Section 503F — INSPECTION SCHEDULE
503F.3 Inspection in Response to Damage or Failure.
San Francisco Building Inspection Commission Codes · edición 2022 · actualizado 2026-07-08 · San Francisco
Esta sección aún no está traducida y se muestra en inglés.
503F.3 Inspection in Response to Damage or Failure. Notwithstanding the Initial Inspection Schedule set forth in Table 503F or the Exceptions to
the initial inspection requirements provided in Section 503F.1, the Department shall require an inspection of façades to be performed in the following
circumstance: If façade elements required to be inspected under this Chapter 5F exhibit significant damage or failure as noted by Department staff or
property owner or owner’s agent, either during the normal passage of time or due to an earthquake or other event, then the property owner is required
to obtain an inspection of the areas of damaged or failed elements and related building elements within 60 days unless the façade poses an unsafe
c on dition. If the Building Official determines that there is an unsafe condition, the provisions of Section 102A shall apply.