Chapter 20.20 — CONTROL OF DRAINAGE, EROSION AND DUST CONTROL
Paso Robles Municipal Code · 2026-09 edition · updated 2026-09-27 · Paso Robles
20.20.010 - Erosion and sediment control plan.¶
A.
A site-specific erosion and sediment control plan (ESCP) shall be required to be prepared and submitted with every application for a grading or building permit.
The ESCP shall be developed per Section III(2.1) Erosion and Sediment Control Plan of the Public Works, Engineering Division.
The ESCP and any subsequent revisions shall be approved in writing by the city engineer or director of public works prior to permit issuance.
A storm water pollution prevention plan (SWPPP) developed pursuant to the state construction general permit may be substituted for the ESCP where a SWPPP is developed. The SWPPP must be reviewed by the city to determine if it meets the ESCP requirements.
B.
The period between September 1st and April 30th is determined to be the period in which most rainfall occurs within the city. Whenever it appears that any grading project previously commenced pursuant to a permit issued by the city engineer will not be completed prior to the rainy season, erosion and sediment control measures shall be installed per the ESCP.
C.
All erosion control devices, including the desilting basins, shall be installed not later than August 15th of each year.
D.
Should the owner fail to install erosion and sediment control measures required by the dates specified therein, it shall be deemed that a default has occurred under the conditions of the grading permit bond. Thereupon the city engineer may enter the property for the purpose of installing, by city forces or by other means, the drainage and erosion control devices shown on the approved plans, or as he may deem necessary to protect adjoining property from storm damage, or the city engineer may cause the owner of the site to be prosecuted as a violator of this chapter, or he may take both actions or pursue any other legal remedies.
(Ord. No. 994 N.S., § 4, 8-20-2013)
20.20.020 - Drainage control.¶
Seasonal Limits.
A.
No fill material shall be placed, spread or rolled at such time or times that weather conditions are considered unfavorable by the city engineer. When the work is interrupted by heavy rain, fill operations shall not be resumed until field tests by the soils engineer indicate that the moisture content and density of the fill materials meet the requirements of this chapter.
B.
The design and construction of desilting basins which discharge drainage onto city streets or natural watercourses shall be under the control of the engineering division.
C.
Grading work shall be limited or ceased if the city engineer finds that its continuance will constitute a hazard to person or property during the period September 1st through April 30th.
(Ord. 702 N.S. (part), 1995; Ord. No. 994 N.S., § 4, 8-20-2013)
Editor's note— Ord. No. 994 N.S., § 4, adopted August 20, 2013, repealed § 20.20.020, erosion control, and renumbered § 20.20.010, drainage control, as § 20.20.020, and amended it to read as set out herein. Former §
20.20.030 - Irrigation and landscaping of slopes.¶
A.
Irrigation.
Plans for irrigation systems in public rights-of-way shall be submitted to and approved by the department of public works prior to installation.
Adequate backflow protection shall be installed in each sprinkler system as required by the plumbing code and city engineer.
A functional test of the irrigation system shall be performed by the installer for all irrigation systems prior to approval.
B.
Landscaping.
General.
a.
When the city has required the installation of landscaping for erosion control or for aesthetics, the permittee, or his authorized representatives, shall be responsible for installing all landscaping in accordance with an approved landscaping planting plan, for a irrigation system, and for maintaining all cut and fill slopes.
b.
Deviations from the requirements of this section may be permitted in exceptional circumstances or where unavoidable hardship would result from a strict application of these requirements when a waiver has first been obtained from the planning commission. A separate bond or cash deposit shall be posted with the city engineer to guarantee such landscaping, irrigation system, and the maintenance thereof, and such bond or cash deposit, or portions thereof, shall not be released until the landscaping has been established for at least ninety days after planting and permanent responsibility for the landscape maintenance has been established.
Landscaping Plan. A landscaping planting plan within the public right-of-way shall be prepared and submitted for approval by the director of public works and the director of community development. A soils test may be required to determine the plant materials which are suitable for the slopes, and the plant materials utilized on the slopes shall be compatible with the soils report. There shall be a variety of ground covers, trees, and shrubs incorporated into the landscaping plan. Other plant materials may be substituted for the "approved planting schedule" if submitted and recommended by a registered landscape architect and approved by the director of public works.
Plants. All plants required by this section shall be selected from a list approved by the director of public works.
Planting. The slopes shall be prepared for planting by one of the following methods:
a.
The slope surface may be prepared for planting by casting top soil over the slope surface. The top soil layer shall not exceed three inches in depth.
b.
The slope surface may be scarified to a depth not to exceed three inches.
c.
Loose material not to exceed three inches in depth may be left on the slope.
d.
The grass, ground cover, shrubs, and tree plant materials shall be certified for the local climatic conditions and soil types.
e.
The plant variety, size, and spacing shall be as shown on the approved plans.
f.
Any dead or dying plants shall be promptly replaced upon request and as directed during the guarantee period.
g.
The landscaping installation, including irrigation, shall be guaranteed for a period of one-year from the date of final inspection.
(Ord. 702 N.S. (part), 1995; Ord. No. 994 N.S., § 4, 8-20-2013)
20.20.040 - Dust control.¶
A.
Seasonal Conditions. The late afternoon summer winds may cause excessive dust blowing during grading operations. In the event that dust cannot be controlled and becomes a nuisance, the city engineer may order the work to be halted for the day.
B.
Dust Control. All graded surfaces and materials shall be wetted, treated or contained in such a manner as to prevent dust from leaving the site.
C.
Completion of Grading. The graded site shall be thoroughly wetted in order to form a crust over the exposed dirt surfaces. Further applications or other methods acceptable to the city engineer may be necessary if the site is disturbed.
(Ord. 702 N.S. (part), 1995; Ord. No. 994 N.S., § 4, 8-20-2013)
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸Contents — Paso Robles Municipal Code
- Title 1 — GENERAL PROVISIONS
- Chapter 2.04 — COUNCIL MEETINGS
- Chapter 2.20 — PLANNING COMMISSION
- Chapter 2.24 — EMERGENCY ORGANIZATION AND FUNCTIONS
- Chapter 2.28 — CITY MANAGER
- Chapter 2.34 — CITY CLERK
- Chapter 2.40 — BONDS AND SALARIES OF OFFICERS
- Chapter 2.44 — PERSONNEL PLAN—RULES AND REGULATIONS
- Chapter 2.58 — POLICE RESERVES
- Chapter 2.60 — POLICE TRAINING
- Chapter 2.62 — TRAINING STANDARDS OF PUBLIC SAFETY DISPATCHERS
- Chapter 2.65 — ELECTIONS
- Title 3 — REVENUE AND FINANCE
- Chapter 3.01 — ASSESSMENT, LEVY AND COLLECTION OF TAXES BY COU…
- Chapter 3.08 — UNIFORM SALES AND USE TAX
- Chapter 3.10 — GENERAL TRANSACTIONS AND USE TAX
- Chapter 3.11 — SUPPLEMENTAL TRANSACTIONS AND USE TAX
- Chapter 3.12 — SPECIAL GAS TAX STREET IMPROVEMENT FUND
- Chapter 3.20 — REAL PROPERTY TRANSFER TAX
- Chapter 3.21 — VISUAL ART IN PUBLIC PLACES
- Chapter 3.22 — CANNABIS BUSINESS TAX
- Chapter 3.26 — TRANSIENT OCCUPANCY TAX
- Chapter 3.28 — BUSINESS LICENSE TAX
- Chapter 3.30 — DENIAL OR REVOCATION OF A BUSINESS LICENSE TAX …
- Title 5 — PERMITS AND REGULATIONS
- Chapter 5.02 — PARKING AND BUSINESS IMPROVEMENT AREA
- Chapter 5.08 — CARD AND BILLIARD ROOMS
- Chapter 5.12 — CLOSING OUT SALES
- Chapter 5.28 — PRIVATE PATROL
- Chapter 5.36 — SOLICITORS
- Chapter 5.38 — MASSAGE THERAPY AND MASSAGE ESTABLISHMENTS
- Chapter 5.40 — TAXICABS
- Chapter 5.45 — ALARM SYSTEMS
- Chapter 5.50 — STATE VIDEO FRANCHISES
- Chapter 6.04 — PURCHASING AND PAYMENT PROCEDURES
- Chapter 7.12 — FOOD AND DRINK ESTABLISHMENTS
- Chapter 7.16 — GARBAGE
- Chapter 7.30 — UNDERGROUND STORAGE OF HAZARDOUS SUBSTANCES
- Chapter 7.40 — RECYCLING AND ORGANIC WASTE COLLECTION
- Chapter 7.50 — CAMPING
- Title 8 — ANIMAL CONTROL
- Chapter 8.04 — GENERAL
- Chapter 9.02 — EMERGENCY REGULATIONS
- Chapter 9.03 — HAZARDOUS MATERIALS
- Chapter 9.04 — MISCELLANEOUS MISDEMEANORS
- Chapter 9.05 — SKATE PARK AND PUMP TRACK FACILITIES
- Chapter 9.06 — NUISANCE ABATEMENT
- Chapter 9.07 — PROHIBITED CONDUCT
- Chapter 9.12 — GAME RESTRICTIONS FOR MINORS—HOURS
- Chapter 9.16 — BINGO
- Chapter 9.32 — CURFEW
- Chapter 9.36 — PINBALL MACHINES
- Chapter 9.38 — UNCLAIMED PROPERTY
- Chapter 9.40 — ABANDONED VEHICLES
- Chapter 9.41 — SMOKING PROHIBITED IN PUBLIC PLACES
- Chapter 9.42 — SWIMMING AND WATER SPORTS PROHIBITED IN CERTAIN…
- Chapter 9.45 — FILMING ACTIVITIES
- Chapter 9.50 — PROHIBITION ON AGGRESSIVE SOLICITATION
- Chapter 9.51 — PSYCHOACTIVE HERBAL INCENSE, PSYCHOACTIVE BATH …
- Chapter 9.55 — PARKS AND RECREATION
- Title 10 — VEGETATION
- Chapter 10.01 — OAK TREE PRESERVATION
- Chapter 10.04 — STREET TREE PLANTING AND MAINTENANCE
- Title 11 — STREETS AND SIDEWALKS
- Chapter 11.02 — ALLEYS
- Chapter 11.04 — PRECISE STREETS AND HIGHWAY PLAN
- Chapter 11.08 — STREET ADDRESSES AND HOUSE NUMBERS
- Chapter 11.12 — CONSTRUCTION OF SIDEWALKS, CURBS AND GUTTERS
- Chapter 11.20 — STREET EXCAVATIONS
- Chapter 11.24 — DISCHARGE OF WASTE WATER INTO STREETS
- Article I — Purpose
- Article II — Definitions
- Article III — Approval of Location Permits
- Article IV — General Pushcart Regulations
- Article VI — Enforcement
- Chapter 11.30 — STREET FURNITURE
- Chapter 11.35 — NEWSRACKS
- Chapter 11.40 — MODIFICATIONS ON STREET IMPROVEMENT REQUIREMENTS
- Chapter 12.04 — DEFINITIONS
- Chapter 12.08 — ADMINISTRATION
- Chapter 12.12 — ENFORCEMENT
- Chapter 12.16 — TRAFFIC CONTROL DEVICES
- Chapter 12.18 — TRAFFIC FEES
- Chapter 12.19 — BRIDGE DEVELOPMENT FEE
- Chapter 12.20 — TURNING MOVEMENTS
- Chapter 12.24 — MISCELLANEOUS DRIVING RULES
- Chapter 12.28 — PEDESTRIANS
- Chapter 12.32 — STOPPING, STANDING AND PARKING
- Chapter 12.36 — LOADING AND UNLOADING
- Chapter 12.37 — VALET
- Chapter 12.38 — PARKING RESTRICTIONS
- Chapter 12.43 — RESIDENTIAL PARKING PERMITS
- Chapter 12.45 — PARKING BENEFIT DISTRICT
- Chapter 12.46 — TRUCK ROUTES
- Chapter 12.50 — ONE-WAY TRAFFIC
- Chapter 12.54 — SPEED LIMITS
- Chapter 12.58 — BICYCLES
- Chapter 12.90 — SCHEDULES
- Chapter 12.92 — OPERATION OF MOTOR VEHICLES ON PUBLIC PROPERTY
- Chapter 13.01 — MUNICIPAL AIRPORT OPERATIONS
- Chapter 13.02 — AIRPORT COMMISSION
- Title 14 — WATER AND SEWERS
- Chapter 14.02 — WATER CONSERVATION AND WATER SHORTAGE CONTINGE…
- Chapter 14.04 — WATER RATES AND REGULATIONS
- Chapter 14.06 — REGULATION OF WELL CONSTRUCTION, REPAIR, MODIF…
- Chapter 14.07 — NON-POTABLE WATER SERVICE
- Chapter 14.08 — SEWERAGE SYSTEM OPERATIONS
- Article I — General Provisions
- Article II — Sewer Connection
- Article III — Private Wastewater Systems
- Article IV — Violations and Penalties
- Chapter 14.10 — SEWER USE
- Article I — Purpose and Policy
- Article II — Prohibitions and Limits on Discharges
- Article III — Hauled Waste
- Article IV — Small Winery and Small Brewery Program
- Article V — Fats, Oils and Grease Control Program
- Article VI — Industrial Wastewater Discharge Permits
- Article VII — Pretreatment
- Article VIII — Compliance Monitoring
- Article IX — Reporting Requirements
- Article X — Public Participation
- Article XI — Fees, Rates, and Charges
- Article XII — Liability and Enforcement
- Article XIII — Affirmative Defense to Discharge Violations
- Article XIV — Miscellaneous Provisions
- Chapter 14.12 — CONNECTIONS TO MAINS WHERE STREETS TO BE IMPRO…
- Chapter 14.16 — SEWER CHARGES
- Chapter 14.18 — CROSS-CONNECTIONS CONTROL AND INSPECTIONS
- Article I — General Provisions
- Article II — Prohibitions
- Article III — Reduction of Pollutants in Storm Water
- Article IV — Construction Activities
- Article V — Post-Construction
- Article VI — Inspection, Monitoring, and Data Collection
- Article VII — Enforcement
- Title 15 — PUBLIC UTILITIES
- Chapter 15.04 — UNDERGROUND UTILITIES DISTRICTS
- Title 16 — FIRE
- Chapter 16.04 — FIRE LIMITS
- Chapter 16.08 — FIRE DEPARTMENT
- Chapter 16.10 — ABATEMENT OF HAZARDOUS FUELS AND RUBBISH
- Title 17 — BUILDINGS AND CONSTRUCTION
- Chapter 17.04 — UNIFORM CODES
- Chapter 17.08 — MOVING BUILDINGS
- Chapter 17.12 — SECURITY OF BODIES OF WATER TO BE USED FOR THE…
- Chapter 17.16 — DEMOLITION OF BUILDINGS AND STRUCTURES
- Chapter 17.18 — AMENDMENTS TO THE CALIFORNIA EXISTING BUILDING…
- Chapter 17.20 — SMALL RESIDENTIAL ROOFTOP SOLAR SYSTEMS
- Chapter 17.25 — ELECTRIC VEHICLE CHARGING STATIONS
- Title 19 — BILLBOARD SIGNS
- Chapter 19.01 — PURPOSE AND APPLICABILITY
- Chapter 19.02 — REVIEW PROCESS
- Chapter 19.03 — ALLOWED LOCATIONS
- Chapter 19.04 — DEVELOPMENT STANDARDS FOR BILLBOARDS
- Chapter 19.05 — NONCONFORMING BILLBOARDS
- Chapter 20.04 — GENERAL PROVISIONS
- Chapter 20.08 — DEFINITIONS
- Chapter 20.12 — PERMIT REQUIREMENTS
- Chapter 20.16 — GRADING REQUIREMENTS
- Chapter 20.20 — CONTROL OF DRAINAGE, EROSION AND DUST CONTROL
- Chapter 20.24 — VIOLATIONS AND APPEALS
- Title 21 — ZONING
- Chapter 21.01 — PURPOSE AND APPLICABILITY OF THE ZONING CODE
- Chapter 21.02 — INTERPRETATION OF THE ZONING CODE
- Chapter 21.03 — ZONING DISTRICTS
- Chapter 21.04 — SPECIAL PLANNED DEVELOPMENTS ESTABLISHED
- Chapter 21.05 — SPECIFIC PLANS ESTABLISHED
- Chapter 21.06 — ZONING MAP
- Chapter 21.08 — PLANNING AUTHORITIES
- Chapter 21.09 — APPLICATION PROCESSING AND COMMON PROCEDURES
- Chapter 21.10 — AMENDMENTS TO THE GENERAL PLAN, ZONING CODE, A…
- Chapter 21.11 — SPECIAL PLANNED DEVELOPMENTS (SPD)
- Chapter 21.12 — DEVELOPMENT AGREEMENTS
- Chapter 21.13 — DEVELOPMENT AGREEMENTS ESTABLISHED
- Chapter 21.14 — SPECIFIC PLANS
- Chapter 21.15 — DEVELOPMENT REVIEW
- Chapter 2.16 — DEVELOPMENT PLANS
- Chapter 21.17 — SITE PLANS
- Chapter 21.18 — PLOT PLANS
- Chapter 21.19 — CONDITIONAL USE PERMITS AND ADMINISTRATIVE USE…
- Chapter 21.20 — TEMPORARY USE PERMITS
- Chapter 21.21 — HOME OCCUPATION PERMITS
- Chapter 21.22 — VARIANCES
- Chapter 21.24 — ENTITLEMENT IMPLEMENTATION, EXTENSIONS, AMENDM…
- Chapter 21.25 — APPEALS AND CALLS FOR REVIEW
- Chapter 21.26 — PUBLIC HEARINGS AND NOTICE
- Chapter 21.27 — REASONABLE ACCOMMODATIONS
- Chapter 21.32 — LAND USE REGULATIONS IN ZONING DISTRICTS
- Chapter 21.33 — RESIDENTIAL ZONING DISTRICTS (R-A, R-1, R-2, R…
- Chapter 21.34 — COMMERCIAL, INDUSTRIAL, AND AIRPORT ZONING DIS…
- Chapter 21.35 — PUBLIC FACILITIES, PARKS AND OPEN SPACE, OPEN …
- Chapter 21.36 — OVERLAY ZONING DISTRICTS (HOS, HP, MU, PD, L, …
- Chapter 21.41 — RULES OF MEASUREMENT
- Chapter 21.42 — ACCESSORY STRUCTURES
- Chapter 21.43 — AWNINGS, CANOPIES, AND PATIO COVERS
- Chapter 21.44 — FENCES, WALLS, AND HEDGES
- Chapter 21.45 — LANDSCAPING AND OPEN SPACE
- Chapter 21.47 — MECHANICAL EQUIPMENT AND SCREENING
- Chapter 21.48 — PARKING AND LOADING REGULATIONS
- Chapter 21.50 — OBJECTIVE DESIGN STANDARDS FOR MIXED-USE AND M…
- Chapter 21.51 — REFUSE AND RECYCLING AREAS
- Chapter 21.52 — SIGNS
- Chapter 21.53 — SWIMMING POOLS
- Chapter 21.54 — UNDERGROUND UTILITIES
- Chapter 21.55 — VISIBILITY AT INTERSECTIONS
- Chapter 21.56 — WATER EFFICIENT LANDSCAPING
- Chapter 21.58 — ACCESSORY DWELLING UNITS
- Chapter 21.59 — ADULT BUSINESS USES
- Chapter 21.60 — CANNABIS
- Chapter 21.61 — DENSITY BONUS
- Chapter 21.62 — HISTORIC PRESERVATION
- Chapter 21.63 — MURALS
- Chapter 21.64 — SHORT-TERM RENTALS
- Chapter 21.65 — URBAN DWELLING UNITS
- Chapter 21.66 — WIRELESS COMMUNICATIONS FACILITIES
- Chapter 21.69 — STANDARDS FOR SPECIFIC LAND USES AND ACTIVITIES
- Chapter 21.74 — GENERAL NONCONFORMING PROVISIONS
- Chapter 21.75 — NONCONFORMING LOTS
- Chapter 21.76 — NONCONFORMING STRUCTURES
- Chapter 21.77 — NONCONFORMING USES
- Chapter 21.78 — OTHER NONCONFORMING PROVISIONS
- Chapter 21.80 — FLOODPLAIN MANAGEMENT
- Chapter 21.81 — HILLSIDE DEVELOPMENT
- Chapter 21.82 — LIGHTING AND ILLUMINATION
- Chapter 21.83 — NOISE
- Chapter 21.84 — OAK TREE PRESERVATION
- Chapter 21.85 — PERFORMANCE STANDARDS—GENERAL
- Chapter 21.86 — SURFACE MINING AND RECLAMATION
- Chapter 21.90 — PURPOSE
- Chapter 21.91 — LAND USE DEFINITIONS
- Chapter 21.92 — GENERAL DEFINITIONS
- Title 22 — SUBDIVISIONS
- Chapter 22.04 — GENERAL PROVISIONS
- Chapter 22.08 — DEFINITIONS
- Chapter 22.12 — TENTATIVE MAP
- Chapter 22.14 — VESTING TENTATIVE MAP PROCEDURES
- Chapter 22.16 — FINAL MAP
- Chapter 22.18 — LOT LINE ADJUSTMENT PROCESS
- Chapter 22.20 — DESIGN OF IMPROVEMENTS
- Chapter 22.24 — CONSTRUCTION OF IMPROVEMENTS
- Chapter 22.28 — EXCEPTIONS
- Chapter 22.32 — APPEAL
- Chapter 22.34 — URBAN LOT SPLITS