Maywood Zoning Code § 5040.30 Time Limit for Processing of Applications
Maywood Zoning Code · 2026-06 edition · updated 2026-09-09 · Maywood
Cite as: Maywood Zoning Code § 5040.30 · Text as of 2026-09-09
When an application has been accepted as complete by the Commission, it shall be scheduled for public hearing so that final action may be achieved within six months of acceptance of the application, except for applications requiring environmental review. Those applications requiring environmental review pursuant to Section 21080 of the Public Resources Code, Application to Discretionary Projects, shall be scheduled to achieve final action within one year of acceptance of the application as complete, pursuant to Section 21100.2 of the Public Resources Code, Time Limits, and Section 65950 of the Government Code, Time Limits for Lead Agency.