503F.1 Initial Inspection Types.

San Francisco Building Inspection Commission Codes · edición 2022 · actualizado 2026-07-08 · San Francisco

Esta sección aún no está traducida y se muestra en inglés.

503F.1 Initial Inspection Types.

503F.1.1 Initial Comprehensive Inspection. All buildings within the scope of this Chapter 5F shall conduct an initial comprehensive façade inspection pursuant to Section 504F and submit an inspection report subject to the requirements of Section 505F within the timelines detailed in Table 503F.

503F.1.2 Initial Supplemental Inspection. All buildings 15 or more stories tall shall submit an initial supplemental façade inspection report in accordance with the requirements of Section 504F within six months of notification by the Department, or within the timelines detailed in Table 503F. After submitting the initial supplemental inspection report, periodic supplemental inspection reports shall be conducted and submitted by building owners in accordance with Section 503F.2.

Exceptions:

  1. Buildings for which comprehensive façade inspection and necessary maintenance, restoration, or replacement has been completed during the 10 years preceding the date of the required initial inspection report due date may apply to the Building Official for a waiver of the initial inspection.

  2. Notwithstanding the initial inspection schedules in this Chapter 5F or any other provision, the Building Official may require a façade inspection of any building that the Building Official finds may pose a health and safety hazard.

Table 503F

Initial Inspections Schedule

Compliance
Tier
Building Construction Completion
1
Date
Comprehensive
Inspection Report Due
Date
Supplemental
Inspection Report Due
Date
1 Building was constructed prior to
1910
December 31, 2021 December 31, 2026
2 Building was constructed from 1910
through 1925
December 31, 2023 December 31, 2028
3 Building was constructed from 1926
through 1970
December 31, 2025 December 31, 2030
4 Building was constructed from 1971
through 1997
December 31, 2027 December 31, 2032
5 Building was constructed after 1997 December 31 of the
30th year after receiving
Certificate of Final
Completion and
Occupancy
April 30, 2024
1   Building construction date refers to the date the Department issued the Certificate of Completion for the
original building or other Department documentation showing the date of completion of the original
construction, regardless of the dates of any additions or alterations.
1   Building construction date refers to the date the Department issued the Certificate of Completion for the
original building or other Department documentation showing the date of completion of the original
construction, regardless of the dates of any additions or alterations.
1   Building construction date refers to the date the Department issued the Certificate of Completion for the
original building or other Department documentation showing the date of completion of the original
construction, regardless of the dates of any additions or alterations.
1   Building construction date refers to the date the Department issued the Certificate of Completion for the
original building or other Department documentation showing the date of completion of the original
construction, regardless of the dates of any additions or alterations.