§ 18.64.010. Applicability.

This section applies to applications for expedited building permits for electric vehicle charging stations pursuant to California Government Code Section 65850.7. (Ord. 490 § 3, 2023)

§ 18.64.020. Process.

  • A. The building official shall adopt a checklist of all requirements for an application for an expedited building permit for electric vehicle charging stations. The checklist shall substantially conform to the check-list and standard plans contained in the most current version of the "Plug-In Electric Vehicle Infrastructure Permitting Checklist" of the "Zero-Emission Vehicles in California: Community Readiness Guidebook" published by the Governor's Office of Planning and Research.

  • B. If the building official determines that the application for an expedited building permit is complete and meets the requirements of the checklist, the building official shall issue the expedited building permit.

  • C. If the application for an expedited building permit is incomplete, the building official shall provide a written correction notice of the deficiencies and the additional information required to be eligible for expedited building permit issuance.

  • D. The checklist, application form, and any other documents required by the building official shall be published on the city's website.

  • E. An application for an expedited building permit for electric vehicle charging stations may be filed by email.

  • F. If the chief building official finds, based on substantial evidence, that an electric vehicle charging station could have a specific adverse impact upon the public health or safety, the city may require the applicant to apply for a conditional use permit pursuant to Chapter 18.76 .

(Ord. 490 § 3, 2023)