.)4
Concrete, Wrapped Timber, Protected Steel
or Composite Materials (FRP, plastic, etc.)4
Concrete, Wrapped Timber, Protected Steel
or Composite Materials (FRP, plastic, etc.)4
INSPECTION
CONDITION
ASSESSMENT
_RATING (ICAR)6 _
Benign2
Environment
_Aggressive3 _
Environment
Benign2
Environment
_Aggressive3 _
Environment
Benign2
Environment
_Aggressive3 _
Environment
6 (Good) 6 4 6 5 6 5
5 (Satisfactory) 6 4 6 5 6 5
4 (Fair) 5 3 5 4 6 5
3 (Poor) 4 3 5 4 6 5
2 (Serious) 2 1 2 2 2 2
1 (Critical) N/A5 N/A5 N/A5 N/A5 N/A5 N/A5

1. The maximum interval between Underwater Inspections shall be changed as appropriate, with the approval of the Division, based on the extent of deterioration observed on a structure, the rate of further anticipated deterioration or other factors. 2. Benign environments include fresh water and maximum current velocities less than 1.5 knots for the majority of the days in a calendar year. 3. Aggressive environments include brackish or salt water, polluted water or waters with current velocities greater than 1.5 knots for the majority of the days in the calendar year. 4. For most structures, two maximum intervals will be shown in this table, one for the assessment of construction material (timber, concrete, steel, etc.) and one for scour (last 2 columns). The shorter interval of the two should dictate the maximum interval used. 5. MOTs rated “Critical” will not be operational; and Emergency Action shall be required in accordance with Table 31F-2-6. 6. ICARs shall be assigned in accordance with Table 31F-2-4.

31F-6 2022 CALIFORNIA BUILDING CODE

Copyright © 2022 by, or licensed to, International Code Council, Inc. (ALL RIGHTS RESERVED); licensed to California Building Standards Commission pursuant to License Agreement. No further reproductions is authorized. Any unauthorized reproduction or distribution is a violation of the federal copyright act and the license agreement, and subject to civil and criminal penalties thereunder.

the strength and/or ductility characteristics of construc- tion materials shall be determined, as appropriate. Nonde- structive testing, partially destructive testing and/or laboratory testing methods may be used.

All fire, piping, mechanical and electrical systems shall be documented as to location, capacity, operating limits and physical conditions in the equipment layout dia- gram(s).

3102F.2 Annual compliance inspection.

The Division may carry out annual inspections to determine the compliance status of the MOT with this code, based on the terminal’s audit and inspection findings and action plan implementation (see Section 3102F.3.9).

These inspections may include a visual and tactile assess- ment of structural, mechanical and electrical systems of the topside and underside areas of the dock, including the splash zone. Subject to operating procedures, a boat shall be pro- vided to facilitate the inspection of the dock undersides and piles down to the splash zone.

3102F.3 Audits.

3102F.3.1 Objective. The objective of the audit is to review structural, mechanical and electrical systems on a prescribed periodic basis to verify that each berthing sys- tem is fit for its specific defined purpose. The audit includes above water and underwater inspections, engi- neering evaluation, documentation and recommended fol- low-up actions.

3102F.3.2 Overview. The audit shall include above water and underwater inspections, and structural, electrical and mechanical systems evaluations, with supporting docu- mentation, drawings and follow-up actions. Structural sys- tems shall include seismic, operational, mooring, berthing and geotechnical considerations. Mechanical systems shall include fire, piping/pipelines and mechanical equip- ment considerations. The audit is performed by a multi- disciplinary team of engineers, qualified inspectors and may include Division representatives.

The above water inspection involves an examination of all structural, mechanical and electrical components above the waterline. Structural defects and their severity shall be documented, but the exact size and location of each deficiency is typically not required.

The underwater inspection involves an examination of all structural, mechanical and electrical components below the waterline. A rational and representative under- water sampling of piles may be acceptable with Division approval, for cases of limited visibility, heavy marine growth, restricted inspection times because of environ- mental factors (currents, water temperatures, etc.) or a very large number of piles.

Global operational structural assessment rating(s) (OSAR), global seismic structural assessment rating(s) (SSAR) and global inspection condition assessment rat- ing(s) (ICAR) shall be assigned to each structure and over- all berthing system, where appropriate (Table 31F-2-4).

Remedial action priorities (RAP) shall be assigned for component deficiencies (Table 31F-2-5). Recommenda-

MARINE OIL TERMINALS

tions for remediation and/or upgrading shall be pre- scribed as necessary.

An audit is not considered complete until the audit report is received (in electronic and hard copy formats) by the Division.

3102F.3.3 Schedule.

3102F.3.3.1 Initial audit. For a new MOT or new berthing system(s), the initial audit of the “as-built” systems(s) shall be performed prior to commencement of operations.

3102F.3.3.2 Subsequent audits. A subsequent audit of each terminal shall be completed concurrently with the inspections (see Section 3102F.3.5). The audit team leader shall recommend either: (1) a default subse- quent audit interval of 4 years, or (2) an alternate interval, based on assessments of the structural, mechanical and electrical systems, and consideration of:

1. The extent of the latest deterioration and/or dis- repair,

2. The rate of future anticipated deterioration and/ or disrepair,

3. The underwater inspection guidance provided in Table 31F-2-1, and

4. Other specified factors.

Based on independent assessment of these factors, the Division may accept the audit team leader’s recom- mendation or require a different subsequent audit interval.

If there are no changes in the defined purpose (see Section 3102F.3.6.1) of the berthing system(s), relevant prior analyses may be referenced. However, if there is a significant change in the operations or condition of berthing system(s), a new analysis may be required.

The Division may require an audit, inspection or supplemental evaluations to justify changes in the use of the berthing system(s).

3102F.3.4 Audit team.

3102F.3.4.1 Project manager. The audit shall be con- ducted by a multidisciplinary team under the direction of a project manager representing the MOT. The proj- ect manager shall have specific knowledge of the MOT and may serve other roles on the audit team.

3102F.3.4.2 Audit team leader. The audit team leader shall lead the on-site audit team and shall be responsi- ble for directing field activities, including the inspec- tion of all structural, mechanical and electrical systems. The team leader shall be a California regis- tered civil or structural engineer and may serve other roles on the audit team.

3102F.3.4.3 Structural inspection team.

The structural inspection shall be conducted under the direction of a registered civil or structural engineer.

All members of the structural inspection team shall be graduates of a 4-year civil/structural engineering,

Copyright © 2022 by, or licensed to, International Code Council, Inc. (ALL RIGHTS RESERVED); licensed to California Building Standards Commission pursuant to License Agreement. No further reproductions is authorized. Any unauthorized reproduction or distribution is a violation of the federal copyright act and the license agreement, and subject to civil and criminal penalties thereunder.

MARINE OIL TERMINALS

or closely related (ocean/coastal) engineering curricu- lum, and shall have been certified as an Engineer-in- Training; or shall be technicians who have completed a course of study in structural inspections. The minimum acceptable course in structural inspections shall include 80 hours of instruction specifically related to structural inspection, followed by successful comple- tion of a comprehensive examination. An example of an acceptable course is the U.S. Department of Transpor- tation’s “Safety Inspection of In- Service Bridges.” Certification as a Level IV Bridge Inspector by the National Institute of Certification in Engineering Tech- nologies (NICET) shall also be acceptable [2.2].

For underwater inspections, the registered civil or structural engineer directing the underwater structural inspection shall also be a commercially trained diver or equivalent and shall actively participate in the inspection, by personally conducting a minimum of 25 percent of the underwater examination [2.2].

Each underwater team member shall also be a com- mercially trained diver, or equivalent. Divers perform- ing manual tasks such as cleaning or supporting the diving operation, but not conducting or reporting on inspections, may have lesser technical qualifications

[2.2].

3102F.3.4.4 Structural analyst.

A California regis- tered civil or structural engineer shall be in responsible charge of the structural evaluations.

3102F.3.4.5 Electrical inspection team. A registered electrical engineer shall direct the on-site team per- forming the inspection and evaluation of electrical components and systems.

3102F.3.4.6 Mechanical inspection team. A registered engineer shall direct the on-site team performing the inspection and evaluation of piping/pipeline, mechani- cal and fire components and systems, except the Fire Protection Assessment in accordance with Section 3108F.2.2.

3102F.3.4.7 Corrosion specialist.

The corrosion spe- cialist shall be a chemical engineer, corrosion engi- neer, chemist or other professional with expertise in the types and causes of corrosion, and available means to prevent, monitor and mitigate associated damage. The specialist shall perform the corrosion assessment (Sec- tion 3102F.3.6.5) and may be directly involved in cor- rosion inspection (Section 3102F.3.5.4).

3102F.3.4.8 Geotechnical analyst. A California regis- tered civil engineer with a California authorization as a geotechnical engineer shall perform the geotechnical evaluation required for the audit and all other geotech- nical evaluations.

3102F.3.4.9 Division representation.

The Division representative(s) may participate in any audit or inspection as observer(s). The Division shall be notified in advance of audit-related inspections. 3102F.3.5 Scope of inspections.

3102F.3.5.1 Structural inspections.

3102F.3.5.1.1 Above water structural inspection. The above water inspection shall include all acces- sible components above and below deck that are reachable without the need for excavation or exten- sive removal of materials that may impair visual inspection. The above water inspection shall include, but not be limited to, the following:

1. Piles

2. Pile caps

3. Beams

4. Deck soffit

5. Bracing

6. Retaining walls and bulkheads

7. Connections

8. Seawalls

9. Slope protection

10. Deck topsides and curbing

11. Expansion joints

12. Fender system components

13. Dolphins and deadmen

14. Mooring points and hardware

15. Navigation aids

16. Platforms, ladders, stairs, handrails and gangways

17. Backfill (sinkholes/differential settlement)

3102F.3.5.1.2 Underwater structural inspection.

The underwater inspection shall include all compo- nents below deck to the mudline, including the slope and slope protection, in areas immediately sur- rounding the MOT. The water depth at the berth(s) shall be evaluated, verifying the maximum or loaded draft specified in the MOT’s Operations Manual (2 CCR 2385) [2.1].

The underwater structural inspection shall include the Level I, II and III inspection efforts, as shown in Tables 31F-2-2 and 31F-2-3. The underwater inspec- tion levels of effort are described below, per [2.2]:

Level I—Includes a close visual examination, or a tactile examination using large sweeping motions of the hands where visibility is limited. Although the Level I effort is often referred to as a “swim-by” inspection, it must be detailed enough to detect obvi- ous major damage or deterioration due to overstress or other severe deterioration. It should confirm the continuity of the full length of all members and detect undermining or exposure of normally buried ele- ments. A Level I effort may also include limited prob- ing of the substructure and adjacent channel bottom.

Level II—A detailed inspection which requires marine growth removal from a representative sam- pling of components within the structure. For piles, a 12-inch high band shall be cleaned at designated locations, generally near the low waterline, at the

31F-8 2022 CALIFORNIA BUILDING CODE

Copyright © 2022 by, or licensed to, International Code Council, Inc. (ALL RIGHTS RESERVED); licensed to California Building Standards Commission pursuant to License Agreement. No further reproductions is authorized. Any unauthorized reproduction or distribution is a violation of the federal copyright act and the license agreement, and subject to civil and criminal penalties thereunder.

mudline, and midway between the low waterline and the mudline. On a rectangular pile, the marine growth removal should include at least three sides; on an octagon pile, at least six sides; on a round pile, at least three-fourths of the perimeter. On large diam- eter piles, 3 ft or greater, marine growth removal should be effected on 1 ft by 1 ft areas at four loca- tions approximately equally spaced around the perimeter, at each elevation. On large solid faced ele- ments such as retaining structures, marine growth removal should be effected on 1 ft by 1 ft areas at the three specified elevations. The inspection should also focus on typical areas of weakness, such as attach- ment points and welds. The Level II effort is intended

MARINE OIL TERMINALS

to detect and identify damaged and deteriorated areas that may be hidden by surface biofouling. The thoroughness of marine growth removal should be governed by what is necessary to discern the condi- tion of the underlying structural material. Removal of all biofouling staining is generally not required.

Level III—A detailed inspection typically involv- ing nondestructive or partially-destructive testing, conducted to detect hidden or interior damage, or to evaluate material homogeneity. Level III testing is generally limited to key structural areas, areas which are suspect or areas which may be represen- tative of the underwater structure.

TABLE 31F-2-2

UNDERWATER INSPECTION LEVELS OF EFFORT [2.2]

LEVEL PURPOSE DETECTABLE DEFECTS
LEVEL PURPOSE Steel Concrete Timber Composite
I General visual/tactile
inspection to confirm as-
built condition and detect
severe damage
Extensive corrosion, holes
Severe mechanical damage
Major spalling and cracking
Severe reinforcement corrosion
Broken piles
Major loss of section
Broken piles and bracings
Severe abrasion or marine
borer attack
Permanent deformation
Broken piles
Major cracking or
mechanical damage
II To detect surface defects
normally obscured by
marine growth
Moderate mechanical damage
Corrosion pitting and loss of
section
Surface cracking and spalling
Rust staining
Exposed reinforcing steel and/
or prestressing strands
External pile damage due to
marine borers
Splintered piles
Loss of bolts and fasteners
Rot or insect infestation
Cracking
Delamination
Material degradation
III To detect hidden or
interior damage, evaluate
loss of cross-sectional
area or evaluate material
homogeneity
Thickness of material
Electrical potentials for
cathodic protection
Location of reinforcing steel
Beginning of corrosion of
reinforcing steel
Internal voids
Change in material strength
Internal damage due to
marine borers (internal
voids)
Decrease in material
strength
N/A
TABLE 31F-2-3 SCOPE OF UNDERWATER INSPECTION [2.2]
LEVEL SAMPLE SIZE AND METHODOLOGY1 SAMPLE SIZE AND METHODOLOGY1 SAMPLE SIZE AND METHODOLOGY1 SAMPLE SIZE AND METHODOLOGY1 SAMPLE SIZE AND METHODOLOGY1 SAMPLE SIZE AND METHODOLOGY1 SAMPLE SIZE AND METHODOLOGY1 SAMPLE SIZE AND METHODOLOGY1
LEVEL Steel Steel Concrete Concrete Timber Timber Composite Slope
Protection,
Channel
Bottom or
Mudline-Scour
LEVEL Piles Bulkheads/
Retaining Walls
Piles Bulkheads/
Retaining Walls
Piles Bulkheads/
Retaining Walls
Piles Piles
I Sample Size:
Method:
100%
Visual/Tactile
100%
Visual/Tactile
100%
Visual/Tactile
100%
Visual/Tactile
100%
Visual/Tactile
100%
Visual/Tactile
100%
Visual/Tactile
100%
Visual/Tactile
II Sample Size:
Method:
10%
Visual:
Removal of
marine
growth in 3
bands
Every 100 LF
Visual: Removal
of marine
growth in 1 SF
areas
10%
Visual:
Removal of
marine growth
in 3 bands
Every 100 LF
Visual: Removal
of marine
growth in 1 SF
areas
10%
Visual:
Removal of
marine growth
on 3 bands
Measurement:
Remaining
diameter
Every 50 LF
Visual:
Removal of
marine growth
in 1 SF areas
10%
Visual:
Removal of
marine growth
in 3 bands
As necessary
III Sample Size:
Method:
5%
Remaining
thickness
measurement;
electrical
potential
measurement;
corrosion
profiling as
necessary
Every 200 LF
Remaining
thickness
measurement;
electrical
potential
measurement;
corrosion
profiling as
necessary
0%
N/A
0%
N/A
5%
Internal
marine borer
infestation
evaluation
Every 100 LF
Internal marine
borer
infestation
evaluation
0% Sonar imaging
as necessary

1. The minimum inspection sampling size for small structures shall include at least two components. LF = Linear Feet; SF = Square Feet; N/A = Not Applicable

Copyright © 2022 by, or licensed to, International Code Council, Inc. (ALL RIGHTS RESERVED); licensed to California Building Standards Commission pursuant to License Agreement. No further reproductions is authorized. Any unauthorized reproduction or distribution is a violation of the federal copyright act and the license agreement, and subject to civil and criminal penalties thereunder.

MARINE OIL TERMINALS

3102F.3.5.2 Special inspection considerations.

3102F.3.5.2.1 Coated components. For coated steel components, Level I and Level II efforts should focus on the evaluation of the integrity and effectiveness of the coating. The piles should be inspected without damaging the coating. Level III efforts should include ultrasonic thickness measurements without removal of the coating, where feasible.

3102F.3.5.2.2 Encased components. For steel, con- crete or timber components that have been encased, the Level I and II efforts should focus on the evalua- tion of the integrity of the encasement. If evidence of significant damage to the encasement is present, or if evidence of significant deterioration of the under- lying component is present, then the damage evalua- tion should consider whether the encasement was provided for protection and/or structural capacity. Encasements should not typically be removed for an audit.

For encasements on which the formwork has been left in place, the inspection should focus on the integrity of the encasement, not the formwork. Level I and Level II efforts in such cases should concentrate on the top and bottom of the encase- ment. For concrete components, if deterioration, loss of bonding or other significant problems with the encasement are suspected, it may be necessary to conduct a special inspection, including coring of the encasement and laboratory evaluation of the materials.

3102F.3.5.2.3 Wrapped components.

For steel, concrete or timber components that have been wrapped, the Level I and II efforts should focus on the evaluation of the integrity of the wrap. Since the effectiveness of a wrap may be compromised by removal, and since the removal and re-installation of wraps is time-consuming, it should not be rou- tinely done. However, if evidence of significant dam- age exists, or if the effectiveness of the wraps is in question, then samples should be removed to facili- tate the inspection and evaluation. The samples may be limited to particular zones or portions of mem- bers if damage is suspected, based on the physical evidence of potential problems. A minimum sample size of three members should be used. A five-percent sample size, up to 30 total members, may be ade- quate as an upper limit.

For wrapped timber components, Level III efforts should consist of removal of the wraps from a representative sample of components in order to evaluate the condition of the timber beneath the wrap. The sample may be limited to particular zones or portions of the members if damage is suspected (e.g., at the mudline/ bottom of wrap or in the tidal zone). The sample size should be determined based on the physical evidence of potential problems and the aggressiveness of the environment. A minimum sample size of three members should be used. A five-

percent sample size, up to 30 total members, may be adequate as an upper limit.

3102F.3.5.3 Mechanical and electrical inspections.

The mechanical and electrical inspections shall include but not be limited to the following:

1. Loading arms

2. Cranes and lifting equipment, including cables

3. Piping/manifolds and supports

4. Oil transfer hoses

5. Fire detection and suppression systems

6. Vapor control system

7. Sumps/sump tanks

8. Vent systems

9. Pumps and pump systems

10. Lighting

11. Communications equipment

12. Gangways

13. Electrical switches and junction boxes

14. Emergency power equipment

15. Air compressors

16. Meters

17. Cathodic protection systems

18. Winches

19. ESD and other control systems

20. Ladders

All alarms, limit switches, load cells, current meters, anemometers, leak detection equipment, etc., shall be operated and/or tested to the extent feasible, to ensure proper function.

Utility, auxiliary and fire protection piping shall have external visual inspections, similar to that defined in Section 10.1 of API RP 574 [2.3] (N/E).

3102F.3.5.4 Corrosion inspection.

During each audit, a comprehensive corrosion inspection shall be per- formed by a qualified engineer or technician. This inspection shall include all steel and metallic compo- nents, and any installed cathodic protection system (CPS). CPS inspection during the audit is not intended to substitute for required testing and maintenance per- formed on a more frequent schedule per Section 3111F.10. All inspection results shall be documented, and shall be used in the corrosion assessment (Section

3102F.3.6.5).

Submerged wharf structures and associated cathodic protection equipment (if installed) shall be inspected per [2.2]. Above water structures, ancillary equipment, supports and hardware shall be visually inspected. Corrosion inspection of utility, auxiliary and fire pipelines shall be done per Section 3102F.3.5.3.

For oil pipelines in an API 570 [2.4] inspection program, a corrosion inspection is not required as part

31F-10 2022 CALIFORNIA BUILDING CODE

Copyright © 2022 by, or licensed to, International Code Council, Inc. (ALL RIGHTS RESERVED); licensed to California Building Standards Commission pursuant to License Agreement. No further reproductions is authorized. Any unauthorized reproduction or distribution is a violation of the federal copyright act and the license agreement, and subject to civil and criminal penalties thereunder.

of the audit; however, the latest inspection results, cal- culations and conclusions shall be reviewed, and any significant results shall be included in the corrosion assessment.

3102F.3.6 Evaluation and assessment.

3102F.3.6.1 Terminal operating limits. The physical boundaries of the facility shall be defined by the berth- ing system operating limits, along with the vessel size limits and environmental conditions.

The audit shall include “Terminal Operating Lim- its” (TOLs) diagrams, which provide a concise state- ment of the purpose of each berthing system in terms of operating limits for representative vessel size ranges and mooring configurations approved to call and/or conduct transfer operations at the MOT. This descrip- tion shall include, the minimum and maximum vessel sizes, including Length Overall (LOA), beam and maxi- mum draft with associated displacement (see Figure 31F-2-1).

In establishing limits for both the minimum and maximum vessel sizes, due consideration shall be given to water depths, dolphin spacing, fender system limita- tions, manifold height and hose/loading arm reach, with allowances for tidal fluctuations, surge and drift.

Maximum wind, current or wave conditions, or combinations thereof, shall be clearly defined as limit- ing conditions for vessels at each berth, both with and without active product transfer.

The TOLs shall be explicitly presented to facilitate implementation by the MOT operator, such as through incorporation in the MOT’s Operations Manual (2 CCR 2385 [2.1]). The TOLs shall allow for direct com- parison of operating limits and output from monitoring systems and instrumentation (i.e., anemometers, cur- rent meters, tension monitoring systems, velocity moni- toring systems). Design and implementation considerations shall include, but not be limited to:

1. Units of measurement (i.e., English vs. System International units)

2. Directionality (i.e., current restrictions “to”, wind restrictions “from”, true or magnetic north)

3. Parameters of monitoring systems and instru- mentation (i.e., duration/averaging of readings, elevation/depth of readings, distance/location of readings)

3102F.3.6.2 Mooring and berthing.

Mooring and berthing analyses shall be performed in accordance with Section 3105F. The analyses shall be consistent with the terminal operating limits and the structural configuration of the wharf and/or dolphins and associ- ated hardware.

Based on inspection results, analyses and engineer- ing judgment, mooring and berthing OSARs shall be assigned on a global basis, independently for each

MARINE OIL TERMINALS

structure and overall berthing system. The OSARs defined in Table 31F-2-4 shall be used for this purpose. The mooring and berthing OSARs document the berth- ing system(s) fitness-for-purpose.

3102F.3.6.3 Structure.

A structural evaluation, includ- ing a seismic analysis, shall be performed in accor- dance with Sections 3103F through 3107F. Such evaluation shall consider local or global reduction in capacity, as determined from the inspection.

Based on inspection results, structural analyses and engineering judgment, OSARs (for operational load- ing) and SSARs shall be assigned on a global basis, independently for each structure, structural system(s) and berthing system(s), as appropriate. The OSARs and SSARs defined in Table 31F-2-4 shall be used for this purpose and document the structural and/or berthing system(s) fitness-for-purpose.

Based on inspection results and engineering judg- ment, ICARs shall be assigned on a global basis, inde- pendently for each above and underwater structure, structural system and berthing system, as appropriate. The ICARs defined in Table 31F-2-4 shall be used for this purpose.

Structural component deficiencies assigned RAPs as per Table 31F-2-5 shall be considered in the OSARs, SSARs and ICARs. The assigned ratings shall remain in effect until all the significant corrective action has been completed to the satisfaction of the Division, or until completion of the next audit.

3102F.3.6.4 Mechanical and electrical systems.

An evaluation of all mechanical and electrical systems and components shall be performed in accordance with Sec- tions 3108F through 3111F of these standards. Forces and imposed seismic displacements resulting from the structural analysis shall be considered in the pipeline stress analyses (Section 3109F.3), and the piping/pipe- lines shall be assigned SSARs in Table 31F-2-7B. Mechanical and electrical component deficiencies shall be assigned ratings from Table 31F-2-5.

3102F.3.6.5 Corrosion assessment (N/E).

A compre- hensive assessment shall be performed by the corrosion specialist (Section 3102F.3.4.7), to determine the exist- ing and potential corrosion using “as-built” drawings and specifications. This assessment shall comprise all steel and metallic components, including the structure, pipelines, supports and other MOT ancillary equip- ment. This assessment shall also include prestressed and reinforced concrete structures.

If cathodic protection is installed to protect wharf structures and/or pipelines, the following records shall be evaluated for each system:

1. CPS equipment condition and maintenance

2. Impressed current readings (as applicable)

3. Potential survey results

Copyright © 2022 by, or licensed to, International Code Council, Inc. (ALL RIGHTS RESERVED); licensed to California Building Standards Commission pursuant to License Agreement. No further reproductions is authorized. Any unauthorized reproduction or distribution is a violation of the federal copyright act and the license agreement, and subject to civil and criminal penalties thereunder.

MARINE OIL TERMINALS

TABLE 31F-2-4 ASSESSMENT RATINGS
RATING RATING DESCRIPTION OF STRUCTURE(S) AND/OR SYSTEMS4 DESCRIPTION OF STRUCTURE(S) AND/OR SYSTEMS4
RATING RATING _OSAR1 and SSAR2 _ ICAR3
6 Good The capacity of the structure or system meets the requirements
of this standard.
The structure or system should be considered fit-for-purpose.
No repairs or upgrades are required.
No problems or only minor problems noted. Structural elements may
show very minor deterioration, but no overstressing observed.
No repairs or upgrades are required.
5 Satisfactory The capacity of the structure or system meets the requirements
of this standard.
The structure or system should be considered fit-for-purpose.
No repairs or upgrades are required.
Limited minor to moderate defects or deterioration observed, but no
overstressing observed.
No repairs or upgrades are required.
4 Fair The capacity of the structure or system is no more than 15
percent below the requirements of this standard, as
determined from an engineering evaluation.
The structure or system should be considered as marginal.
Repair and/or upgrade measures may be required to remain
operational. Facility may remain operational, provided a plan
and schedule for remedial action is presented to and accepted
by the Division.
All primary structural elements are sound, but minor to moderate
defects or deterioration observed. Localized areas of moderate to
advanced deterioration may be present, but do not significantly reduce
the load bearing capacity of the structure.
Repair and/or upgrade measures may be required to remain operational.
Facility may remain operational, provided a plan and schedule for
remedial action is presented to and accepted by the Division.
3 Poor The capacity of the structure or system is no more than 25
percent below the requirements of this standard, as
determined from an engineering evaluation.
The structure or system is not fit-for-purpose. Repair and/or
upgrade measures may be required to remain operational. The
facility may be allowed to remain operational on a restricted
or contingency basis until the deficiencies are corrected,
provided a plan and schedule for such work is presented to
and accepted by the Division.
Advanced deterioration or overstressing observed on widespread
portions of the structure, but does not significantly reduce the load
bearing capacity of the structure.
Repair and/or upgrade measures may be required to remain
operational. The facility may be allowed to remain operational on a
restricted or contingency basis until the deficiencies are corrected,
provided a plan and schedule for such work is presented to and
accepted by the Division.
2 Serious The capacity of the structure or system is more than 25 percent
below the requirements of this standard, as determined from
an engineering evaluation.
The structure or system is not fit-for-purpose. Repairs and/or
upgrade measures may be required to remain operational. The
facility may be allowed to remain operational on a restricted
basis until the deficiencies are corrected, provided a plan and
schedule for such work is presented to and accepted by the
Division.
Advanced deterioration, overstressing or breakage may have
significantly affected the load bearing capacity of primary structural
components. Local failures are possible and loading restrictions may be
necessary.
Repairs and/or upgrade measures may be required to remain
operational. The facility may be allowed to remain operational on a
restricted basis until the deficiencies are corrected, provided a plan and
schedule for such work is presented to and accepted by the Division.
1 Critical The capacity of the structure or system is critically deficient
relative to the requirements of this standard.
The structure or system is not fit-for-purpose. The facility shall
cease operations until deficiencies are corrected and accepted
by the Division.
Very advanced deterioration, overstressing or breakage has resulted in
localized failure(s) of primary structural components. More widespread
failures are possible or likely to occur and load restrictions should be
implemented as necessary.
The facility shall cease operations until deficiencies are corrected and
accepted by the Division.

1. OSAR = Operational Structural Assessment Ratings 2. SSAR = Seismic Structural Assessment Ratings 3. ICAR = Inspection Condition Assessment Ratings [2.2]; Ratings shall be assigned comparing the observed condition to the as-built condition. 4. Structural, mooring or berthing systems

TABLE 31F-2-5 COMPONENT DEFICIENCY REMEDIAL ACTION PRIORITIES (RAP)
REMEDIAL
PRIORITIES
DESCRIPTION AND REMEDIAL ACTIONS
P1 Specified whenever a condition that poses an immediate threat to public health, safety or the environment is observed. Emergency Actionsmay
consist of barricading or closing all or portions of the berthing system, evacuating product lines and ceasing transfer operations.
The berthing system is not fit-for-purpose.Immediate remedial actions are required prior to the continuance of normal operations.
P2 Specified whenever defects or deficiencies pose a potential threat to public health, safety and the environment. Actions may consist of limiting
or restricting operations until remedial measures have been completed.
The berthing system is not fit-for-purpose. This priority requires investigation, evaluation and urgent action.
P3 Specified whenever systems require upgrading in order to comply with the requirement of these standards or current applicable codes. These
deficienciesdo not require emergency or urgent actions.
The MOT may have limitations placed on its operational status.
P4 Specified whenever damage or defects requiring repair are observed.
The berthing system is fit-for-purpose. Repair can be performed during normal maintenance cycles, but not to exceed one year.
R Recommended action is a good engineering/maintenance practice, but not required by these standards.
The berthing system is fit-for-purpose.

31F-12 2022 CALIFORNIA BUILDING CODE

Copyright © 2022 by, or licensed to, International Code Council, Inc. (ALL RIGHTS RESERVED); licensed to California Building Standards Commission pursuant to License Agreement. No further reproductions is authorized. Any unauthorized reproduction or distribution is a violation of the federal copyright act and the license agreement, and subject to civil and criminal penalties thereunder.

MARINE OIL TERMINALS

TABLE 31F-2-6 FOLLOW-UP ACTIONS [2.2]
FOLLOW-UP ACTION DESCRIPTION
Emergency Action Specified whenever a condition which poses an immediate threat to public health, safety or the environment is
observed. Emergency Actions may consist of barricading or closing all or portions of the berthing system, limiting
vessel size, placing load restrictions, evacuating product lines, ceasing transfer operations, etc.
Engineering Evaluation Specified whenever damage or deficiencies are observed which require further investigation or evaluation to
determine appropriate follow-up actions.
Repair Design Inspection Specified whenever damage or defects requiring repair are observed. The repair design inspection is performed to the
level of detail necessary to prepare appropriate repair plans, specifications and estimates.
Upgrade Design and Implementation Specified whenever the system requires upgrading in order to comply with the requirements of these standards and
current applicable codes.
Special Inspection Typically specified to determine the cause or significance of nontypical deterioration, usually prior to designing
repairs. Special testing, laboratory analysis, monitoring or investigation using nonstandard equipment or techniques
are typically required.
Develop and Implement Repair Plans Specified when the Repair Design Inspection and required Special Inspections have been completed. Indicates that
the structure is ready to have repair plans prepared and implemented.
No Action Specified when no further action is necessary until the next scheduled audit or inspection.

3102F.3.7 Follow-up actions.

Follow-up actions per Table 31F-2-6 shall be prescribed by the audit team. Mul- tiple follow-up actions may be assigned; however, guid- ance shall be provided as to the order in which the follow- up actions should be carried out.

If an assessment rating of “1”, “2” or “3” (Table 31F- 2-4) or a RAP of “P1” or “P2” (Table 31F-2-5) or “Emer- gency Action” using Table 31F-2-6, is assigned to a struc- ture, berthing system or critical component, the Division shall be notified immediately. The Executive Summary Table ES-2 (see Example Table 31F-2-8) shall include implementation schedules for all follow-up and remedial actions. Follow-up and remedial actions and implementa- tion schedules are subject to Division approval.

For action plan implementation between audits, see Section 3102F.3.9.

3102F.3.8 Documentation and reporting.

The audit reports shall be signed and stamped by the audit team leader. The inspection and other reports and drawings shall be signed and stamped by the engineers in responsi- ble charge.

Each audit and inspection, whether partial or com- plete, shall be adequately documented. Partial inspections cover only specific systems or equipment examined. The resulting reports shall summarize and reference relevant previous ratings and deficiencies. Inspection reports shall be included in subsequent audits.

The contents of the audit and inspection reports for each berthing system shall, at a minimum, include the fol- lowing as appropriate:

Executive summary— a concise narrative of the audit or inspection results and analyses conclusions. It shall include summary information for each berthing system, including an overview of the assigned follow-up actions. The Executive Summary Tables shall also be included (see Example Tables 31F-2-7A through 31F- 2-7C and 31F-2-8).

Table of contents

Introduction— a brief description of the purpose and scope of the audit or inspection, as well as a descrip- tion of the inspection/evaluation methodology used.

Existing conditions— a description, along with a sum- mary, of the observed conditions. Subsections shall be used to describe the above water structure, underwater structure, fire, piping/pipeline, mechanical and electri- cal systems, to the extent each are included in the scope of the audit. Photos, plan views and sketches shall be utilized as appropriate to describe the structure and the observed conditions. Details of the inspection results such as test data, measurements data, etc., shall be documented in an appendix.

Evaluation and assessment— assessment ratings shall be assigned to all structures and/or berthing sys- tems. Also, see Section 3102F.3.6. All supporting cal- culations, as-built drawings and documentation shall be included in appendices as appropriate to substanti- ate the ratings. However, the results and recommen- dations of the engineering analyses shall be included in this section. Component deficiencies shall be described and a corresponding RAP assigned. Follow-up actions— Specific follow-up actions (Table 31F-2-6) shall be documented (Table 31F-2-8), and remedial schedules included, for each audited system. Audit team leaders shall specify which follow-up actions require a California registered engineer to cer- tify that the completion is acceptable.

Appendices— When appropriate, the following appen- dices shall be included:

1. Background data on the terminal - description of the service environment (wind/waves/currents), extent and type of marine growth, unusual envi- ronmental conditions, etc.

2. Inspection/testing data

Copyright © 2022 by, or licensed to, International Code Council, Inc. (ALL RIGHTS RESERVED); licensed to California Building Standards Commission pursuant to License Agreement. No further reproductions is authorized. Any unauthorized reproduction or distribution is a violation of the federal copyright act and the license agreement, and subject to civil and criminal penalties thereunder.

MARINE OIL TERMINALS

3. Mooring and berthing analyses

4. Structural and seismic analyses and calculations

5. Geotechnical report

6. MOT Fire Protection Assessment

7. Pipeline stress and displacement analyses

8. Mechanical and electrical system documentation

9. Corrosion assessment

10. Photographs, sketches and supporting data shall be included to document typical conditions and referenced deficiencies, and to justify the assess- ment ratings and the remedial action priorities RAPs assigned.

3102F.3.9 Action plan implementation between audits.

The operator is responsible for correction of deficiencies between audits. Prior to implementation, projects shall be submitted for Division review in accordance with Sec- tion 3101F.8.3. During project implementation, the Divi- sion shall be informed of any significant changes. After project completion, “as-built” documentation, including drawings, calculations and analyses, shall be submitted to the Division.

Executive Summary Tables shall be updated by the operator and submitted to the Division at least annually.

3102F.4 Post-event notification and inspection.

A post-event inspection is a focused inspection following a significant, potentially damage-causing event such as an earthquake, storm, vessel impact, fire, explosion, construction incident or tsunami. The primary purpose is to assess the integrity of structural, mechanical and electrical systems. This assess- ment will determine the operational status and/or any reme- dial measures required.

3102F.4.1 Notification and action plan. Notification as per 2 CCR 2325(e) [2.1] shall be provided to the local area Division field office. The notification shall include, as a minimum:

1. Brief description of the event 2. Brief description of the nature, extent and signifi- cance of any damage observed as a result of the event 3. Operational status and any required restrictions 4. Statement as to whether a Post-Event inspection will be carried out The Division may carry out or cause to be carried out, a post-event inspection. In the interim, the Division may direct a change in the operations manual, per 2 CCR 2385 (f)(3) [2.1].

If a post-event inspection is required, an action plan shall be submitted to the Division within five (5) days after the event. This deadline may be extended in special cir- cumstances. The action plan shall include the scope of the inspection (above water, underwater, electrical, mechani- cal systems, physical limits, applicable berthing systems, etc.) and submission date of the final report. The action plan is subject to Division approval.

3102F.4.2 Inspection team. The qualifications of the inspection team shall be the same as those prescribed in Section 3102F.3.4. Division representatives may partici- pate in any post-event inspection, as observers, and may provide guidance.

3102F.4.3 Scope. The post-event inspection shall focus on the possible damage caused by the event. General obser- vations of long-term or preexisting deterioration such as significant corrosion-related damage or other deteriora- tion should be made as appropriate, but should not be the focus of the inspection. The inspection shall always include an above-water assessment of structural, mechan- ical and electrical components.

The inspection team leader shall determine the need for, and methodology of, an underwater structural assess- ment, in consultation with the Division. Above water observations, such as shifting or differential settlement, misalignments, significant cracking or spalling, bulging, etc., shall be used to determine whether or not an under- water assessment is required. Similarly, the inspection team leader shall determine, in consultation with the Divi- sion, the need for, and methodology of, any supplemental inspections (e.g., special inspections (see Section 3102F.3.5.3).

The following information may be important in deter- mining the need for, and methodology of, the post-event inspection:

1. Earthquakes or vessel or debris impact typically cause damage both above and below the waterline. Following a major earthquake, the inspection should focus on components likely to attract highest lateral loads (batter or shorter piles in the rear of the structure, etc.). In case of vessel or debris impact, the inspection effort should focus on compo- nents in the path of the impact mass.

2. Major floods or tsunamis may cause undermining of the structure and/or scouring at the mudline.

3. Fire damage varies significantly with the type of construction materials but all types may be adversely affected. Special inspections (sampling and laboratory testing) shall be conducted, as deter- mined by the inspection team leader, in order to determine the nature and extent of damage.

4. High wind or wave events often cause damage both above and below the waterline. An underwater inspection may be required if damage is visible above the waterline. Structural damage may be potentially increased if a vessel was at the berth during the event. The effects of high wind may be most prevalent on equipment and connections of such equipment to the structure.

The methodology of conducting an underwater post- event inspection should be established with due consider- ation of the structure type and type of damage anticipated. Whereas slope failures or scour may be readily apparent in waters of adequate visibility, overstressing cracks on

31F-14 2022 CALIFORNIA BUILDING CODE

Copyright © 2022 by, or licensed to, International Code Council, Inc. (ALL RIGHTS RESERVED); licensed to California Building Standards Commission pursuant to License Agreement. No further reproductions is authorized. Any unauthorized reproduction or distribution is a violation of the federal copyright act and the license agreement, and subject to civil and criminal penalties thereunder.

piles covered with marine growth will not be readily apparent. Where such hidden damage is suspected, marine growth removal should be performed on a representative sampling of components in accordance with the Level II effort requirements described in Section 3102F.3.5.2. The cause of the event will determine the appropriate sample size and locations.

3102F.4.4 Post-event ratings. A post-event rating [2.2] shall be assigned to each berthing system upon completion of the inspection (see Table 31F-2-9). All observations of the above and under water structure, mechanical and electrical components and systems shall be considered in assigning a post-event rating.

Ratings should consider only damage that was likely caused by the event. Pre-existing deterioration such as cor- rosion damage should not be considered unless the struc- tural integrity is immediately threatened or safety systems or protection of the environment may be compromised.

Assignment of ratings should reflect an overall charac- terization of the berthing system being rated. The rating shall consider both the severity of the deterioration and the extent to which it is widespread throughout the facility. The fact that the facility was designed for loads that are lower than the current standards for design should have no influence upon the ratings.

3102F.4.5 Follow-up actions. Follow-up actions shall be assigned upon completion of the post-event inspection of each berthing system. Table 31F-2-5 specifies remedial action priorities for deficiencies. Table 31F-2-6 specifies various follow-up actions. Multiple follow-up actions may be assigned; however, guidance should be provided as to the order in which the follow-up actions should be carried out. Follow-up actions shall be subject to Division approval.

3102F.4.6 Documentation and reporting. Documentation of the specific attributes of each defect shall not be required during a post-event inspection. However, a nar- rative description of significant damage shall be used. The description shall be consistent with and shall justify the post-event rating assigned.

A report shall be prepared and submitted to the Divi- sion upon completion of the post-event inspection and shall, at a minimum, include:

1. Brief description of the facility including the physi- cal limits of the structure, type of construction mate- rial(s), and the mechanical and electrical systems present

2. Brief description of the event triggering the inspec- tion

3. Scope of the inspection (above water, underwater, electrical or mechanical)

4. Date of the inspection

5. Names and affiliations of inspection team

6. Description of the nature, extent and significance of any observed damage resulting from the event

MARINE OIL TERMINALS

7. Photographs should be provided to substantiate the descriptions and justify the condition rating

8. Assignment of a post-event rating

9. Statement regarding whether the facility is fit to resume operations and, if so, under what conditions

10. Assignment of follow-up action(s)

11. Inspection data, drawings, calculations and other relevant engineering materials

12. Signature and stamp of team leader(s)

3102F.4.7 Action Plan Report. Upon completion of all actions delineated in the action plan, a final report shall be submitted to the Division to document the work com- pleted. Supporting documentation such as calculations or other relevant data shall be provided in appendices.

3102F.5 References.

[2.1]California Code of Regulations (CCR), Title 2, Divi-

sion 3, Chapter 1, Article 5 – Marine Terminals Inspection and Monitoring (2 CCR 2300 et seq.)

[2.2]Childs, K.M., editor, 2001, “Underwater Investiga-

tions - Standard Practice Manual,” American Soci- ety of Civil Engineers, Reston, VA.

[2.3]American Petroleum Institute (API), 2009, API Rec-

ommended Practice 574 (API RP 574), “Inspection Practices for Piping System Components,” 3 rd ed., Washington, D.C.

[2.4]American Petroleum Institute (API), 2009, API 570,

“Piping Inspection Code: In-service Inspection, Rat- ing, Repair, and Alteration of Piping Systems,” 3 rd

ed., Washington, D.C. Authority: Sections 8750 through 8760, Public Resources Code

Reference: Sections 8750, 8751, 8755 and 8757, Public Resources Code.

Copyright © 2022 by, or licensed to, International Code Council, Inc. (ALL RIGHTS RESERVED); licensed to California Building Standards Commission pursuant to License Agreement. No further reproductions is authorized. Any unauthorized reproduction or distribution is a violation of the federal copyright act and the license agreement, and subject to civil and criminal penalties thereunder.

MARINE OIL TERMINALS

TABLE 31F-2-7A
EXAMPLE EXECUTIVE SUMMARY TABLE (ES-1A)
GLOBAL OPERATIONAL STRUCTURAL ASSESSMENT RATINGS (OSAR)
EXECUTIVE SUMMARY TABLE (ES-1A)
GLOBAL OPERATIONAL STRUCTURAL ASSESSMENT RATINGS (OSAR)
EXECUTIVE SUMMARY TABLE (ES-1A)
GLOBAL OPERATIONAL STRUCTURAL ASSESSMENT RATINGS (OSAR)
EXECUTIVE SUMMARY TABLE (ES-1A)
GLOBAL OPERATIONAL STRUCTURAL ASSESSMENT RATINGS (OSAR)
EXECUTIVE SUMMARY TABLE (ES-1A)
GLOBAL OPERATIONAL STRUCTURAL ASSESSMENT RATINGS (OSAR)
EXECUTIVE SUMMARY TABLE (ES-1A)
GLOBAL OPERATIONAL STRUCTURAL ASSESSMENT RATINGS (OSAR)
EXECUTIVE SUMMARY TABLE (ES-1A)
GLOBAL OPERATIONAL STRUCTURAL ASSESSMENT RATINGS (OSAR)
EXECUTIVE SUMMARY TABLE (ES-1A)
GLOBAL OPERATIONAL STRUCTURAL ASSESSMENT RATINGS (OSAR)
EXECUTIVE SUMMARY TABLE (ES-1A)
GLOBAL OPERATIONAL STRUCTURAL ASSESSMENT RATINGS (OSAR)
REV. #
MM/YYYY
Berthing
system
Berth(s)1 Structure(s)1 Type of
analysis2
OSAR
rating4
Last
audit date
(MM/YYYY)
Next
audit due date
(MM/YYYY)
Last
analysis date
(MM/YYYY)5
Repair/
replacement
due date
(MM/YYYY)6
Fit-for-
purpose
(Y/N)
Description
or comments7
North
Wharf
Berth 1 Wharfhead O 5 08/2008 08/2011 02/2008 N/A Y None
North
Wharf
Berth 1 Mooring
Dolphin
M 3 08/2008 08/2011 05/2008 12/2008 N Hook capacity inadequate
North
Wharf
Berth 1 Breasting
Dolphin
B 2 08/2008 08/2011 06/2008 02/2010 N Berthing velocity restrictions
required. Velocity monitoring
system operational. Fender
system to be upgraded.
See Terminal Operating Limits.
North
Wharf
Berth 1 Overall O 4 08/2008 08/2011 02/2008 N/A Y None
North
Wharf
Berth 1 Dolphins,
Trestles,
Catwalks,
Bulkhead
walls, etc.
08/2008 08/2011
South
Wharf
Berth 2 08/2008 08/2011

TABLE 31F-2-7B

EXAMPLE EXECUTIVE SUMMARY TABLE (ES-1B)
GLOBAL SEISMIC STRUCTURAL ASSESSMENT RATINGS (SSAR)
REV. #
MM/YYYY
Berthing
system
Berth(s)1 Structure(s)1 SSAR
rating4
Last
audit date
(MM/YYYY)
Next
audit due date
(MM/YYYY)
Last
analysis date
(MM/YYYY)5
Repair/
replacement
due date
(MM/YYYY)6
Fit-for-
purpose
(Y/N)
Description
or comments7
North
Wharf
Berth 1 Wharfhead 2 08/2008 08/2011 05/2008 02/2010 N Level 1 – OK; SAP2000 Pushover Analysis
Level 2 – NG; SAP2000 Pushover Analysis
displacements too large and liquefaction
North
Wharf
Berth 1 Trestle 5 08/2008 08/2011 05/2008 N/A Y Level 1 – OK; SAP2000 Linear Analysis
Level 2 – OK; SAP2000 Linear Analysis
North
Wharf
Berth 1 30” Crude
line
5 08/2008 08/2011 05/2008 N/A Y Level 1 – N/A
Level 2 – OK; CAESAR Analysis
North
Wharf
Overall Overall
North
Wharf
Berth 1 Dolphins,
Pipeline,
Trestles,
Bulkhead
walls, etc.
South
Wharf
Berth 2

31F-16 2022 CALIFORNIA BUILDING CODE

Copyright © 2022 by, or licensed to, International Code Council, Inc. (ALL RIGHTS RESERVED); licensed to California Building Standards Commission pursuant to License Agreement. No further reproductions is authorized. Any unauthorized reproduction or distribution is a violation of the federal copyright act and the license agreement, and subject to civil and criminal penalties thereunder.

MARINE OIL TERMINALS

TABLE 31F-2-7C
EXAMPLE EXECUTIVE SUMMARY TABLE (ES-1C)
GLOBAL INSPECTION CONDITION ASSESSMENT RATINGS (ICAR)8
EXECUTIVE SUMMARY TABLE (ES-1C)
GLOBAL INSPECTION CONDITION ASSESSMENT RATINGS (ICAR)8
EXECUTIVE SUMMARY TABLE (ES-1C)
GLOBAL INSPECTION CONDITION ASSESSMENT RATINGS (ICAR)8
EXECUTIVE SUMMARY TABLE (ES-1C)
GLOBAL INSPECTION CONDITION ASSESSMENT RATINGS (ICAR)8
EXECUTIVE SUMMARY TABLE (ES-1C)
GLOBAL INSPECTION CONDITION ASSESSMENT RATINGS (ICAR)8
EXECUTIVE SUMMARY TABLE (ES-1C)
GLOBAL INSPECTION CONDITION ASSESSMENT RATINGS (ICAR)8
EXECUTIVE SUMMARY TABLE (ES-1C)
GLOBAL INSPECTION CONDITION ASSESSMENT RATINGS (ICAR)8
REV. #
MM/YYYY
Berthing
system
Berth(s)1 Structure(s)1 Type of
inspection3
ICAR
rating4,9
Last
inspection date
(MM/YYYY)10
Inspection
interval
(YRS.)
Next inspection
due date
(MM/YYYY)10
Description
or comments7
North Wharf Berth 1 Wharfhead AW 5 02/2008 3 02/2011 General satisfactory condition.
See RAPs in Table ES-2 for details.
North Wharf Berth 1 Wharfhead UW 4 02/2008 5 02/2013 Pile damage; 10 serve, 15 minor
See RAPs in Table ES-2 for details.
North Wharf Berth 1 Breasting
Dolphin BD-1
AW 6 02/2008 3 02/2011 See RAPs in Table ES-2
North Wharf Berth 1 Breasting
Dolphin BD-1
UW 5 02/2008 5 02/2013 See RAPs in Table ES-2
North Wharf Berth 1 Dolphins,
Trestle,
Catwalks,
Bulkhead walls,
etc.
South Wharf Berth 2

These notes apply to Tables 31F-2-7A through 7C:

1. The term “Overall” shall be input in this field when the assessment ratings are summarized for a berth. 2. “Types of Analyses”: “O” = Operational Loading Analysis, “M” = Mooring Analysis, “B” = Berthing Analysis 3. “Types of Inspections”: “AW” = Above Water Inspection, “UW” = Underwater Inspection 4. All assessment ratings shall be assigned in accordance with Table 31F-2-4. 5. The “Analysis Dates” are defined by the month and year in which the final design package is submitted to the Division. 6. The “Repair/Replacement Dates” are defined by the month and year in which the repair/replacement is to be completed and operational. 7. The “Description or Comments” shall reference all MOT operating limits. For OSARs, this includes berthing velocity restrictions, load limits, etc. For SSARs, this includes a brief list of the findings for each Seismic Performance Level. 8. Inspection findings may trigger a structural reassessment (see Tables 31F-2-7A and 31F-2-7B). 9. Ratings shall be assigned comparing the observed condition to the as-built condition. 10. The “Inspection Dates” are defined by the month and year in which the last day of formal field inspection is conducted.

his includes a brief list of the findings for each Seismic Performance Level._ 8. Inspection findings may trigger a structural reassessment (see Tables 31F-2-7A and 31F-2-7B). 9. Ratings shall be assigned comparing the observed condition to the as-built condition. 10. The “Inspection Dates” are defined by the month and year in which the last day of formal field inspection is conducted.

Copyright © 2022 by, or licensed to, International Code Council, Inc. (ALL RIGHTS RESERVED); licensed to California Building Standards Commission pursuant to License Agreement. No further reproductions is authorized. Any unauthorized reproduction or distribution is a violation of the federal copyright act and the license agreement, and subject to civil and criminal penalties thereunder.

MARINE OIL TERMINALS

TABLE 31F-2-8
EXAMPLE EXECUTIVE SUMMARY TABLE (ES-2)
COMPONENT DEFICIENCY REMEDIAL ACTION PRIORITIES (RAP)1
EXECUTIVE SUMMARY TABLE (ES-2)
COMPONENT DEFICIENCY REMEDIAL ACTION PRIORITIES (RAP)1
EXECUTIVE SUMMARY TABLE (ES-2)
COMPONENT DEFICIENCY REMEDIAL ACTION PRIORITIES (RAP)1
EXECUTIVE SUMMARY TABLE (ES-2)
COMPONENT DEFICIENCY REMEDIAL ACTION PRIORITIES (RAP)1
EXECUTIVE SUMMARY TABLE (ES-2)
COMPONENT DEFICIENCY REMEDIAL ACTION PRIORITIES (RAP)1
EXECUTIVE SUMMARY TABLE (ES-2)
COMPONENT DEFICIENCY REMEDIAL ACTION PRIORITIES (RAP)1
EXECUTIVE SUMMARY TABLE (ES-2)
COMPONENT DEFICIENCY REMEDIAL ACTION PRIORITIES (RAP)1
EXECUTIVE SUMMARY TABLE (ES-2)
COMPONENT DEFICIENCY REMEDIAL ACTION PRIORITIES (RAP)1
EXECUTIVE SUMMARY TABLE (ES-2)
COMPONENT DEFICIENCY REMEDIAL ACTION PRIORITIES (RAP)1
EXECUTIVE SUMMARY TABLE (ES-2)
COMPONENT DEFICIENCY REMEDIAL ACTION PRIORITIES (RAP)1
EXECUTIVE SUMMARY TABLE (ES-2)
COMPONENT DEFICIENCY REMEDIAL ACTION PRIORITIES (RAP)1
REV. #
MM/YYYY
Berthing
system
Berth(s) Structure(s)
or
location(s)
Deficiency
item label2
Component:
deficiency
description
Remedial
action
priority
(RAP)3
CBC
section
reference
Audit
checklist
reference
(optional)
Description
of planned
remedial
action
P.E.
review
required?
(Y/N)4
Repair/
replacement
due date
(MM/YYYY)
Completion
date
_ (MM/YYYY)_
Description
of completed
actions
North
Wharf
Berth 1 Wharfhead 02.0001.001 Piles:10 piles
have severe
damage; 15
piles have
minor damage.
P2 3102F.3.5.2 Replace 10
severe piles.
Monitor 15
minor piles.
Y 05/2008 04/2008 10 piles
replaced
North
Wharf
Berth 1 Mooring
Dolphin
MD-1
02.0001.002 Curb:_ Spalling_
of concrete
curb w/o
exposed
reinforcement.
R 3102F.3.5.2 Repair
concrete curbs.
N 02/2009
North
Wharf
Berth 1 Wharfhead 08.0001.002 International
Shore Fire
Connection:
Connections
available, but
not connected.
P3 3108F.6.3.4 8.6.22 Install
International
Shore Fire
Connections.
N 10/2008
North
Wharf
Berth 1 Wharfhead 11.0001.001 Conduit Seals
near Manifold:
Conduit seals
inadequate for
Class 1,
Division 1
location.
P1 3111F.2 Replace
conduit seals
with seals
adequate for
Class 1.
Division 1
location within
30 days.
Y 04/2008 04/2008 Seals replaced
North
Wharf
Berth 1 Wharfhead 11.0001.001 Pressurized
Instrumentatio
n Panel near
Shelter:
Pressure gauge
reads “low”
and will not
hold pressure
in Class 1,
Division 2
location.
P2 3111F.2 3111F.4.5 Repair
pressurized
instrumentation
panel in Class
1, Division 2
Location
within 60 days.
Y 05/2008 05/2008 Pressurized
instrumentation
panel could not
be repaired and
was replaced.

These notes apply to Table 31F-2-8: 1. After a deficiency is corrected/completed, the row of text corresponding to that deficiency may be grayed out in subsequent ES-2 tables, and removed entirely in the subsequent audit. 2. The “Deficiency Item Labels” shall be assigned in the format shown above with the first series of numbers representing the Code Division/Section number (“XX”), a period (“.”) for separation, the second series of numbers representing the deficiency item number (“XXXX”), a period (“.”) for separation, and the third series of numbers representing the ES-2 table revision number (“XXX”) in which the deficiency was first reported. Note that the deficiency item numbering will start from “0001” for the first deficiency in each section of the audit, and will increase consecutively in all future ES-2 tables. 3. RAPs shall be assigned in accordance with Table 31F-2-5. 4. Professional engineering review required in accordance with Section 3102F.3.8 under “Follow-up Actions.”

TABLE 31F-2-9 POST-EVENT RATINGS AND REMEDIAL ACTIONS [2.2]

RATING SUMMARY OF DAMAGE REMEDIAL ACTIONS
A No significant event-induced damage observed. No further action required. The berthing system may continue operations.
B Minor to moderate event-induced damage observed but all primary
structural elements and electrical/mechanical systems are sound.
Repairs or mitigation may be required to remain operational. The
berthing system may continue operations.
C Moderate to major event-induced damage observed which may have
significantly affected the load bearing capacity of primary structural
elements or the functionality of key electrical/mechanical systems.
Repairs or mitigation may be necessary to resume or remain operational.
The berthing system may be allowed to resume limited operations.
D Major event-induced damage has resulted in localized or widespread
failure of primary structural components; or the functionality of key
electrical/ mechanical systems has been significantly affected.
Additional failures are possible or likely to occur.
The berthing system may not resume operations until the deficiencies are
corrected.

31F-18 2022 CALIFORNIA BUILDING CODE

Copyright © 2022 by, or licensed to, International Code Council, Inc. (ALL RIGHTS RESERVED); licensed to California Building Standards Commission pursuant to License Agreement. No further reproductions is authorized. Any unauthorized reproduction or distribution is a violation of the federal copyright act and the license agreement, and subject to civil and criminal penalties thereunder.

MARINE OIL TERMINALS

Copyright © 2022 by, or licensed to, International Code Council, Inc. (ALL RIGHTS RESERVED); licensed to California Building Standards Commission pursuant to License Agreement. No further reproductions is authorized. Any unauthorized reproduction or distribution is a violation of the federal copyright act and the license agreement, and subject to civil and criminal penalties thereunder.

MARINE OIL TERMINALS

Get a plain-English answer with a citation back to this text.

Ask AI about this code
Contents — California Building Code (Title 24, Part 2)
California Building Code (Title 24, Part 2)
  1. Chapter 2 — DEFINITIONS AND ABBREVIATIONS
  2. Appendix G — FLOOD-RESISTANT
  3. Appendix L — EARTHQUAKE RECORDING
  4. Appendix M — TSUNAMI-GENERATED
  5. Appendix N — REPLICABLE
  6. Appendix O — PERFORMANCE-BASED
  7. Chapter 1 — SCOPE AND ADMINISTRATION
  8. Chapter 3 — OCCUPANCY CLASSIFICATION AND USE
  9. Chapter 4 — SPECIAL DETAILED REQUIREMENTS BASED ON OCCUPANCY A…
  10. Chapter 5 — GENERAL BUILDING HEIGHTS AND AREAS
  11. Chapter 6 — TYPES OF CONSTRUCTION
  12. Chapter 7 — FIRE AND SMOKE PROTECTION FEATURES
  13. Chapter 7A — MATERIALS AND CONSTRUCTION
  14. Chapter 8 — INTERIOR FINISHES
  15. Chapter 9 — FIRE PROTECTION AND LIFE SAFETY SYSTEMS
  16. Chapter 10 — MEANS OF EGRESS
  17. Chapter 11A — HOUSING ACCESSIBILITY
  18. Chapter 11B — ACCESSIBILITY TO PUBLIC BUILDINGS, PUBLIC ACCOMM…
  19. Chapter 12 — INTERIOR ENVIRONMENT
  20. Chapter 14 — EXTERIOR WALLS
  21. Chapter 15 — ROOF ASSEMBLIES AND ROOFTOP STRUCTURES
  22. Chapter 16 — STRUCTURAL DESIGN
  23. Chapter 16A — STRUCTURAL DESIGN
  24. Chapter 17 — SPECIAL INSPECTIONS AND TESTS
  25. Chapter 18 — SOILS AND FOUNDATIONS
  26. Chapter 19 — CONCRETE
  27. Chapter 20 — ALUMINUM
  28. Chapter 21 — MASONRY
  29. Chapter 22 — STEEL
  30. Chapter 23 — WOOD
  31. Chapter 24 — GLASS AND GLAZING
  32. Chapter 25 — GYPSUM BOARD, GYPSUM PANEL PRODUCTS AND PLASTER
  33. Chapter 26 — PLASTIC
  34. Chapter 27 — ELECTRICAL
  35. Chapter 28 — MECHANICAL SYSTEMS
  36. Chapter 30 — ELEVATORS AND CONVEYING SYSTEMS
  37. Chapter 31 — SPECIAL CONSTRUCTION
  38. Chapter 31B — PUBLIC POOLS
  39. Chapter 31C — RADIATION
  40. Chapter 31D — FOOD ESTABLISHMENTS
  41. Chapter 31F — MARINE OIL TERMINALS
  42. Chapter 32 — ENCROACHMENTS INTO THE PUBLIC RIGHT-OF-WAY
  43. Chapter 33 — SAFEGUARDS DURING CONSTRUCTION
  44. Chapter 35 — REFERENCED STANDARDS
  45. Appendix A — EMPLOYEE QUALIFICATIONS
  46. Appendix B — BOARD OF APPEALS
  47. Appendix C — GROUP U – AGRICULTURAL BUILDINGS
  48. Appendix D — FIRE DISTRICTS
  49. Appendix F — RODENTPROOFING
  50. Appendix H — SIGNS
  51. Appendix I — PATIO COVERS
  52. Appendix J — GRADING
  53. Appendix K — GROUP R-3 AND GROUP R-3.1 OCCUPANCIES
  54. Appendix P — EMERGENCY HOUSING

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.