CRC · California Residential Code

When CALGreen energy provisions are voluntary vs. locally adopted mandatory

CALGreen Appendix A4 energy measures are voluntary statewide; a city or county can make them mandatory locally only after obtaining California Energy Commission approval under Title 24, Part 1, § 10‑106 and filing an ordinance (with findings) and receiving California Building Standards Commission acceptance per § 101.7 — steps required by § A4.201.1.

Last reviewed: July 6, 2026

What the code requires — 2-4 sentences

The CALGreen residential appendices (Appendix A4) contain voluntary energy-efficiency measures that are intended to encourage exemplary local standards; they are not mandatory statewide unless a local jurisdiction makes them mandatory following the procedural approvals required by the state. The controlling rule is § A4.201.1: a city, county or city-and-county that adopts these voluntary provisions as mandatory local energy efficiency standards must submit the required application and receive California Energy Commission approval under Title 24, Part 1, Section 10‑106 prior to enforcement, and then file an ordinance and receive California Building Standards Commission acceptance consistent with § 101.7 before enforcement (see § A4.201.1 ).

The single most important rule: CALGreen Appendix A4 energy measures are voluntary by default; they only become enforceable locally when the jurisdiction follows the CEC approval and BSC filing/acceptance process required by § A4.201.1 and § 101.7.

Requirements in detail

Short rule (plain English)

  • Voluntary: CALGreen Appendix A4 energy measures are published as voluntary guidance for jurisdictions and designers. § A4.201.1 states these measures are intended to encourage local adoption but are not mandatory statewide.
  • To make mandatory locally: the local government must (a) submit the required application and obtain CEC approval under Title 24, Part 1, Section 10‑106, and (b) after the CEC verifies and makes the finding, file an ordinance (showing the local modification and findings) and receive BSC acceptance in accordance with § 101.7 prior to enforcement. See § A4.201.1.

Decision-relevant dimensions (quick reference table)

Decision dimension Possible value(s) you care about Code reference
Default status of A4 energy measures Voluntary § A4.201.1
Who may make them mandatory City, county or city & county § A4.201.1
Required state approvals before enforcement CEC approval under Title 24, Part 1, § 10‑106; then BSC acceptance via filing under § 101.7 § A4.201.1 (references Title 24, Part 1, § 10‑106 and § 101.7)
Where voluntary tiers live Appendix A4 (Divisions A4.6, A4.2, etc.) — voluntary tiers may be adopted locally § 304.1 and § A4.601.1
If adopted locally, when enforceable Only after the CEC finding/approval and the BSC acceptance/filing are completed; prior enforcement is not permitted § A4.201.1
Where mandatory statewide energy rules live California Energy Code (Title 24, Part 6) — CEC continues to adopt mandatory energy standards § A4.201.1

How the two tracks interact

  • The State’s mandatory energy standards continue to be set by the California Energy Commission in Title 24, Part 6; CALGreen’s Appendix energy measures are supplementary, voluntary measures intended to encourage higher performance, not to replace Part 6. § A4.201.1 makes this distinction explicit.
  • Voluntary tiers (Tier 1 / Tier 2) and other Appendix measures remain optional unless a local jurisdiction adopts them by ordinance and completes the required state approvals (see § 304.1 and § A4.601.1).

Exceptions & special cases

  • The code emphasizes that making voluntary energy provisions mandatory is a local decision — but any local energy-related ordinance that amends Part 6 or sets local energy standards must get CEC approval under Title 24, Part 1, § 10‑106 before enforcement, as pointed out in § A4.201.1 and related administration sections. Failure to obtain that approval prevents lawful enforcement.
  • Voluntary tiers include model adoption language and a Residential Model Ordinance to help jurisdictions adopt the measures as mandatory; see § A4.701.1 for recommended content of a local adopting ordinance. That model ordinance is guidance for what to include when filing under § 101.7.

Common mistakes

  • Claim: “CALGreen Appendix A4 energy measures are mandatory statewide.” Reality: they are voluntary by default; a local jurisdiction must follow the approval/filing process in § A4.201.1 and § 101.7 to make them mandatory locally.
  • Claim: “A city can start enforcing a local CALGreen energy ordinance immediately upon passing it.” Reality: enforcement must wait until CEC approval (Title 24, Part 1, § 10‑106) and BSC acceptance/filing per § 101.7 occur — those are required prior to enforcement. § A4.201.1 is explicit about this sequencing.
  • Confusing mandatory Chapter 4 residential measures with Appendix A4 voluntary measures. Use the Matrix Adoption Table and § 101.11 process to determine which items are mandatory for a given occupancy vs. which are voluntary Appendix measures available for local adoption.

Worked example — concrete scenario applying the rule

Scenario: City of Sunnyvale wants to require the Appendix A4 Tier 1 energy package for all new single‑family homes (about 100 homes per year).

Step 1 — Decide locally: City council adopts an ordinance specifying that Appendix A4 Tier 1 energy provisions will be mandatory within city limits (the ordinance must include factual findings and the exact text of local modification). Guidance on what to include is in the Residential Model Ordinance language in § A4.701.1.

Step 2 — Submit to CEC: Before enforcement, the city must submit the required application and receive CEC approval consistent with Title 24, Part 1, Section 10‑106, as required by § A4.201.1. The CEC will review whether the local standard is acceptable under the state rules. No local enforcement until the CEC makes the required finding and verifies the filing.

Step 3 — File with BSC: After the CEC verifies and makes its finding, the city files its ordinance (expressly marking the local modification) with the California Building Standards Commission and receives the required acceptance under § 101.7; only after that filing/acceptance may Sunnyvale enforce the new mandatory local energy requirements. § A4.201.1 requires this sequencing.

Outcome: For the 100 homes/year, builders must comply with the newly mandatory Tier 1 measures only for permits issued after the city has both obtained CEC approval and filed/received BSC acceptance per § 101.7. Until those approvals are complete the Tier 1 measures remain voluntary.

Related provisions

  • § A4.201.1 — Scope and procedure for voluntary Appendix A4 energy measures and the requirement for CEC approval and BSC filing before enforcement.
  • § 304.1 — Voluntary tiers described; voluntary tiers may be adopted by local governments and enforced when adopted (reference to local amendment procedures under § 101.7).
  • § A4.601.1 — Confirms Appendix A4 measures are not mandatory unless adopted by local government as specified in § 101.7 (Tier 1 / Tier 2 overview).
  • § A4.701.1 — Residential Model Ordinance guidance for jurisdictions adopting voluntary measures as mandatory (what to include in the adopting ordinance).
  • § 101.7 — (Referenced repeatedly in Appendix text) Procedures and requirements related to local amendments, additions or deletions, including making voluntary measures mandatory; § A4.201.1 requires filing with BSC per § 101.7.
  • § 101.10 / § 101.11 — Identifies that the code contains both mandatory and voluntary measures and describes how to determine which provisions apply to an occupancy (Matrix Adoption Tables, etc.).

Code references

Grounded in the retrieved California Residential Code — click a citation to read the verbatim passage:

  • CRC § 106.8.2.2 Medium relevance — show source text

    Exception: Areas of parking facilities served by parking lifts, including but not limited to automated mechanicalaccess open parking garages as defined in the California Building Code ; or parking facilities otherwise incapable of supporting electric vehicle charging.

    A4.106.8.2.2 Technical requirements. The EV spaces required by Section A4.106.8.2 shall be designed and constructed in accordance with Sections 4.106.4.2, 4.106.4.2.2.1.1, 4.106.4.2.2.1.2, and 4.106.4.2.5.

    SECTION A4.107 (RESERVED)

    SECTION A4.108 —INNOVATIVE CONCEPTS AND LOCAL ENVIRONMENTAL CONDITIONS

    A4.108.1 Innovative concepts and local environmental conditions. The provisions of this code are not intended to prevent the use of any alternate material, appliance, installation, device, arrangement, method, design or method of construction not specifically prescribed by this code. This code does not limit the authority of city, county, or city and county government to make necessary changes to the provisions contained in this code pursuant to Section 101.7.1.

    2025 CALIFORNIA GREEN BUILDING STANDARDS CODE APPENDIX A4-7

    on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.

    APPENDIX A4-8 2025 CALIFORNIA GREEN BUILDING STANDARDS CODE

    on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.

    A4 RESIDENTIAL VOLUNTARY MEASURES

    DIVISION A4.2 – ENERGY EFFICIENCY

    SECTION A4.201—GENERAL

    A4.201.1 Scope. For the purposes of mandatory energy efficiency standards in the California Building Standards Code (Title 24), the California Energy Commission will continue to adopt mandatory standards in the California Energy Code (Title 24, Part 6). It is the intent of these voluntary provisions to encourage local jurisdictions through codification to achieve exemplary performance in the area of building energy efficiency. Local jurisdictions adopting these voluntary provisions as mandatory local energy efficiency standards shall submit the required application and receive the required approval of the California Energy Commission in compliance with Title 24, Part 1, Section 10-106 prior to enforcement. Once the required filing has been verified and finding has been made by the Energy Commission, local jurisdictions shall file an ordinance expressly marking the local modification along with findings and receive the required acceptance from the California Building Standards Commission in compliance with Section 101.7 of this code, prior to enforcement. (Title 24, Part 1, Section 10-106 is available at https://www.energy.ca.gov/programs-and-topics/programs/build- ing-energy-efficiency-standards/2025-building-energy-efficiency

    SECTION A4.202—DEFINITIONS

    A4.202.1 Definitions. The following terms are defined in Chapter 2.

    ENERGY BUDGET.

    LONG-TERM SYSTEM COST (LSC).

    RECOVERED ENERGY, ON-SITE.

    SOLAR POOL HEATING SYSTEM.

    SECTION A4.203—PERFORMANCE APPROACH FOR NEWLY CONSTRUCTED BUILDINGS

  • CRC § 405.4 Medium relevance — show source text
    1. From Division A5.4,

    a. Comply with recycled content of 10 percent of materials based on estimated total cost, or use two products from Table A5.405.4 for at least 75 percent by cost in Section A5.405.4. b. Comply with the 65-percent reduction in construction and demolition waste in Section A5.408.3.1. c. Comply with one elective measure selected from this division.

    1. From Division A5.5,

    a. Comply with resilient flooring systems for 90 percent of resilient flooring in Section A5.504.4.7. b. Comply with thermal insulation meeting 2009 CHPS low-emitting materials list in Section A5.504.4.8. c. Comply with one elective measure selected from this division. 6. Comply with one additional elective measure selected from any division.

    1 Cool roof is required for compliance with Tiers 1 and 2 and may be used to meet energy standards in Part 6, exceed energy standards and to mitigate heat island effect.

    A5.601.3 CALGreen Tier 2.

    A5.601.3.1 Prerequisites. To achieve CALGreen tier status, a project must meet all of the mandatory measures in Chapter 5 and, in addition, meet the provisions of this section.

    A5.601.3.2 Energy performance. For the purposes of mandatory energy efficiency standards in this code, the California Energy Commission will continue to adopt mandatory standards.

    A5.601.3.3 Tier 2. Comply with the energy efficiency requirements in Section A5.203.1.1 and Section A5.203.1.2.2.

    A5.601.3.4 Voluntary measures for Tier 2. In addition to the provisions of Sections A5.601.3.1 and A5.601.3.3 above, compliance with the following voluntary measures from Appendix A5 is required for Tier 2:

    1. From Division A5.1, a. Comply with the designated parking requirements for fuel efficient vehicles for a minimum of 50 percent of parking capacity per Section A5.106.5.1. b. Electric vehicle (EV) charging [N] and Table A5.106.5.3.2 with footnotes. c. Comply with thermal emittance, solar reflectance or SRI values for cool roofs in Section A5.106.11.2 and Table A5.106.11.2.3. [1]

    d. Comply with three elective measures selected from this division.

    APPENDIX A5-42 2025 CALIFORNIA GREEN BUILDING STANDARDS CODE

    on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.

    APPENDIX A5NONRESIDENTIAL VOLUNTARY MEASURES

    1. From Division A5.2 comply with TWO of the following:

    2. Outdoor lighting as described in A5.203.1.1.1.

    3. Service water heating in restaurants as described in A5.203.1.1.2.

    4. Warehouse Dock Seal Doors A5.203.1.1.3.

    5. Daylight Design Power Adjustments 5.203.1.1.4.

    6. Exhaust Air Heat Recovery A5.203.1.1.5.

    7. From Division A5.3,

  • CRC § 409.4 Medium relevance — show source text

    Solar access is the ratio of solar insolation including shade to the
    solar insolation without shade. Shading from obstructions located on the roof or any other part of the building shall not be included in the determination of annual solar access.
    3.
    Life cycle assessment compliant with Section A5.409.4 in this code may be substituted for prescriptive measures from Division A5.4.|

    A5.601.1 Scope. The measures contained in this appendix are not mandatory unless adopted by local government as specified in Section 101.7. The provisions of this section outline means of achieving enhanced construction or reach levels by incorporating addi

    2025 CALIFORNIA GREEN BUILDING STANDARDS CODE APPENDIX A5-41

    on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.

    APPENDIX A5NONRESIDENTIAL VOLUNTARY MEASURES

    tional green building measures for newly constructed nonresidential buildings as well as additions and alterations. In order to meet one of the tier levels designers, builders or property owners are required to incorporate additional green building measures necessary to meet the threshold of each level. Refer to the provisions in Section 301.3 for nonresidential additions and alterations scope and application.

    A5.601.2 CALGreen Tier 1

    A5.601.2.1 Prerequisites. To achieve CALGreen tier status, a project must meet all of the mandatory measures in Chapter 5 and, in addition, meet the provisions of this section.

    A5.601.2.2 Energy performance. For the purposes of mandatory energy efficiency standards in this code, the California Energy Commission will continue to adopt mandatory standards.

    A5.601.2.3 Tier 1. Comply with the energy efficiency requirements in Section A5.203.1.1 and Section A5.203.1.2.1.

    A5.601.2.4 Voluntary measures for Tier 1. In addition to the provisions of Sections A5.601.2.1 and A5.601.2.3 above, compliance with the following voluntary measures from Appendix A5 is required for Tier 1:

    1. From Division A5.1, a. Comply with the designated parking requirements for high-efficiency vehicles for a minimum of 35 percent of parking capacity per Section A5.106.5.1. b. Electric vehicle (EV) charging [N] and Table A5.106.5.3.1 w/ footnotes. c. Comply with thermal emittance, solar reflectance or SRI values for cool roofs in Section A5.106.11.2 and Table A5.106.11.2.2. [1]

    d. Comply with one elective measure selected from this division. 2. From Division A5.2 comply with ONE of the following:

    1. Outdoor lighting as described in A5.203.1.1.1.

    2. Service water heating in restaurants as described in A5.203.1.1.2.

    3. Warehouse Dock Seal Doors A5.203.1.1.3.

    4. Daylight Design Power Adjustments 5.203.1.1.4.

    5. Exhaust Air Heat Recovery A5.203.1.1.5.

    6. From Division A5.3,

    a. Comply with the 12-percent reduction for indoor potable water use in Section A5.303.2.3.1. b. Comply with one elective measure selected from this division.

    1. From Division A5.4,
  • CRC § 703.1 Medium relevance — show source text

    ||||||| |Verifications||||||| |703.1Verification of compliance with this code may include
    construction documents, plans, specifications builder or installer
    certification, inspection reports or other methods acceptable to the
    enforcing agency which show substantial conformance.||||||| |1. Green building measures listed in this table may be mandatory if adopted by a city, county, or city and county as specified in Section 101.7.
    2. Required prerequisite for this Tier.
    3. These measures are currently required elsewhere in statute or in regulation.|1. Green building measures listed in this table may be mandatory if adopted by a city, county, or city and county as specified in Section 101.7.
    2. Required prerequisite for this Tier.
    3. These measures are currently required elsewhere in statute or in regulation.|1. Green building measures listed in this table may be mandatory if adopted by a city, county, or city and county as specified in Section 101.7.
    2. Required prerequisite for this Tier.
    3. These measures are currently required elsewhere in statute or in regulation.|1. Green building measures listed in this table may be mandatory if adopted by a city, county, or city and county as specified in Section 101.7.
    2. Required prerequisite for this Tier.
    3. These measures are currently required elsewhere in statute or in regulation.|1. Green building measures listed in this table may be mandatory if adopted by a city, county, or city and county as specified in Section 101.7.
    2. Required prerequisite for this Tier.
    3. These measures are currently required elsewhere in statute or in regulation.|1. Green building measures listed in this table may be mandatory if adopted by a city, county, or city and county as specified in Section 101.7.
    2. Required prerequisite for this Tier.
    3. These measures are currently required elsewhere in statute or in regulation.|1. Green building measures listed in this table may be mandatory if adopted by a city, county, or city and county as specified in Section 101.7.
    2. Required prerequisite for this Tier.
    3. These measures are currently required elsewhere in statute or in regulation.|

    2025 CALIFORNIA GREEN BUILDING STANDARDS CODE APPENDIX A4-29

    on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.

    APPENDIX A4-30 2025 CALIFORNIA GREEN BUILDING STANDARDS CODE

    on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.

    DIVISION A4.7 – RESIDENTIAL MODEL ORDINANCE

    A4.701.1 General. The voluntary measures of this code are designed and promulgated to be adopted by reference and made mandatory by local ordinance pursuant to Section 101.7. Jurisdictions wishing to adopt the voluntary provisions of this code as an enforceable regulation governing structures and premises should ensure that certain factual information is included in the adopting ordinance and that the measures are appropriate and achievable and are considered to be suitable as mandatory by the city, county, or city and county. The following sample adoption ordinance addresses several key elements of a code adoption ordinance, including the information required for insertion into the code text.

    This code does not limit the authority of city, county, or city and county government to make necessary changes to the provisions contained in this code.

  • CRC § 602.1 Medium relevance — show source text

    VOLUNTARY MEASURES. . . . . . . . . . . . . . . . . APPENDIX A5-3

    A5.1 Planning and Design . . . . . . . . . . . . . . . . . APPENDIX A5-3 A5.2 Energy Efficiency . . . . . . . . . . . . . . . . . . . APPENDIX A5-13 A5.3 Water Efficiency and Conservation . . . APPENDIX A5-19 A5.4 Material Conservation and Resource Efficiency . . . . . . . . . . . . . . . . . . . . . . . . APPENDIX A5-25 A5.5 Environmental Quality . . . . . . . . . . . . . . APPENDIX A5-35 A5.6 Voluntary Tiers . . . . . . . . . . . . . . . . . . . . . APPENDIX A5-41 A5.601 CALGren Tier 1 and Tier 2. . . . . . . . . . APPENDIX A5-41

    A5.602 CALGreen Verification Guidelines Mandatory Measures Checklist . . . . . . . . . . . . . . . APPENDIX A5-44

    A5.602.1 CALGreen Verification Guidelines

    Tier 1 Checklist . . . . . . . . . . . . . . . . . APPENDIX A5-48

    A5.602.2 CALGreen Verification Guidelines

    Tier 2 Checklist . . . . . . . . . . . . . . . . . APPENDIX A5-55

    APPENDIX A6 VOLUNTARY STANDARDS FOR HEALTH

    FACILITIES [OSHPD 1, 2 & 4] . . . . . . . . . . . APPENDIX A6.1-3 A6.1 Site Planning and Design . . . . . . . . . . . APPENDIX A6.1-3 A6.2 Energy Efficiency . . . . . . . . . . . . . . . . . . APPENDIX A6.1-3 A6.4 Material Conservation and Resource Efficiency . . . . . . . . . . . . . APPENDIX A6.1-32 A6.5 Environmental Quality . . . . . . . . . . . . APPENDIX A6.1-33

    INDEX . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . INDEX-1

    HISTORY NOTE. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . HIST-1

    2025 CALIFORNIA GREEN BUILDING STANDARDS CODE vii

    on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.

    viii 2025 CALIFORNIA GREEN BUILDING STANDARDS CODE

    on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.

    CALIFORNIA GREEN BUILDING STANDARDS CODE – MATRIX ADOPTION TABLE

    CHAPTER 1 – ADMINISTRATION

    (Matrix Adoption Tables are nonregulatory, intended only as an aid to the code user. See Chapter 1 for state agency authority and building applications.)

    |Adopting

  • CRC § 409.4 Medium relevance — show source text

    Shading from obstructions located on the roof or any other part of the building shall not be included in the determination of annual solar access.
    3.
    Life cycle assessment compliant with Section A5.409.4 in this code may be substituted for prescriptive measures from Division A5.4.|1.
    Exception: Allowance may be permitted in Tier 2 for up to 5-percent specialty purpose flooring.
    2.
    Solar water-heating system requirement for newly constructed restaurants as per A5.203.1.1.2.
    Exceptions:
    a. Buildings with a natural gas service water heater with a minimum of 95-percent thermal efficiency.
    b. Buildings where greater than 75 percent of the total roof area has annual solar access that is less than 70 percent. Solar access is the ratio of solar insolation including shade to the
    solar insolation without shade. Shading from obstructions located on the roof or any other part of the building shall not be included in the determination of annual solar access.
    3.
    Life cycle assessment compliant with Section A5.409.4 in this code may be substituted for prescriptive measures from Division A5.4.|1.
    Exception: Allowance may be permitted in Tier 2 for up to 5-percent specialty purpose flooring.
    2.
    Solar water-heating system requirement for newly constructed restaurants as per A5.203.1.1.2.
    Exceptions:
    a. Buildings with a natural gas service water heater with a minimum of 95-percent thermal efficiency.
    b. Buildings where greater than 75 percent of the total roof area has annual solar access that is less than 70 percent. Solar access is the ratio of solar insolation including shade to the
    solar insolation without shade. Shading from obstructions located on the roof or any other part of the building shall not be included in the determination of annual solar access.
    3.
    Life cycle assessment compliant with Section A5.409.4 in this code may be substituted for prescriptive measures from Division A5.4.|

    A5.601.1 Scope. The measures contained in this appendix are not mandatory unless adopted by local government as specified in Section 101.7. The provisions of this section outline means of achieving enhanced construction or reach levels by incorporating addi

    2025 CALIFORNIA GREEN BUILDING STANDARDS CODE APPENDIX A5-41

    on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.

    APPENDIX A5NONRESIDENTIAL VOLUNTARY MEASURES

    tional green building measures for newly constructed nonresidential buildings as well as additions and alterations. In order to meet one of the tier levels designers, builders or property owners are required to incorporate additional green building measures necessary to meet the threshold of each level. Refer to the provisions in Section 301.3 for nonresidential additions and alterations scope and application.

    A5.601.2 CALGreen Tier 1

    A5.601.2.1 Prerequisites. To achieve CALGreen tier status, a project must meet all of the mandatory measures in Chapter 5 and, in addition, meet the provisions of this section.

    A5.601.2.2 Energy performance. For the purposes of mandatory energy efficiency standards in this code, the California Energy Commission will continue to adopt mandatory standards.

  • CRC § 101.7. Medium relevance — show source text

    Green building measures listed in this table may be mandatory if adopted by a city, county, or city and county as specified in Section 101.7.
    2. Required prerequisite for this Tier.
    3. These measures are currently required elsewhere in statute or in regulation.|1. Green building measures listed in this table may be mandatory if adopted by a city, county, or city and county as specified in Section 101.7.
    2. Required prerequisite for this Tier.
    3. These measures are currently required elsewhere in statute or in regulation.|

    2025 CALIFORNIA GREEN BUILDING STANDARDS CODE APPENDIX A4-29

    on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.

    APPENDIX A4-30 2025 CALIFORNIA GREEN BUILDING STANDARDS CODE

    on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.

    DIVISION A4.7 – RESIDENTIAL MODEL ORDINANCE

    A4.701.1 General. The voluntary measures of this code are designed and promulgated to be adopted by reference and made mandatory by local ordinance pursuant to Section 101.7. Jurisdictions wishing to adopt the voluntary provisions of this code as an enforceable regulation governing structures and premises should ensure that certain factual information is included in the adopting ordinance and that the measures are appropriate and achievable and are considered to be suitable as mandatory by the city, county, or city and county. The following sample adoption ordinance addresses several key elements of a code adoption ordinance, including the information required for insertion into the code text.

    This code does not limit the authority of city, county, or city and county government to make necessary changes to the provisions contained in this code.

    SAMPLE RESOLUTION FOR ADOPTION OF THE TIER 1 OR TIER 2 PROVISIONS OF THE CALIFORNIA GREEN BUILDING STANDARDS CODE WITH OR WITHOUT ADDITIONAL ITEMS NECESSARY TO ADDRESS INNOVATIVE CONCEPTS OR LOCAL ENVIRONMENTAL CONDITIONS.

    ATTACHMENT___.

    SAMPLE RESOLUTION ADOPTING THE CALIFORNIA GREEN BUILDING STANDARDS CODE APPENDICES AS A MANDATORY REFERENCE STANDARD

    CITY OF ________________________

    RESOLUTION # __________________

    RESOLUTION ADOPTING ENHANCED GREEN BUILDING MEASURES FOR NEW AND EXISTING RESIDENTIAL CONSTRUCTION.

    WHEREAS, the City/County of ______’s (City or County) General Plan sets forth goals for preserving and improving the natural and built environment of the City/County, protecting the health of its residents and visitors, and fostering its economy; and

    WHEREAS, green building is a holistic approach to design, construction and demolition that minimizes the building’s impact on the environment, the occupants and the community; and

    WHEREAS, green buildings benefit building industry professionals, residents and communities by improving construction quality; increasing building durability; reducing utility, maintenance, water and energy costs; creating healthier homes; and enhancing comfort and livability; and

    WHEREAS, the California Green Building Standards Code appendices have included voluntary tiers to provide a city, county, or city and county, building professionals, and the general public with a range of voluntary green building measures for builders to choose from when constructing homes in California; and

  • CRC § 3-4 Medium relevance — show source text

    302 Mixed Occupancy Buildings . . . . . . . . . . . . . . . . . . . . . . .3-4 303 Phased Projects. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3-4 304 Voluntary Tiers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3-4 305 CALGreen Tier 1 and CALGreen Tier 2 . . . . . . . . . . . . . .3-4

    306 Voluntary Measures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3-4

    CHAPTER 4 RESIDENTIAL MANDATORY MEASURES . . . . . . 4-3

    4.1 Planning and Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4-3 4.2 Energy Efficiency . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4-7 4.3 Water Efficiency and Conservation . . . . . . . . . . . . . . . . .4-9 4.4 Material Conservation and Resource Efficiency . . . . 4-11 4.5 Environmental Quality . . . . . . . . . . . . . . . . . . . . . . . . . . 4-13

    CHAPTER 5 NONRESIDENTIAL MANDATORY MEASURES . . 5-3

    5.1 Planning and Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .5-3 5.2 Energy Efficiency . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 5-15 5.3 Water Efficiency and Conservation . . . . . . . . . . . . . . . 5-19 5.4 Material Conservation and Resource Efficiency . . . . 5-23 5.5 Environmental Quality . . . . . . . . . . . . . . . . . . . . . . . . . . 5-31

    CHAPTER 6 REFERENCED ORGANIZATIONS

    AND STANDARDS. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 6-3

    601 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .6-3

    CHAPTER 7 INSTALLER AND SPECIAL

    INSPECTOR QUALIFICATIONS . . . . . . . . . . . . . . . . . . . . . . 7-3 701 General (Reserved) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .7-3 702 Qualifications. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .7-3

  • CRC § 1-5 Medium relevance — show source text

    102 Construction Documents

    and Installation Verification . . . . . . . . . . . . . . . . . . . .1-5

    103 Building Standards Commission. . . . . . . . . . . . . . . . . . .1-5 104 Department of Housing and Community Development. . . . . . . . . . . . . . . . . .1-6 105 Division of the State Architect . . . . . . . . . . . . . . . . . . . . .1-6

    106 Office of Statewide Health Planning and Development . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1-6

    CHAPTER 2 DEFINITIONS . . . . . . . . . . . . . . . . . . . . . . . . . . . . 2-3

    201 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .2-3

    202 Definitions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .2-3

    CHAPTER 3 GREEN BUILDING . . . . . . . . . . . . . . . . . . . . . . . . 3-3

    301 General . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3-3

    302 Mixed Occupancy Buildings . . . . . . . . . . . . . . . . . . . . . . .3-4 303 Phased Projects. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3-4 304 Voluntary Tiers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3-4 305 CALGreen Tier 1 and CALGreen Tier 2 . . . . . . . . . . . . . .3-4

    306 Voluntary Measures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3-4

    CHAPTER 4 RESIDENTIAL MANDATORY MEASURES . . . . . . 4-3

    4.1 Planning and Design . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4-3 4.2 Energy Efficiency . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .4-7 4.3 Water Efficiency and Conservation . . . . . . . . . . . . . . . . .4-9 4.4 Material Conservation and Resource Efficiency . . . . 4-11 4.5 Environmental Quality . . . . . . . . . . . . . . . . . . . . . . . . . . 4-13

    CHAPTER 5 NONRESIDENTIAL MANDATORY MEASURES . . 5-3

  • CRC § 304.1 Medium relevance — show source text

    SECTION 304—VOLUNTARY TIERS

    304.1 Purpose. Voluntary tiers are intended to further encourage building practices that improve public health, safety and general welfare by promoting the use of building concepts which minimize the building’s impact on the environment and promote a more sustainable design.

    304.1.1 Tiers. The provisions of Divisions A4.6 and A5.6 outline means, in the form of voluntary tiers, for achieving enhanced construction levels by incorporating additional measures for residential and nonresidential new construction. Voluntary tiers may be adopted by local governments and, when adopted, enforced by local enforcing agencies. Buildings complying with tiers specified for each occupancy contain additional prerequisite and elective green building measures necessary to meet the threshold of each tier. See Section 101.7 of this code for procedures and requirements related to local amendments, additions or deletions, including changes to energy standards.

    [BSC & HCD] Where there are practical difficulties involved in complying with the threshold levels of a tier, the enforcing agency may grant modifications for individual cases. The enforcing agency shall first find that a special individual reason makes the strict letter of the tier impractical and that modification is in conformance with the intent and purpose of the measure. The details of any action granting modification shall be recorded and entered in the files of the enforcing agency.

    SECTION 305 [OSHPD 1]— CALGreen TIER 1 AND CALGreen TIER 2

    305.1 CALGreen Tier 1 and CALGreen Tier 2 buildings contain voluntary green building measures necessary to meet the threshold of each level.

    305.1.1 CALGreen Tier 1. To achieve CALGreen Tier 1, buildings must comply with the latest edition of “Savings By Design, Healthcare Modeling Procedures” found online at http://www.energysoft.com/main/page_ downloads_ sbd_healthcare.html.

    305.1.2 CALGreen Tier 2. To achieve CALGreen Tier 2, buildings must exceed the latest edition of “Savings By Design, Healthcare Modeling Procedures” by a minimum of 15 percent.

    SECTION 306 [DSA-SS]—VOLUNTARY MEASURES

    306.1 Purpose. For public schools and community colleges, voluntary measures further encourage building practices that improve public health, safety and general welfare by promoting the use of building concepts which minimize the building’s impact on the environment and promote a more sustainable design.

    306.1.1 Appendix A5, Divisions A5.1 through A5.5, outline means of achieving enhanced sustainable design and construction by incorporating voluntary measures that exceed the mandatory measures.

    306.1.2 Chapter 5 Nonresidential Mandatory Measures that are not adopted as mandatory measures by DSA-SS are voluntary measures recommended and encouraged for the design, construction, verification and maintenance of non-energy systems.

    Note: The building commissioning requirements for energy efficiency specified in the California Energy Code are required.

    3-4 2025 CALIFORNIA GREEN BUILDING STANDARDS CODE

    on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.

    CALIFORNIA GREEN BUILDING STANDARDS CODE – MATRIX ADOPTION TABLE

    CHAPTER 4 – RESIDENTIAL MANDATORY MEASURES

    (Matrix Adoption Tables are nonregulatory, intended only as an aid to the code user. See Chapter 1 for state agency authority and building applications.)

  • CRC § 106.9 Medium relevance — show source text
    FEATURE OR MEASURE COMPLIANCE LEVELS Col3 Col4 NOTES
    FEATURE OR MEASURE Mandatory
    CALGreen
    VOLUNTARY
    CALGreen
    VOLUNTARY
    CALGreen
    VOLUNTARY
    CALGreen
    FEATURE OR MEASURE Mandatory
    CALGreen
    Tier 1 Tier 2 Tier 2
    DIVISION A6.1 – PLANNING AND DESIGN
    SECTION Site Development SECTION Site Development SECTION Site Development SECTION Site Development SECTION Site Development
    **A6.106.9 Building orientation.**Locate and orient the building as follows:
    1. When site and location permit, orient the building with the long sides facing north and
    south.
    2. Protect the building from thermal loss, drafts and degradation of the building envelope
    caused by wind and wind-driven materials such as dust.
    DIVISION A6.2 – ENERGY EFFICIENCY
    SECTION A6.203 Performance Measures SECTION A6.203 Performance Measures SECTION A6.203 Performance Measures SECTION A6.203 Performance Measures SECTION A6.203 Performance Measures
    A6.203.1 Energy performance. [OSHPD 1]
    **A6.203.1.1 CALGreen Tier 1. [OSHPD 1]**Buildings must comply with the latest edition of
    “Savings By Design, Healthcare Modeling Procedures.”
    A.5.203.1.2 CALGreen Tier 2. [OSHPD 1] Buildings must exceed the latest edition of “Savings
    By Design, Healthcare Modeling Procedures” by 15 percent.
    SECTION A6.204 Prescriptive Measures
    **A6.204.1 ENERGY STAR equipment and appliances.**All equipment and appliances provided
    by the builder shall be ENERGY STAR labeled if ENERGY STAR is applicable to that equipment
    or appliance.
    A6.204.4 Commissioning. Building commissioning for all building systems covered by T24,
    Part 6, process systems and renewable energy systems shall be included in the design and
    construction processes of the building project. Commissioning requirements shall include as
    a minimum items listed in Section A6.204.4.
    **A6.204.4.1 Owner’s Project Requirements (OPR).**Documented before the design phase of
    the project begins the OPR shall include items listed in Section A6.204.4.
    **A6.204.4.2 Basis of Design (BOD).**A written explanation of how the design of the building
    systems meets the OPR shall be completed at the design phase of the building project and
    updated periodically to cover the systems listed in Section A6.204.4.2.
    **A6.204.4.3 Commissioning plan.
  • CRC § 8-40 Medium relevance — show source text

    . . . . . . . . . . . . . 8-40

    APPENDIX A4 RESIDENTIAL

    VOLUNTARY MEASURES. . . . . . . . . . . . . . . . . APPENDIX A4-3

    A4.1 Planning and Design . . . . . . . . . . . . . . . . . APPENDIX A4-3 A4.2 Energy Efficiency . . . . . . . . . . . . . . . . . . . . APPENDIX A4-9 A4.3 Water Efficiency and Conservation . . . APPENDIX A4-13 A4.4 Material Conservation and Resource Efficiency . . . . . . . . . . . . . . . . . . . . . . . . APPENDIX A4-15 A4.5 Environmental Quality . . . . . . . . . . . . . . APPENDIX A4-19 A4.6 Tier 1 and Tier 2 . . . . . . . . . . . . . . . . . . . . APPENDIX A4-21

    Division A4.6—Residential Occupancies Application Checklist . . . . . . . . . . . . . APPENDIX A4-23 A4.7 Residential Model Ordinance . . . . . . . . . APPENDIX A4-31

    APPENDIX A5 NONRESIDENTIAL

    VOLUNTARY MEASURES. . . . . . . . . . . . . . . . . APPENDIX A5-3

    A5.1 Planning and Design . . . . . . . . . . . . . . . . . APPENDIX A5-3 A5.2 Energy Efficiency . . . . . . . . . . . . . . . . . . . APPENDIX A5-13 A5.3 Water Efficiency and Conservation . . . APPENDIX A5-19 A5.4 Material Conservation and Resource Efficiency . . . . . . . . . . . . . . . . . . . . . . . . APPENDIX A5-25 A5.5 Environmental Quality . . . . . . . . . . . . . . APPENDIX A5-35 A5.6 Voluntary Tiers . . . . . . . . . . . . . . . . . . . . . APPENDIX A5-41 A5.601 CALGren Tier 1 and Tier 2. . . . . . . . . . APPENDIX A5-41

    A5.602 CALGreen Verification Guidelines Mandatory Measures Checklist . . . . . . . . . . . . . . . APPENDIX A5-44

    A5.602.1 CALGreen Verification Guidelines

    Tier 1 Checklist . . . . . . . . . . . . . . . . . APPENDIX A5-48

    A5.602.2 CALGreen Verification Guidelines

    Tier 2 Checklist . . . . . . . . . . . . . . . . . APPENDIX A5-55

    APPENDIX A6 VOLUNTARY STANDARDS FOR HEALTH

Frequently asked questions

Can a city immediately enforce CALGreen Appendix A4 energy measures by local ordinance?

No. Appendix A4 measures are voluntary by default. To enforce them locally the jurisdiction must obtain CEC approval under Title 24, Part 1, § 10‑106 and then file the ordinance and receive BSC acceptance per § 101.7 before enforcement, per § A4.201.1.

Are statewide energy standards in CALGreen?

No. The state’s mandatory energy standards are adopted by the California Energy Commission in Title 24, Part 6; CALGreen Appendix energy measures are supplementary, voluntary measures unless adopted locally. § A4.201.1 explains this separation.

Where can a local jurisdiction find model language to adopt the voluntary measures as mandatory?

See the Residential Model Ordinance guidance in § A4.701.1, which lists elements a jurisdiction should include when adopting Appendix A measures as mandatory.

What happens if a local jurisdiction amends energy requirements but does not get CEC approval?

Per § A4.201.1, the required CEC approval under Title 24, Part 1, § 10‑106 and the subsequent filing/acceptance with the BSC under § 101.7 are prerequisites to enforcement; without those approvals the jurisdiction cannot lawfully enforce the local energy standards.

Do voluntary CALGreen tiers become enforceable automatically if the local building department wants them?

No — voluntary tiers must be formally adopted by ordinance and processed through the CEC/BSC approval steps specified in § A4.201.1 and related administrative sections before they may be enforced.

More in California Residential Code

Ask about the CRC

Get cited, plain-English answers on the California Residential Code for your project — any code section, any scenario.

Start Free Trial

Related in the CRC