Chapter 1 — SCOPE AND ADMINISTRATION
Section 111
California Building Code (Title 24, Part 2) · 2022 edition · updated 2026-09-12 · California
Italicized text is a California amendment to the model code, as printed in the official publication.
CERTIFICATE OF OCCUPANCY
[A] 111.1 Change of occupancy. A building or structure shall not be used or occupied in whole or in part, and a change of occupancy of a building or structure or portion thereof shall not be made, until the building official has issued a certificate of occupancy therefor as provided herein. Issuance of a certificate of occupancy shall not be construed as an approval of a violation of the provisions of this code or of other ordinances of the jurisdiction. Certificates presuming to give authority to violate or cancel the provisions of this code or other ordinances of the jurisdiction shall not be valid.
Exception: Certificates of occupancy are not required for work exempt from permits in accordance with Section 105.2.
[A] 111.2 Certificate issued. After the building official inspects the building or structure and does not find violations
of the provisions of this code or other laws that are enforced by the department, the building official shall issue a certificate of occupancy that contains the following:
- The permit number.
- The address of the structure.
- The name and address of the owner or the owner’s authorized agent.
- A description of that portion of the structure for which the certificate is issued.
- A statement that the described portion of the structure has been inspected for compliance with the requirements of this code.
- The name of the building official.
- The edition of the code under which the permit was issued.
- The use and occupancy, in accordance with the provisions of Chapter 3.
- The type of construction as defined in Chapter 6.
- The design occupant load.
- Where an automatic sprinkler system is provided, whether the sprinkler system is required.
- Any special stipulations and conditions of the building permit.
[A] 111.3 Temporary occupancy. The building official is authorized to issue a temporary certificate of occupancy before the completion of the entire work covered by the permit, provided that such portion or portions shall be occupied safely. The building official shall set a time period during which the temporary certificate of occupancy is valid.
[A] 111.4 Revocation. The building official is authorized to suspend or revoke a certificate of occupancy or completion issued under the provisions of this code, in writing, wherever the certificate is issued in error, or on the basis of incorrect information supplied, or where it is determined that the building or structure or portion thereof is in violation of the provisions of this code or other ordinance of the jurisdiction.
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸Contents — California Building Code (Title 24, Part 2)
- Chapter 2 — DEFINITIONS AND ABBREVIATIONS
- Appendix G — FLOOD-RESISTANT
- Appendix L — EARTHQUAKE RECORDING
- Appendix M — TSUNAMI-GENERATED
- Appendix N — REPLICABLE
- Appendix O — PERFORMANCE-BASED
▸Chapter 1 — SCOPE AND ADMINISTRATION
Overview- Section 1.1
- Section 1.2
- Section 1.3
- Section 1.4
- Section 1.5
- Section 1.6
- Section 1.7
- Section 1.8
- Section 1.8.2
- Section 1.8.3
- Section 1.8.4
- Section 1.8.5
- Section 1.8.6
- Section 1.8.7
- Section 1.8.8
- Section 1.8.9
- Section 1.8.10
- Section 1.9
- Section 1.10
- Section 1.11
- Section 1.12
- Section 1.13
- Section 1.14
- Section 101
- Section 102
- Section 103
- Section 104
- Section 105
- Section 106
- Section 107
- Section 108
- Section 109
- Section 110
- Section 111
- Section 112
- Section 113
- Section 114
- Section 115
- Section 116
- Section 201
- Section 202
- Chapter 3 — OCCUPANCY CLASSIFICATION AND USE
- Chapter 4 — SPECIAL DETAILED REQUIREMENTS BASED ON OCCUPANCY A…
- Chapter 5 — GENERAL BUILDING HEIGHTS AND AREAS
- Chapter 6 — TYPES OF CONSTRUCTION
- Chapter 7 — FIRE AND SMOKE PROTECTION FEATURES
- Chapter 7A — MATERIALS AND CONSTRUCTION
- Chapter 8 — INTERIOR FINISHES
- Chapter 9 — FIRE PROTECTION AND LIFE SAFETY SYSTEMS
- Chapter 10 — MEANS OF EGRESS
- Chapter 11A — HOUSING ACCESSIBILITY
- Chapter 11B — ACCESSIBILITY TO PUBLIC BUILDINGS, PUBLIC ACCOMM…
- Chapter 12 — INTERIOR ENVIRONMENT
- Chapter 14 — EXTERIOR WALLS
- Chapter 15 — ROOF ASSEMBLIES AND ROOFTOP STRUCTURES
- Chapter 16 — STRUCTURAL DESIGN
- Chapter 16A — STRUCTURAL DESIGN
- Chapter 17 — SPECIAL INSPECTIONS AND TESTS
- Chapter 18 — SOILS AND FOUNDATIONS
- Chapter 19 — CONCRETE
- Chapter 20 — ALUMINUM
- Chapter 21 — MASONRY
- Chapter 22 — STEEL
- Chapter 23 — WOOD
- Chapter 24 — GLASS AND GLAZING
- Chapter 25 — GYPSUM BOARD, GYPSUM PANEL PRODUCTS AND PLASTER
- Chapter 26 — PLASTIC
- Chapter 27 — ELECTRICAL
- Chapter 28 — MECHANICAL SYSTEMS
- Chapter 30 — ELEVATORS AND CONVEYING SYSTEMS
- Chapter 31 — SPECIAL CONSTRUCTION
- Chapter 31B — PUBLIC POOLS
- Chapter 31C — RADIATION
- Chapter 31D — FOOD ESTABLISHMENTS
- Chapter 31F — MARINE OIL TERMINALS
- Chapter 32 — ENCROACHMENTS INTO THE PUBLIC RIGHT-OF-WAY
- Chapter 33 — SAFEGUARDS DURING CONSTRUCTION
- Chapter 35 — REFERENCED STANDARDS
- Appendix A — EMPLOYEE QUALIFICATIONS
- Appendix B — BOARD OF APPEALS
- Appendix C — GROUP U – AGRICULTURAL BUILDINGS
- Appendix D — FIRE DISTRICTS
- Appendix F — RODENTPROOFING
- Appendix H — SIGNS
- Appendix I — PATIO COVERS
- Appendix J — GRADING
- Appendix K — GROUP R-3 AND GROUP R-3.1 OCCUPANCIES
- Appendix P — EMERGENCY HOUSING