810.0260 Inspection and Compliance.

Yucaipa Zoning Code · 2026-06 edition · updated 2026-09-10 · Yucaipa

The City Engineer shall conduct inspections to ensure compliance with this Chapter.

  • (a) Inspection

The following inspections may be performed by the City Engineer.

  • (1) Pre-Site Inspection

To determine the potential for erosion resulting from the proposed project

(2) Operation Progress Inspections

To determine ongoing compliance

  • (3) Final Inspection

To determine compliance with approved plans and specifications

(b) Notification

The permittee shall notify the City Engineer at least 24 hours prior to the start of the authorized work, and also nine business hours prior to any inspection requested by the permittee or the permittee’s authorized agent.

(c) Right of Entry

The filing of an application for a development permit constitutes a grant of permission for the City to enter the permit area for the purpose of administering this chapter from the date of the application to the termination of the erosion control maintenance period.

810.0265 Applicable Laws and Regulations.

Any person doing work in conformance with this chapter must also abide by all other applicable local, State and Federal laws and regulations. Where there is a conflict with other pre-existing City regulations, that conflict shall be resolved before the project is allowed to proceed.

Get a plain-English answer with a citation back to this text.

Ask AI about this code
Contents — Yucaipa Zoning Code

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.