Chapter 4 — SPECIAL DETAILED REQUIREMENTS BASED ON OCCUPANCY AND USE

Section 417 — DRYING ROOMS

2025 California Building Code (Title 24, Part 2) · 2025 edition · ingested 2026-07-07 · California

Full text via GoCodebook AI

We have the complete 2025 text of this code. Ask a question and get the exact controlling section with a citation.

Ask about this chapter

[F] 417.1 General. A drying room or dry kiln installed within a building shall be constructed entirely of approved noncombustible materials or assemblies of such materials regulated by the approved rules or as required in the general and specific sections of this chapter for special occupancies and where applicable to the general requirements of the California Mechanical Code . [F] 417.2 Piping clearance. Overhead heating pipes shall have a clearance of not less than 2 inches (51 mm) from combustible contents in the dryer. [F] 417.3 Insulation. Where the operating temperature of the dryer is…