Section 609.0 — INSTALLATION, TESTING, UNIONS AND LOCATION
San Francisco Building Inspection Commission Codes · edición 2022 · actualizado 2026-07-08 · San Francisco
Esta sección aún no está traducida y se muestra en inglés.
609.11.2 Add the following section:
609.11.2 Air Chambers. Air chambers shall be installed on all hot and cold water outlets supplying quick-acting valves to provide water hammer relief. The size of each air chamber shall be 24 times the diameter of the fixture supply.
609.11.3 Add the following section:
609.11.3 Quick-Acting Valves. The following valves shall be considered quick-acting: flushometers, single-handle faucets, single-handle tub and tub/shower combination control valves, single-handle shower control valves, rapid response electric solenoid valves (such as used on ice-makers, clothes washers, etc.) and any other appliance or fixture that dispenses water in a quick open and close method in its operation.
Chapter 7 SANITARY DRAINAGE
| Part I – DRAINAGE SYSTEMS | Col2 | Col3 |
|---|---|---|
| Part I – DRAINAGE SYSTEMS | ||