Section 505E — PROGRAM IMPLEMENTATION AND ADMINISTRATION; FEE

505E.2 Compliance Deadlines.

San Francisco Building Inspection Commission Codes · edición 2022 · actualizado 2026-07-08 · San Francisco

Esta sección aún no está traducida y se muestra en inglés.

505E.2 Compliance Deadlines.

TABLE 5E-A

Compliance Deadlines (in years [1] )

Compliance Tier Submission of
Screening Form and
Optional Evaluation
Form
Submittal of Permit
Application with Plans
for Seismic Retrofit
Work
Completion of Work
And Issuance of CFC
I 1 2 4
II 1 3 5
III 1 4 6
IV 1 5 September 15, 2021
1   All time periods are in years measured from 90 days after the operative date of this Chapter. 1   All time periods are in years measured from 90 days after the operative date of this Chapter. 1   All time periods are in years measured from 90 days after the operative date of this Chapter. 1   All time periods are in years measured from 90 days after the operative date of this Chapter.