A5.204.1 ENERGY STAR equipment and appliances. All equipment and appliances provided by the builder shall be ENERGY STAR labeled if ENERGY STAR is applicable to that equipment or appliance.

A5.204.4 Commissioning. [OSHPD 1 & 4] Building commissioning shall be included in the design and construction processes of the building project to verify that the building’s energy related systems are installed, calibrated and perform according to the owner’s project requirements, basis of design and construction documents.

The owner and designer shall designate an individual as the Commissioning Authority (CxA) to lead, review and oversee the completion of the commissioning process activities. The owner shall document the Owner’s Project Requirements (OPR). The design team shall develop the Basis of

Copyright © 2019 ICC. ALL RIGHTS RESERVED. Accessed by Kevin Day (kevin.day@dgs.ca.gov), (California Building Standards Commission) Order Number #100735044 on Jul 24, 2019 03:54 PM (PDT) pursuant to License Agreement with ICC. No further reproduction or distribution authorized. Single user only, copying and networking prohibited. ANY UNAUTHORIZED REPRODUCTION OR DISTRIBUTION IS A VIOLATION OF THE FEDERAL COPYRIGHT ACT AND THE LICENSE AGREEMENT, AND SUBJECT TO CIVIL AND CRIMINAL PENALTIES THEREUNDER.

100735044

APPENDIX A6.1 – VOLUNTARY STANDARDS FOR HEALTH FACILITIES [OSHPD 1, 2 & 4]

Design (BOD). The CxA shall review these documents for clarity and completeness. The owner and design team shall be responsible for updates to their respective documents, develop and incorporate commissioning requirements into the construction documents and develop and implement a commissioning plan. The CxA shall verify the installation and performance of the systems to be commissioned, verify that training and operation and maintenance documentation have been provided to the owner’s operations staff and complete a commissioning report.

Commissioning process activities shall be completed for the following energy-related systems, at a minimum:

  1. Heating, ventilating, air conditioning and refrigeration (HVAC&R) systems (mechanical and passive) and associated controls.

  2. Lighting and daylighting controls.

  3. Domestic hot water systems.

  4. Renewable energy systems (wind, solar, etc.).

  5. Building envelope systems.

A5.204.4.1 Owner’s Project Requirements (OPR). The expectations and requirements of the building shall be documented by the owner and the designer before the design phase of the project begins. This shall be reviewed by the CxA. At a minimum, this documentation shall include the following:

  1. Environmental and sustainability goals.

  2. Energy efficiency goals.

  3. Indoor environmental quality requirements.

  4. Equipment and systems expectations.

  5. Building occupant and O&M personnel expectations.

A5.204.4.2 Basis of Design (BOD). A written explanation of how the design of the building systems meets the Owner’s Project Requirements shall be completed at the design phase of the building project and updated as necessary during the design and construction phases. This shall be reviewed by the CxA. At a minimum, the Basis of Design document shall cover the following systems:

  1. Heating, ventilation, air conditioning (hvac) systems and controls.

  2. Indoor lighting system and controls.

  3. Water heating system.

  4. Renewable energy systems.

A5.204.4.3 Commissioning plan. A commissioning plan shall be completed to document the approach to how the project will be commissioned and shall be started during the design phase of the building project. This shall be reviewed by the CxA. The Commissioning Plan shall include the following at a minimum:

  1. General project information.

  2. Commissioning goals.

  3. Systems to be commissioned. Plans to test systems and components shall include at a minimum:

a. A detailed explanation of the original design

intent;

b. Equipment and systems to be tested, including

the extent of tests;

c. Functions to be tested;

d. Conditions under which the test shall be per formed; and

e. Measurable criteria for acceptable performance.

  1. Commissioning team information.

  2. Commissioning process activities, schedules and responsibilities – plans for the completion of commissioning requirements listed in Sections A5.204.4.4 through A5.204.4.6 shall be included.

A5.204.4.4 Functional performance testing. Functional performance tests shall demonstrate the correct installation and operation of each component, system and system-tosystem interface in accordance with the approved plans and specifications. Functional performance testing reports shall contain information addressing each of the building components tested, the testing methods utilized and include any readings and adjustments made. This shall be reviewed and verified by the CxA.

A5.204.4.5 Postconstruction documentation and train- ing. A systems manual and systems operations training are required.

A5.204.4.5.1 Systems manual. Documentation of the operational aspects of the building shall be completed within the systems manual and delivered to the building owner and facilities operator. This shall be reviewed by the CxA. At a minimum, the systems manual shall include the following:

  1. Site information, including facility description, history and current requirements.

  2. Site contact information.

  3. Basic operations and maintenance, including general site operating procedures, basic troubleshooting, recommended maintenance requirements, site events log.

  4. Major systems.

  5. Site equipment inventory and maintenance notes.

  6. Other resources and documentation.

A5.204.4.5.2 Systems operations training. The CxA shall oversee the training of the appropriate maintenance staff for each equipment type and/or system. The training shall include, as a minimum, the following:

  1. System/equipment overview (what it is, what it does and what other systems and/or equipment it interfaces with).

  2. Review of the information in the systems manual.

  3. Review of the record drawings on the system/ equipment.

A5.204.4.6 Commissioning report. The CxA shall create a complete report of commissioning process activities under

174 2019 CALIFORNIA GREEN BUILDING STANDARDS CODE

Copyright © 2019 ICC. ALL RIGHTS RESERVED. Accessed by Kevin Day (kevin.day@dgs.ca.gov), (California Building Standards Commission) Order Number #100735044 on Jul 24, 2019 03:54 PM (PDT) pursuant to License Agreement with ICC. No further reproduction or distribution authorized. Single user only, copying and networking prohibited. ANY UNAUTHORIZED REPRODUCTION OR DISTRIBUTION IS A VIOLATION OF THE FEDERAL COPYRIGHT ACT AND THE LICENSE AGREEMENT, AND SUBJECT TO CIVIL AND CRIMINAL PENALTIES THEREUNDER.

100735044

APPENDIX A6.1 – VOLUNTARY STANDARDS FOR HEALTH FACILITIES [OSHPD 1, 2 & 4]

taken through the design, construction and postconstruction phases of the building project and provided to the owner.

A5.204.6 Building orientation and shading. Locate orient and shade the building as required in Section A5.106.9.

Get a plain-English answer with a citation back to this text.

Ask AI about this code
Contents — California Green Building Standards Code (Title 24, Part 11)

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.