Title 24 · California Energy Code
Certificates of Acceptance / Installation Certificates — what must be submitted
Before a certificate of occupancy is issued you must submit the required Certificates of Acceptance (for systems listed in § 10-103(a)) and Installation Certificates for lighting or energy-management controls (which must show compliance with NA7.7.1 / NA7.7.2). Acceptance tests must follow the named NA7 procedures, and where Part‑1 requires certified testers the tester’s certification ID must appear on the Certificate. The uploaded code excerpts direct when and which documents are required, but the full NA7.7.1 and NA7.7.2 checklist text was not present in the retrieved files — I can retrieve or review those appendices and produce a fillable checklist if you want.
Last reviewed: July 6, 2026
What the code requires — 2–4 sentences
Before an occupancy permit is issued the building owner (or their agent) must submit formal documents certifying that required systems were installed and function as intended. Specifically, a Certificate of Acceptance must be submitted to the enforcement agency for systems that require acceptance testing under § 10-103(a), and certain lighting and energy-management controls require an Installation Certificate that affirms compliance with the referenced NA7 installation requirements. The Code ties each required certificate to the specific NA7 test or installation procedure (for example, NA7.5.x for acceptance tests and NA7.7.1 / NA7.7.2 for lighting / EMCS installation), and when Part‑1 certification rules apply the field tester’s certification ID must appear on the Certificate of Acceptance.
The single most important rule: submit the required Certificate(s) (Acceptance and/or Installation) to the enforcing agency before the occupancy permit is granted — Certificates prove required tests were done and systems meet the NA7 acceptance/installation requirements.
Requirements in detail
Which documents, and when
Certificate of Acceptance — required for equipment/systems listed in § 10-103(a) (many mechanical, ventilation, refrigeration, elevator, parking garage and other systems). It certifies that the equipment "meets the Acceptance Requirements for Code Compliance" and must be submitted to the enforcement agency prior to issuance of occupancy.
Installation Certificate — required for certain lighting control systems and energy management control systems to be "recognized for compliance with Part 6." The Code requires the Installation Certificate be submitted in accordance with § 10-103(a) and to certify compliance with the NA7 installation appendices (for example § NA7.7.1 for lighting controls and § NA7.7.2 for energy management control systems).
Technician certification/disclosure: where Part‑1 § 10-103.1 requires certification, the acceptance testing must be performed by a certified acceptance-test technician (example: CLCATT for lighting controls or CMATT for mechanical) and that technician must disclose a valid certification identification number on the Certificate of Acceptance. The technician and employer rules are repeated in multiple acceptance sections.
What each certificate must show (decision-relevant checklist)
Use this table to decide which document you must prepare and what to include.
| Document | When required | Core contents (decision‑relevant) | Signed / ID by | Code Reference |
|---|---|---|---|---|
| Certificate of Acceptance | Before occupancy for systems listed in § 10-103(a) (HVAC, DOAS, duct tests, air economizers, refrigeration, elevators, parking garage ventilation, etc.) | Statement that equipment/systems meet acceptance requirements; test reports / measured results per the applicable NA7 test procedure; plans/specs/installation info if required | Field tester + responsible person; where required include certified technician ID (CMATT, CLCATT, etc.) on form | § 10-103(a) — acceptance list and submission requirement |
| Installation Certificate (lighting / EMCS) | When a lighting control system or EMCS is installed to meet Part 6 requirements | Certification that installation meets Part 6 rules and the NA7 installation checklist (e.g., wiring, labeling, settings, override requirements, documentation) | Installer or responsible party; in some cases certifier/technician info tied to Part 1 rules | § 130.4(b) referencing § NA7.7.1 and § NA7.7.2; submit in accordance with § 10-103(a) |
| Technician statement / certification | When Part 1 § 10-103.1 or acceptance-test rules require a certified tester | Tester certification ID and attestation that acceptance procedures were completed and results are true and correct | Certified acceptance-test technician (e.g., CLCATT or CMATT) — include certification ID on Certificate of Acceptance | § 130.4(c) and Part 1 references (see § 10-103(a)4) |
What the Code ties to specific NA7 procedures
Acceptance testing procedures are called out by system type (for example NA7.5.1 for outdoor air ventilation, NA7.5.4 for air economizers/DOAS/HRV/ERV testing). The Certificate of Acceptance must reflect the applicable NA7 test and results.
Installation Certificates for lighting controls must certify compliance with the NA7 installation appendices — the Code explicitly requires Installation Certificates to “comply with Reference Nonresidential Appendix NA7.7.1” (lighting) and “NA7.7.2” (energy management control systems) when those systems are used to meet Part 6 requirements. Note: the main code references NA7.7.1 and NA7.7.2 as the required installation checklists.
Important note: the uploaded files used for this page include the Code text that directs submission of certificates and references NA7.7.1 / NA7.7.2, but the full text of § NA7.7.1 and § NA7.7.2 (the detailed installation checklists themselves) was not present in the retrieved files I searched. If you want the exact NA7.7.1/NA7.7.2 worksheets or line-item fields, I can look them up in the missing appendix text if you upload it or allow a web lookup.
Exceptions & special cases
Factory‑calibrated air economizers: air economizers that are factory‑installed and certified to the Commission as factory calibrated and tested may be exempt from certain functional testing steps of the NA7.5.4 acceptance procedure. That exception is explicit in the mechanical acceptance section.
Healthcare facilities: several acceptance/installation documentation requirements defer to OSHPD (the Office of Statewide Health Planning & Development) or other healthcare-specific procedures; healthcare occupancies are carved out for some NA7 acceptance rules (i.e., they follow OSHPD documentation).
Small / alteration work: some installation/acceptance requirements only apply to new systems or to altered systems meeting certain thresholds (the parent sections spell out when testing applies — check the specific § tied to the system). Always confirm whether the system is “new” vs “altered” in the controlling §.
Common mistakes
Waiting until after the final inspection: the Certificate(s) must be submitted before the occupancy permit is granted — failure to submit halts final occupancy.
Omitting the tester’s certification ID when required: when Part 1 requires a certified tester (e.g., CLCATT for lighting controls, CMATT for mechanical), the technician’s certification identification number must be shown on the Certificate of Acceptance. Inspecting authorities will reject certificates missing the required testers’ IDs.
Submitting incomplete NA7 evidence: the Certificate must reference and include the results from the applicable NA7 acceptance/installation procedure (not just a short narrative). For lighting controls the Installation Certificate must conform to § NA7.7.1 (or NA7.7.2 for EMCS). If you submit a generic installer letter without the NA7 checklist or referenced data, it may be rejected.
Confusing Certificate types: do not substitute an Installation Certificate for a Certificate of Acceptance (or vice versa). The Code differentiates acceptance testing (Certificate of Acceptance) from installation-only attestations (Installation Certificate) and ties each to specific systems and NA7 procedures.
Worked example — concrete scenario
Scenario: A new 20,000 ft² office (nonresidential) installs a DOAS with an air economizer and a networked Energy Management Control System (EMCS) that will also perform required lighting control functions.
What must be submitted:
DOAS / air economizer acceptance — because DOAS/air economizers are listed in the acceptance table, the project must submit a Certificate of Acceptance showing the DOAS/economizer was tested in accordance with NA7.5.4 (functional tests and measured results). If the economizer is factory‑certified by the manufacturer and so listed, certain functional tests may be excepted per the Code. Submit this Certificate before occupancy.
EMCS used for lighting control — because the EMCS is functioning as a lighting control required by Part 6, the project must submit an Installation Certificate certifying the EMCS “functionally meets all applicable requirements” and complies with § NA7.7.2, submitted per § 10-103(a). If Part‑1 certification applies, the acceptance testing and certificates must include the certified technician’s ID as required.
Numeric example of timing:
- Testing performed and results recorded on 6/10.
- Certificate of Acceptance (DOAS) signed by the field tester + responsible person and uploaded/submitted to the enforcing agency on 6/12.
- Installation Certificate for EMCS signed by installer and submitted on 6/12.
- Final inspection 6/15 — enforcement agency verifies certificates are on file; occupancy permit issued the same day if everything is complete.
Key citations for the scenario: § 10-103(a) for required Certificates of Acceptance and submission timing; § 130.4(b) which requires Installation Certificates to comply with § NA7.7.1 / § NA7.7.2 when applicable.
Related provisions
- § 10-103(a) — Certificate of Acceptance submission requirements and list of systems that require acceptance testing.
- § 130.4 — Lighting control acceptance and Installation Certificate requirements (references NA7.6, NA7.7.1, NA7.7.2).
- § 120.5 — Nonresidential mechanical system acceptance (lists systems and references NA7.5.x acceptance procedures).
- § 160.3(d) — Multifamily mechanical acceptance requirements and CMATT rules for some multifamily systems.
- § 110.6(a) — Fenestration acceptance requirements (site-built fenestration must be certified per NA7).
Code references
Grounded in the retrieved California Energy Code — click a citation to read the verbatim passage:
§ 209.5 High relevance — show source text
APPENDIX A6.1 — VOLUNTARY STANDARDS FOR HEALTH FACILITIES [OSHPD 1, 2 & 4]
Exception 3 to Section A6.209.5: Traffic Signs. Traffic signs shall meet the requirements of the Appliance Efficiency Regulations.
A6.209.6 Sign lighting controls. All signs with permanently connected lighting shall meet the requirements below:
- Automatic time switch control. All signs with permanently connected lighting shall be controlled with an automatic time switch control that complies with the applicable requirements of Section A6.209.1.
- Photocontrol or outdoor astronomical time switch control. All outdoor signs shall be controlled with a photocontrol or outdoor astronomical time switch control.
Exception: Outdoor signs in tunnels and large covered areas that require illumination during daylight hours. 3. Dimming. All outdoor signs shall be controlled with a dimmer that provides the ability to automatically reduce sign power by a minimum of 65 percent during nighttime hours. Exceptions:
- Signs that are illuminated for less than 1 hour per day during daylight hours.
- Outdoor signs in tunnels and large covered areas that require illumination during daylight hours.
- Metal halide, high pressure sodium, cold cathode and neon lamps used to illuminated signs or parts of signs.
- Demand Responsive Electronic Message Center Control. An Electronic Message Center (EMC) having a new connected lighting power load greater than 15 kW shall have a control installed that is capable of reducing the lighting power by a minimum of 30 percent when receiving a demand response signal that is sent out by the local utility.
- EMCs required by a health or life safety statue ordinance or regulation, including but not limited to exit signs and traffic signs.
A6.209.7 Nonresidential lighting control acceptance. Before an occupancy permit is granted for a new building or space or a new lighting system serving a building, space or site is operated for normal use, all indoor and outdoor lighting controls serving the building, space or site shall be certified as meeting the Acceptance Requirements for Code Compliance. A Certificate of Acceptance shall be submitted to the enforcement agency under Section 10-103(a) of Title 24, Part 1, that:
Certifies that plans, specifications, installation certificates and operating and maintenance information meet the requirements of Title 24, Part 6.
Certifies that automatic daylighting controls meet the applicable requirements of Sections A6.209.1 and A6.209.2.3.2.4.
Certifies that when a multilevel astronomical time switch is used to meet Exception 3 to Section A6.209.2.3.2.2 all general lighting in the skylit area is controlled by a multilevel astronomical time switch that meets the applicable requirements of Section A6.209.1 and that has an override switch that meets the requirements of Section A209.2.4.2.
Certifies that lighting controls meet the requirements of Sections A6.209.2.1 through A6.209.2.3 and Title 24, Part 6, Sections 131(e) and (f) and 146(a)2, as applicable.
Certifies that automatic lighting controls meet the applicable requirements of Sections A6.209.1 and A6.209.2.4.
Certifies that occupant-sensors meet the applicable requirements of Sections A6.209.1 and A6.209.2.4.
Certified that outdoor lighting controls meet the applicable requirements of Sections A6.209.1 and A6.209.3.
§ 5.1. High relevance — show source text
(a) Before an occupancy permit is granted, the following equipment and systems shall be certified as meeting the Acceptance Requirements for Code Compliance, as specified by the Reference Nonresidential Appendix NA7. A Certificate of Acceptance shall be submitted to the enforcement agency that certifies that the equipment and systems meet the acceptance requirements:
Outdoor air ventilation systems shall be tested in accordance with NA7.5.1.
Constant volume, single zone unitary air conditioning and heat pump unit controls shall be tested in accordance with NA7.5.2.
Duct systems that are subject to testing under Section 120.4(g)1, Section 141.0(b)2Di or Section 141.0(b)2Dii shall be tested in accordance with NA7.5.3.
Air economizers, DOAS, HRV or ERV systems shall be tested in accordance with NA7.5.4. Exception 1 to Section 120.5(a)4: Air economizers installed by the HVAC system manufacturer and certified to the Commission as being factory calibrated and tested are not required to comply with the Functional Testing section of the air economizer controls acceptance test as described in NA7.5.4.2. Exception 2 to Section 120.5(a)4: The DOAS, HRV, or ERV unit that does not meet the exhaust air heat recovery ratio as specified in Section 140.4(q)1 or does not include bypass or control to disable energy recovery as specified in Section 140.4(q)2.
Demand control ventilation systems required by Section 120.1(c)3 shall be tested in accordance with NA7.5.5.
Supply fan variable flow controls shall be tested in accordance with NA7.5.6.
Hydronic system variable flow controls shall be tested in accordance with NA7.5.7 and NA7.5.9.
Boiler or chillers that require isolation controls as specified by Section 140.4(k)2 or 140.4(k)3 shall be tested in accordance with NA7.5.7.
Hydronic systems with supply water temperature reset controls shall be tested in accordance with NA7.5.8.
Automatic demand shed controls shall be tested in accordance with NA7.5.10.
Fault Detection and Diagnostics (FDD) for Packaged Direct-Expansion Units shall be tested in accordance with NA7.5.11.
Automatic fault detection and diagnostics (FDD) for air handling units and zone terminal units shall be tested in accordance with NA7.5.12.
Distributed Energy Storage DX AC Systems shall be tested in accordance with NA7.5.13.
Thermal Energy Storage (TES) Systems shall be tested in accordance with NA7.5.14.
Supply air temperature reset controls shall be tested in accordance with NA7.5.15.
Water-cooled chillers served by cooling towers with condenser water reset controls shall be tested in accordance with NA7.5.16.
When an energy management control system is installed, it shall functionally meet all of the applicable requirements of Part 6.
Occupant sensing zone controls shall be tested in accordance with NA7.5.17.
Conductivity controls and overflow alarms for open and closed-circuit cooling towers shall be tested according to NA7.5.18.
§ 7.13. High relevance — show source text
A certificate of acceptance shall be submitted to the enforcement agency that certifies that the equipment and systems meet the acceptance requirements specified in NA 7.13.
(f) Mandatory requirements for elevators. Elevators shall meet the following requirements:
The light power density for the luminaires inside the elevator cab shall be no greater than 0.6 watts per square foot. Exception to Section 120.6(f)1: Interior signal lighting and interior display lighting are not included in the calculation of lighting power density.
Elevator cab ventilation fans for cabs without space conditioning shall not exceed 0.33 watts per cfm as measured at maximum speed.
When the elevator cab is stopped and unoccupied with doors closed for over 15 minutes, the cab interior lighting and ventilation fans shall be switched off until elevator cab operation resumes.
Lighting and ventilation shall remain operational in the event that the elevator cabin gets stuck when passengers are in the cabin.
Elevator Lighting and Ventilation Control Acceptance. Before an occupancy permit is granted for elevators subject to 120.6(f), the following equipment and systems shall be certified as meeting the Acceptance Requirement for Code Compli
88 2025 CALIFORNIA ENERGY CODE
on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.
NONRESIDENTIAL, HOTEL/MOTEL OCCUPANCIES, AND COVERED PROCESSES—MANDATORY REQUIREMENTS
ance, as specified by the Reference Nonresidential Appendix NA7. A Certificate of Acceptance shall be submitted to the enforcement agency that certifies that the equipment and systems meet the acceptance requirements specified in NA7.14.
Exception to Section 120.6(f): Elevators located in healthcare facilities.
(g) Mandatory requirements for escalators and moving walkways .
- Escalators and moving walkways located in airports, hotels, and transportation function areas shall automatically slow to the minimum permitted speed in accordance with ASME A17.1/CSA B44 when not conveying passengers.
- Escalators and Moving Walkways Acceptance. Before an occupancy permit is granted for escalators and moving walkways subject to 120.6(g), the following equipment and systems shall be certified as meeting the Acceptance Requirement for Code Compliance, as specified by the Reference Nonresidential Appendix NA7. A Certificate of Acceptance shall be submitted to the enforcement agency that certifies that the equipment and systems meet the acceptance requirements specified in NA7.15.
(h) Mandatory requirements for controlled environment horticulture (CEH) spaces.
- Indoor growing, dehumidification. Dehumidification equipment shall be one of the following: A. Dehumidifiers subject to regulation under federal appliance standards tested in accordance with 10 CFR 430.23(z) and Appendix X or X1 to Subpart B of 10 CFR Part 430 as applicable, and complying with 10 CFR 430.32(v)2; B. Integrated HVAC system with on-site heat recovery designed to fulfill at least 75 percent of the annual energy for dehumidification reheat;
C. Chilled water system with on-site heat recovery designed to fulfill at least 75 percent of the annual energy for dehumidification reheat; or
D. Solid or liquid desiccant dehumidification system for system designs that require dew point of 50°F or less. 2. Indoor growing, electrical power distribution systems. Electrical power distribution systems serving CEH spaces shall be designed so that a measurement device is capable of monitoring the electrical energy usage of aggregate horticultural lighting load. 3.
§ 160.2 High relevance — show source text
E. Demand control ventilation systems required by Section 160.2(c)3 shall be tested in accordance with NA7.5.5. F. Supply fan variable flow controls shall be tested in accordance with NA7.5.6. G. Hydronic system variable flow controls shall be tested in accordance with NA7.5.7 and NA7.5.9. H. Boilers or chillers that require isolation controls as specified by Section 170.2(c)4Iii or 170.2(c)4Iiii shall be tested in accordance with NA7.5.7.
I. Hydronic systems with supply water temperature reset controls shall be tested in accordance with NA7.5.8.
J. Automatic demand shed controls shall be tested in accordance with NA7.5.10.
K. Fault detection and diagnostics (FDD) for packaged direct expansion units shall be tested in accordance with NA7.5.11. L. Automatic fault detection and diagnostics (FDD) for air handling units and zone terminal units shall be tested in accordance with NA7.5.12.
M. Distributed energy storage DX AC systems shall be tested in accordance with NA7.5.13. N. Thermal energy storage (TES) systems shall be tested in accordance with NA7.5.14. O. Supply air temperature reset controls shall be tested in accordance with NA7.5.15. P. Water-cooled chillers served by cooling towers with condenser water reset controls shall be tested in accordance with NA7.5.16.
Q. When an energy management control system is installed, it shall functionally meet all of the applicable requirements of Part 6.
R. Occupant sensing zone controls shall be tested in accordance with NA7.5.17. 2. Multifamily dwelling units. Before an occupancy permit is granted, the following systems and equipment serving multifamily dwelling units shall be certified as meeting the acceptance requirements for code compliance, as specified by the Reference Nonresidential Appendix NA7. These systems and equipment shall also comply with the applicable requirements of Section 160.3(d)3. A Certificate of Acceptance shall be submitted to the enforcement agency that certifies that the equipment and systems meet the acceptance requirements: A. Multifamily building central ventilation ducts subject to Section 160.2(b)2C shall be leak tested in accordance with NA7.18.3.
B. Multifamily building central ventilation system heat recovery or energy recovery systems in multifamily buildings with four or more habitable stories shall be tested in accordance with NA7.18.4.
- When certification is required by Title 24, Part 1, Section 10-103.2, the acceptance testing specified by Section 160.3(d)1 and 2 shall be performed by a Certified Mechanical Acceptance Test Technician (CMATT). If the CMATT is operating as an employee, the CMATT shall be employed by a Certified Mechanical Acceptance Test Employer. The CMATT shall disclose on the Certificate of Acceptance a valid CMATT certification identification number issued by an approved Acceptance Test Technician Certification Provider. The CMATT shall complete all Certificate of Acceptance documentation in accordance with the applicable requirements in Section 10-103(a)4.
TABLE 160.3-A—RETURN DUCT SIZING FOR SINGLE RETURN DUCT SYSTEMS Col2 Col3 Return duct length shall not exceed 30 feet and shall contain no more than 180 degrees of bend. § 120.6 High relevance — show source text
B. Compressors for transcritical CO 2 refrigeration systems shall be designed to operate at a minimum condensing temperature of 60°F or less. Exception to Section 120.6(a)5B: Compressors with a design saturated suction temperature greater than or equal to 30°F shall be designed to operate at a minimum condensing temperature of 70°F or less. C. New open-drive screw compressors in new refrigeration systems with a design saturated suction temperature (SST) of 28°F or lower that discharges to the system condenser pressure shall control compressor speed in response to the refrigeration load. Exception 1 to Section 120.6(a)5C: Refrigeration plants with more than one dedicated compressor per suction
group. Exception 2 to Section 120.6(a)5C: Compressors and condensers on a refrigeration system for which more than 20 percent of the total design refrigeration cooling load is for quick chilling/ freezing of products [space with design cooling capacities of greater than 240 Btu/hr-ft [2] (2 tons per 100 ft [2] )], or process refrigeration cooling for other than a refrigerated space. D. New screw compressors with nominal electric motor power greater than 150 HP shall include the ability to automatically vary the compressor volume ratio (Vi) in response to operating pressures. 6. Infiltration barriers. Passageways between freezers and higher-temperature spaces, and passageways between coolers and nonrefrigerated spaces, shall have an infiltration barrier consisting of strip curtains, an automaticallyclosing door or an air curtain designed by the manufacturer for use in the passageway and temperature for which it is applied. Exception 1 to Section 120.6(a)6: Openings with less than 16 square feet of opening area. Exception 2 to Section 120.6(a)6: Dock doorways for trailers. 7. Refrigerated warehouse acceptance. Before an occupancy permit is granted for a new refrigerated warehouse, or before a new refrigeration system serving a refrigerated warehouse is operated for normal use, the following equipment and systems shall be certified as meeting the acceptance requirements for code compliance, as specified by the Reference Nonresidential Appendix NA7. A certificate of acceptance shall be submitted to the enforcement agency that certifies that the equipment and systems meet the acceptance requirements: A. Electric resistance underslab heating systems shall be tested in accordance with NA7.10.1. B. Evaporators fan motor controls shall be tested in accordance with NA7.10.2. C. Evaporative condensers shall be tested in accordance with NA7.10.3.1.
D. Air-Cooled condensers shall be tested in accordance with NA7.10.3.2.
E. Adiabatic condensers shall be tested in accordance with NA7.10.3.3.
§ 5.17. High relevance — show source text
R. Occupant sensing zone controls shall be tested in accordance with NA7.5.17. 2. Multifamily dwelling units. Before an occupancy permit is granted, the following systems and equipment serving multifamily dwelling units shall be certified as meeting the acceptance requirements for code compliance, as specified by the Reference Nonresidential Appendix NA7. These systems and equipment shall also comply with the applicable requirements of Section 160.3(d)3. A Certificate of Acceptance shall be submitted to the enforcement agency that certifies that the equipment and systems meet the acceptance requirements: A. Multifamily building central ventilation ducts subject to Section 160.2(b)2C shall be leak tested in accordance with NA7.18.3.
B. Multifamily building central ventilation system heat recovery or energy recovery systems in multifamily buildings with four or more habitable stories shall be tested in accordance with NA7.18.4.
- When certification is required by Title 24, Part 1, Section 10-103.2, the acceptance testing specified by Section 160.3(d)1 and 2 shall be performed by a Certified Mechanical Acceptance Test Technician (CMATT). If the CMATT is operating as an employee, the CMATT shall be employed by a Certified Mechanical Acceptance Test Employer. The CMATT shall disclose on the Certificate of Acceptance a valid CMATT certification identification number issued by an approved Acceptance Test Technician Certification Provider. The CMATT shall complete all Certificate of Acceptance documentation in accordance with the applicable requirements in Section 10-103(a)4.
TABLE 160.3-A—RETURN DUCT SIZING FOR SINGLE RETURN DUCT SYSTEMS Col2 Col3 Return duct length shall not exceed 30 feet and shall contain no more than 180 degrees of bend. If the total bending exceeds 90 degrees, one bend
shall be a metal elbow.
Return grille devices shall be labeled in accordance with the requirements in Section 160.2(b)1Biv to disclose the grille's design airflow rate and a
maximum allowable clean-filter pressure drop of 25 Pa (0.1 inches water) for the air filter when tested using ASHRAE Standard 52.2, or as rated in
accordance with AHRI Standard 680 for the design airflow rate for the return grille.Return duct length shall not exceed 30 feet and shall contain no more than 180 degrees of bend. If the total bending exceeds 90 degrees, one bend
shall be a metal elbow.
Return grille devices shall be labeled in accordance with the requirements in Section 160.2(b)1Biv to disclose the grille's design airflow rate and a
maximum allowable clean-filter pressure drop of 25 Pa (0.1 inches water) for the air filter when tested using ASHRAE Standard 52.2, or as rated in
accordance with AHRI Standard 680 for the design airflow rate for the return grille.Return duct length shall not exceed 30 feet and shall contain no more than 180 degrees of bend. If the total bending exceeds 90 degrees, one bend
shall be a metal elbow.
Return grille devices shall be labeled in accordance with the requirements in Section 160.2(b)1Biv to disclose the grille's design airflow rate and a
maximum allowable clean-filter pressure drop of 25 Pa (0.1 inches water) for the air filter when tested using ASHRAE Standard 52.2, or as rated in
accordance with AHRI Standard 680 for the design airflow rate for the return grille.§ 160.3 High relevance — show source text
(d) Mechanical acceptance testing.
- Common areas. Before an occupancy permit is granted, the following systems and equipment serving multifamily common areas shall be certified as meeting the Acceptance Requirements for Code Compliance, as specified by Reference Nonresidential Appendix NA7. These systems and equipment shall also comply with the applicable requirements of Section
220 2025 CALIFORNIA ENERGY CODE
on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.
MULTIFAMILY BUILDINGS—MANDATORY REQUIREMENTS
160.3(d)3. A Certificate of Acceptance shall be submitted to the enforcement agency that certifies that the equipment and systems meet the acceptance requirements: A. Outdoor air ventilation systems shall be tested in accordance with NA7.5.1. B. Constant volume, single zone air conditioning and heat pump unit controls shall be tested in accordance with NA7.5.2. C. Duct systems shall be tested in accordance with NA7.5.3 where either: a. They are new duct systems; or b. They are part of an altered system. D. Air economizers, DOAS, HRV or ERV systems shall be tested in accordance with NA7.5.4. Exception to Section 160.3(d)1D: Air economizers installed by the HVAC system manufacturer and certified to the Commission as being factory calibrated and tested are not required to comply with the Functional Testing section of the Air Economizer Controls acceptance test as described in NA7.5.4.2. E. Demand control ventilation systems required by Section 160.2(c)3 shall be tested in accordance with NA7.5.5. F. Supply fan variable flow controls shall be tested in accordance with NA7.5.6. G. Hydronic system variable flow controls shall be tested in accordance with NA7.5.7 and NA7.5.9. H. Boilers or chillers that require isolation controls as specified by Section 170.2(c)4Iii or 170.2(c)4Iiii shall be tested in accordance with NA7.5.7.
I. Hydronic systems with supply water temperature reset controls shall be tested in accordance with NA7.5.8.
J. Automatic demand shed controls shall be tested in accordance with NA7.5.10.
K. Fault detection and diagnostics (FDD) for packaged direct expansion units shall be tested in accordance with NA7.5.11. L. Automatic fault detection and diagnostics (FDD) for air handling units and zone terminal units shall be tested in accordance with NA7.5.12.
M. Distributed energy storage DX AC systems shall be tested in accordance with NA7.5.13. N. Thermal energy storage (TES) systems shall be tested in accordance with NA7.5.14. O. Supply air temperature reset controls shall be tested in accordance with NA7.5.15. P. Water-cooled chillers served by cooling towers with condenser water reset controls shall be tested in accordance with NA7.5.16.
Q. When an energy management control system is installed, it shall functionally meet all of the applicable requirements of Part 6.
§ 10-103 High relevance — show source text
- Compliance demonstration requirements for performance standards. A. Certificate of compliance and application for a building permit. The application for a building permit shall include documentation pursuant to Sections 10-103(a)1 and 10-103(a)2 which demonstrates, using an approved calculation method, that the building has been designed so that its energy consumption does not exceed the standard design energy budgets for the applicable climate zone. Exception to Section 150.1(b)2A Multiple orientation: A permit applicant may demonstrate compliance with the energy budget requirements of Section 150.1(a) and (b) for any orientation of the same building model if the documentation demonstrates that the building model with its proposed designs and features would comply in each of the four cardinal orientations.
B. Field verification. When performance of installed features, materials, components, manufactured devices or systems above the minimum specified in Section 150.1(c) is necessary for the building to comply with Section 150.1(b), or is necessary to achieve a more stringent local ordinance, field verification shall be performed in accordance with the applicable requirements in the following subsections, and the results of the verification(s) shall be documented on applicable certificates of installation pursuant to Section 10-103(a)3 and applicable certificates of verification pursuant to Section 10-103(a)5. i. EER2/SEER2/CEER/HSPF2 Rating. When performance compliance requires installation of a space-conditioning system with a rating that is greater than the minimum rating required by Table 150.1-A or specified for the standard design, the installed system shall be field verified in accordance with the procedures specified in the applicable sections of Reference Residential Appendix RA3.4. ii. Variable capacity heat pump (VCHP) compliance option. When performance compliance requires installation of a heat pump system that meets all the requirements of the VCHP compliance option specified in the ACM
2025 CALIFORNIA ENERGY CODE 177
on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.
SINGLE-FAMILY RESIDENTIAL BUILDINGS—PERFORMANCE AND PRESCRIPTIVE COMPLIANCE APPROACHES
Reference Manual, the system shall be field verified in accordance with the procedures in Reference Residential Appendix RA3.4.4.3. iii. Low leakage air handler. When performance compliance requires installation of a low leakage air-handling unit, the installed air-handling unit shall be field verified in accordance with the procedures specified in Reference Residential Appendix RA3.1.4.3.9.
iv. Reserved.
v. Heat pump — rated heating capacity. When performance compliance requires installation of a heat pump system, the heating capacity values at 47°F and 17°F shall be field verified in accordance with the procedures specified in Reference Residential Appendix RA3.4. vi. Whole-house fan. When performance compliance requires installation of a whole-house fan, the whole-house fan ventilation airflow rate and fan efficacy shall be field verified in accordance with the procedures in Reference Residential Appendix RA3.9. vii. Central fan ventilation cooling system. When performance compliance requires installation of a central fan ventilation cooling system, the installed system shall be field verified in accordance with the procedures in Reference Residential Appendix RA3.3.4. viii. Building enclosure air leakage. When performance compliance requires a building enclosure leakage rate that is lower than the standard design, the building enclosure shall be field verified in accordance with the procedures specified in Reference Residential Appendix RA3.8. ix. **Quality Insulation Installation (QII).
§ 170.1 Medium relevance — show source text
A. The Efficiency LSC energy is the sum of the LSC energy for space-conditioning, water heating, mechanical ventilation, lighting and the self-utilization credit. B. The Total LSC energy is the sum of the Efficiency LSC energy and LSC energy from the photovoltaic system, battery energy storage systems (BESS), and demand flexibility. 2. Source energy. The source energy budget is determined by applying the mandatory and prescriptive requirements of the standard design, except with a consumer gas or propane water heater, to the proposed design building.
Exception to Section 170.1(a): A community shared solar electric generation system, or other renewable electric generation system, and/or community shared BESS, that provides dedicated power, utility energy reduction credits or payments for energy bill reductions to the permitted building and is approved by the Energy Commission as specified in Title 24, Part 1, Section 10-115, may offset part or all of the solar electric generation system or BESS LSC energy required to comply with the standards, as calculated according to methods established by the Commission in the Nonresidential ACM Reference Manual.
(b) Compliance demonstration requirements for performance standards.
- Certificate of Compliance and Application for a Building Permit. The application for a building permit shall include documentation pursuant to Sections 10-103(a)1 and 10-103(a)2 that demonstrates, using an approved calculation method, that the building has been designed so that its source energy and LSC energy consumption do not exceed the standard design energy budgets for the applicable climate zone.
- Field verification of individual dwelling unit systems. When performance of installed features, materials, components, manufactured devices or systems above the minimum specified in Section 170.2 is necessary for the building to comply with Section 170.1, or is necessary to achieve a more stringent local ordinance, field verification shall be performed in accordance with the applicable requirements in the following subsections, and the results of the verification(s) shall be documented on applicable Certificates of Installation pursuant to Section 10-103(a)3 and applicable Certificates of Verification pursuant to Section 10-103(a)5. A. EER2/SEER2/CEER/HSPF2 Rating. When performance compliance requires installation of a space-conditioning system with a rating that is greater than the minimum rating required by Table 170.2-K or specified for the standard
2025 CALIFORNIA ENERGY CODE 237
on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.
MULTIFAMILY BUILDINGS—PERFORMANCE AND PRESCRIPTIVE COMPLIANCE APPROACHES
design, the installed system shall be field verified in accordance with the procedures specified in the applicable sections of Reference Residential Appendix RA3. B. Variable capacity heat pump (VCHP) compliance option. When performance compliance requires installation of a heat pump system that meets all the requirements of the VCHP compliance option specified in the ACM Reference Manual, the system shall be field verified in accordance with the procedures in Reference Residential Appendix RA3.4.4.3.
C. Low leakage air handler. When performance compliance requires installation of a low leakage air-handling unit, the installed air handling unit shall be field verified in accordance with the procedures specified in Reference Residential Appendix RA3.1.4.3.9. D. Thermal balancing valve. When performance compliance requires installation of thermal balancing valves with variable speed circulation pump(s), the installation shall meet the procedures specified in Reference Residential Appendix RA4.4.3. E. Heat pump—rated heating capacity.
§ 140.9 Medium relevance — show source text
A certificate of acceptance shall be submitted to the enforcement agency that certifies that the equipment and systems meet the acceptance requirements specified in Nonresidential Appendix NA7.16. 4. Fume Hood Automatic Sash Closure. Variable air volume laboratory fume hoods with vertical only sashes located in fume hood intensive laboratories, as described in Table 140.9-D, shall have an automatic sash closure system that complies with the following: A. The automatic sash closure system shall be capable of the following: i. The automatic sash closure system shall have a dedicated zone presence sensor that detects people in the area near the fume hood sash and automatically closes the sash within 5 minutes of no detection. ii. The automatic sash closure system shall have controls to prevent the sash from automatic closing when a force of no more than 10 lbs is detected.
iii. The automatic sash closure system shall be equipped with an obstruction sensor that prevents the sash from automatic closing with obstructions in the sash opening. Obstruction sensor shall be capable of sensing transparent materials such as laboratory glassware. iv. The automatic sash closure system shall be capable of being configured in a manual open mode where once the sash is closed, detection of people in the area near the fume hood by the zone presence sensor does not open the fume hood sash. B. Fume Hood Automatic Sash Closure Acceptance. Before an occupancy permit is granted for the fume hoods subject to 140.9(c)4, the equipment and systems shall be certified as meeting the Acceptance Requirement for Code Compliance as specified by the Reference Nonresidential Appendix NA7. A Certificate of Acceptance shall be submitted to the enforcement agency that certifies that the equipment and systems meet the acceptance requirements specified in NA7.17.
TABLE 140.9-D—FUME HOOD INTENSIVE LABORATORIES THRESHOLD (both must be true) Col2 Col3 Col4 Col5 Col6 Col7 Occupied minimum ventilation ACH ≤ 4 > 4 and ≤ 6 > 6 and ≤ 8 > 8 and ≤ 10 > 10 and ≤ 12 > 12 and ≤ 14 Hood density (linear feet per 10,000 ft3 of
laboratory space)≥ 6 ≥ 8 ≥ 10 ≥ 12 ≥ 14 ≥ 16 - Reheat limitation. Air handlers in buildings with greater than 20,000 cfm of laboratory exhaust that serve multiple spaceconditioning zones in laboratory spaces shall not mechanically cool air handler supply air below 80°F and shall not heat air
144 2025 CALIFORNIA ENERGY CODE
on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.
NONRESIDENTIAL AND HOTEL/MOTEL OCCUPANCIES—PERFORMANCE AND PRESCRIPTIVE
COMPLIANCE APPROACHES FOR ACHIEVING ENERGY EFFICIENCY
handler supply air above 50°F, and each zone shall include heating and cooling capacity to prevent cooling at the air handler and reheating at the zones. Exception 1 to Section 140.9(c)5: Additions or alterations to existing air-handling systems serving existing zones without heating and cooling capacity. Exception 2 to Section 140.9(c)5: Systems in Climate Zones 7 or 15.
§ 120.6 Medium relevance — show source text
B. Piping section average velocity. Compressor room interconnection and main header piping shall be sized so that at coincident peak flow conditions, the average velocity in the segment of pipe is no greater than 20 ft/sec. Compressor room interconnection and main header piping are the pipes that deliver compressed air from the compressor outlets to the inlet to the distribution piping. Each segment of distribution and service piping shall be sized so that at coincident peak flow conditions, the average velocity in the segment of pipe is no greater than 30 ft/sec. Distribution piping are pipes that deliver compressed air from the compressor room interconnection piping or main header piping to the service line piping. C. Piping total pressure drop. Piping shall be designed such that piping frictional pressure loss at coincident peak loads is less than 5 percent of operating pressure between the compressor and end use or end use regulator. 6. Compressed air system acceptance. Before an occupancy permit is granted for a compressed air system subject to Section 120.6(e), the equipment and systems shall be certified as meeting the acceptance requirements for code compliance, as specified by the Reference Nonresidential Appendix NA7. A certificate of acceptance shall be submitted to the enforcement agency that certifies that the equipment and systems meet the acceptance requirements specified in NA 7.13.
(f) Mandatory requirements for elevators. Elevators shall meet the following requirements:
The light power density for the luminaires inside the elevator cab shall be no greater than 0.6 watts per square foot. Exception to Section 120.6(f)1: Interior signal lighting and interior display lighting are not included in the calculation of lighting power density.
Elevator cab ventilation fans for cabs without space conditioning shall not exceed 0.33 watts per cfm as measured at maximum speed.
When the elevator cab is stopped and unoccupied with doors closed for over 15 minutes, the cab interior lighting and ventilation fans shall be switched off until elevator cab operation resumes.
Lighting and ventilation shall remain operational in the event that the elevator cabin gets stuck when passengers are in the cabin.
Elevator Lighting and Ventilation Control Acceptance. Before an occupancy permit is granted for elevators subject to 120.6(f), the following equipment and systems shall be certified as meeting the Acceptance Requirement for Code Compli
88 2025 CALIFORNIA ENERGY CODE
on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.
NONRESIDENTIAL, HOTEL/MOTEL OCCUPANCIES, AND COVERED PROCESSES—MANDATORY REQUIREMENTS
ance, as specified by the Reference Nonresidential Appendix NA7. A Certificate of Acceptance shall be submitted to the enforcement agency that certifies that the equipment and systems meet the acceptance requirements specified in NA7.14.
Exception to Section 120.6(f): Elevators located in healthcare facilities.
§ 0.69 Medium relevance — show source text
A.| |Metal, thermal break|Fixed|Clear|N.A.|0.69|N.A.| |Metal, thermal break|Operable|Tinted|N.A.|0.53|N.A.| |Metal, thermal break|Fixed|Tinted|N.A.|0.57|N.A.| |Nonmetal|Operable|Clear|0.74|0.65|0.70| |Nonmetal|Fixed|Clear|0.76|0.67|0.67| |Nonmetal|Operable|Tinted|0.60|0.53|N.A.| |Nonmetal|Fixed|Tinted|0.63|0.55|N.A.| |N.A. = Not applicable.
1. Translucent or transparent panels shall use glass block values.|N.A. = Not applicable.
1. Translucent or transparent panels shall use glass block values.|N.A. = Not applicable.
1. Translucent or transparent panels shall use glass block values.|N.A. = Not applicable.
1. Translucent or transparent panels shall use glass block values.|N.A. = Not applicable.
1. Translucent or transparent panels shall use glass block values.|N.A. = Not applicable.
1. Translucent or transparent panels shall use glass block values.|2025 CALIFORNIA GREEN BUILDING STANDARDS CODE APPENDIX A6.1-5
on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.
APPENDIX A6.1 — VOLUNTARY STANDARDS FOR HEALTH FACILITIES [OSHPD 1, 2 & 4]
A6.205.1.1.4 Labeling. Fenestration products shall:
- Have a temporary label (or label certificate for site- built fenestration) meeting the requirements of Section 10111(a)1 of Title 24, Part 1 not to be removed before inspection by the enforcement agency, listing the certified U factor and SHGC and certifying that the air leakage requirements of Section A6.205.1.1.1 are met for each product line; and
- Have a permanent label (or label certificate for site-built fenestration) meeting the requirements of Section 10111(a)2 of Title 24, Part 1 if the product is rated using NFRC procedures.
A6.205.1.1.5 Fenestration acceptance requirements. Before an occupancy permit is granted, site-built fenestration products in other than low-rise residential buildings shall be certified as meeting the Acceptance Requirements for Code Compliance, as specified by the Reference Nonresidential Appendix NA7 of the California Energy Commission 2008 Building Energy Efficiency Standards for Residential and Nonresidential Buildings to ensure that site-built fenestration meet Standards requirements, including a matching label certificate for each product installed and be readily accessible at the project location. A Certificate of Acceptance shall be submitted to the enforcement agency that certifies that the fenestration product meets the acceptance requirements.
Exception: Fenestration products removed and reinstalled as part of a building alteration or addition.
§ 160.5 High relevance — show source text
(e) Lighting control acceptance and installation certificate requirement. Multifamily common use areas shall comply with the applicable requirements of Sections 160.5(e)1 through 160.5(e)3.
- Lighting control acceptance requirements. Before an occupancy permit is granted, indoor and outdoor lighting controls serving the building, area or site and installed to comply with Section 160.5(b)4D, 160.5(b)4C, 160.5(b)4E, 160.5(c)2 or 170.2(e)1Aiij shall be certified as meeting the Acceptance Requirements for Code Compliance as specified by Reference Nonresidential Appendix NA7.6 and NA7.8. A Certificate of Acceptance shall be submitted to the enforcement agency under Section 10-103(a) of Part 1 that the equipment and systems meet the acceptance requirements:
A. Reserved;
B. Reserved; C. Daylight responsive controls shall be tested in accordance with Reference Nonresidential Appendix NA7.6.1; D. Lighting shut-OFF controls shall be tested in accordance with Reference Nonresidential Appendix NA7.6.2; E. Demand responsive lighting controls shall be tested in accordance with Reference Nonresidential Appendix NA7.6.3; and
F. Outdoor lighting controls shall be tested in accordance with Reference Nonresidential Appendix NA7.8; and G. Lighting systems receiving the Institutional Tuning Power Adjustment Factor shall be tested in accordance with Reference Nonresidential Appendix NA7.6.4. H. Demand responsive controls required to control controlled receptacles shall be tested in accordance with Reference Nonresidential Appendix NA7.6.5. 2. Lighting control installation certificate requirements. To be recognized for compliance with Part 6, an Installation Certificate shall be submitted in accordance with Section 10-103(a) for any lighting control system, energy management control system, interlocked lighting system, lighting power adjustment factor, or additional wattage available for a videoconference studio, in accordance with the following requirements, as applicable: A. Certification that when a lighting control system is installed to comply with lighting control requirements in Part 6, it complies with the applicable requirements of Section 110.9 and complies with Reference Nonresidential Appendix NA7.7.1.
B. Certification that when an energy management control system is installed to function as a lighting control required by Part 6, it functionally meets all applicable requirements for each application for which it is installed, in accordance with Sections 110.9, 160, 170 and 180, and complies with Reference Nonresidential Appendix NA7.7.2. C. Certification that interlocked lighting systems used to serve an approved area comply with Section 170.2(e)2A and comply with Reference Nonresidential Appendix NA7.7.4. D. Certification that lighting controls installed to earn a lighting power adjustment factor (PAF) comply with Section 170.2(e)2B and comply with Reference Nonresidential Appendix NA7.7.5.
E. Reserved.
§ 6.4. High relevance — show source text
- Outdoor lighting controls shall be tested in accordance with Reference Nonresidential Appendix NA7.8; and
- Lighting systems receiving the Institutional Tuning Power Adjustment Factor shall be tested in accordance with Reference Nonresidential Appendix NA7.6.4.
- Demand responsive controls required to control controlled receptacles shall be tested in accordance with Reference Nonresidential Appendix NA7.6.5.
(b) Lighting control installation certificate requirements. To be recognized for compliance with Part 6 an installation certificate shall be submitted in accordance with Section 10-103(a) for any lighting control system, energy management control system, interlocked lighting system, lighting power adjustment factor, or additional wattage available for a videoconference studio, in accordance with the following requirements, as applicable:
Certification that when a lighting control system is installed to comply with lighting control requirements in Part 6 it complies with the applicable requirements of Section 110.9; and complies with Reference Nonresidential Appendix NA7.7.1.
Certification that when an energy management control system is installed to function as a lighting control required by Part 6 it functionally meets all applicable requirements for each application for which it is installed, in accordance with Sections 110.9, 130.0 through 130.5, 140.6 through 150.0, and 150.2; and complies with Reference Nonresidential Appendix NA7.7.2.
Reserved.
Reserved.
Certification that interlocked lighting systems used to serve an approved area comply with Section 140.6(a)1; and comply with Reference Nonresidential Appendix NA7.7.4.
Certification that lighting controls installed to earn a lighting power adjustment factor (PAF) comply with Section 140.6(a)2; and comply with Reference Nonresidential Appendix NA7.7.5.
2025 CALIFORNIA ENERGY CODE 101
on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.
NONRESIDENTIAL AND HOTEL/MOTEL OCCUPANCIES—MANDATORY REQUIREMENTS FOR LIGHTING SYSTEMS AND EQUIPMENT, AND ELECTRICAL POWER DISTRIBUTION SYSTEMS
- Certification that additional lighting wattage installed for a videoconference studio complies with Section 140.6(c)2Gvii; and complies with Reference Nonresidential Appendix NA7.7.6.
(c) When certification is required by Title 24, Part 1, Section 10-103.1, the acceptance testing specified by Section 130.4 shall be performed by a certified lighting controls acceptance test technician (CLCATT). If the CLCATT is operating as an employee, the CLCATT shall be employed by a certified lighting controls acceptance test employer. The CLCATT shall disclose on the Certificate of Acceptance a valid CLCATT certification identification number issued by an approved acceptance test technician certification provider. The CLCATT shall complete all certificate of acceptance documentation in accordance with the applicable requirements in Section 10-103(a)4.
Note: Authority cited: Sections 25402, 25402.1 and 25213, Public Resources Code . Reference: Sections 25007, 25008, 25218.5, 25310, 25402, 25402.1, 25402.4, 25402.5, 25402.8, and 25943, Public Resources Code .
SECTION 130.5—ELECTRICAL POWER DISTRIBUTION SYSTEMS
§ 130.3 High relevance — show source text
Exception to Section 130.3(a)2B: Outdoor signs in tunnels and large covered areas that are intended to be illuminated both day and night. 3. Demand responsive Electronic Message Center (EMC) control. See Section 110.12 for requirements for demand responsive EMC controls .
Note: Authority: Sections 25213, 25218, 25218.5, 25402 and 25402.1, Public Resources Code. Reference: Sections 25007, 25008, 25218.5, 25310, 25402, 25402.1, 25402.4, 25402.5, 25402.8, and 25943, Public Resources Code.
SECTION 130.4—LIGHTING CONTROL ACCEPTANCE AND INSTALLATION CERTIFICATE REQUIREMENTS
Nonresidential buildings other than healthcare facilities and hotel/motel buildings shall comply with the applicable requirements of Sections 130.4(a) through 130.4(c). Healthcare facilities shall comply with the applicable acceptance and installation documentation requirements of OSHPD.
(a) Lighting and receptacle control acceptance requirements. Before an occupancy permit is granted, indoor and outdoor lighting and receptacle controls serving the building, area or site and installed to comply with Section 110.12, 120.6(h)5B, 130.1, 130.2, 130.5 or 140.6 shall be certified as meeting the Acceptance Requirements for Code Compliance as specified by the Reference Nonresidential Appendix NA7.6 and NA7.8. A Certificate of Acceptance shall be submitted to the enforcement agency under Section 10-103(a) of Part 1, that the equipment and systems meet the acceptance requirements:
Reserved.
Reserved.
Daylight responsive controls shall be tested in accordance with Reference Nonresidential Appendix NA7.6.1;
Lighting shut-OFF controls shall be tested in accordance with Reference Nonresidential Appendix NA7.6.2;
Demand responsive lighting controls shall be tested in accordance with Reference Nonresidential Appendix NA7.6.3; and
Outdoor lighting controls shall be tested in accordance with Reference Nonresidential Appendix NA7.8; and
Lighting systems receiving the Institutional Tuning Power Adjustment Factor shall be tested in accordance with Reference Nonresidential Appendix NA7.6.4.
Demand responsive controls required to control controlled receptacles shall be tested in accordance with Reference Nonresidential Appendix NA7.6.5.
(b) Lighting control installation certificate requirements. To be recognized for compliance with Part 6 an installation certificate shall be submitted in accordance with Section 10-103(a) for any lighting control system, energy management control system, interlocked lighting system, lighting power adjustment factor, or additional wattage available for a videoconference studio, in accordance with the following requirements, as applicable:
Certification that when a lighting control system is installed to comply with lighting control requirements in Part 6 it complies with the applicable requirements of Section 110.9; and complies with Reference Nonresidential Appendix NA7.7.1.
Certification that when an energy management control system is installed to function as a lighting control required by Part 6 it functionally meets all applicable requirements for each application for which it is installed, in accordance with Sections 110.9, 130.0 through 130.5, 140.6 through 150.0, and 150.2; and complies with Reference Nonresidential Appendix NA7.7.2.
Reserved.
Reserved.
§ 6.4. High relevance — show source text
F. Outdoor lighting controls shall be tested in accordance with Reference Nonresidential Appendix NA7.8; and G. Lighting systems receiving the Institutional Tuning Power Adjustment Factor shall be tested in accordance with Reference Nonresidential Appendix NA7.6.4. H. Demand responsive controls required to control controlled receptacles shall be tested in accordance with Reference Nonresidential Appendix NA7.6.5. 2. Lighting control installation certificate requirements. To be recognized for compliance with Part 6, an Installation Certificate shall be submitted in accordance with Section 10-103(a) for any lighting control system, energy management control system, interlocked lighting system, lighting power adjustment factor, or additional wattage available for a videoconference studio, in accordance with the following requirements, as applicable: A. Certification that when a lighting control system is installed to comply with lighting control requirements in Part 6, it complies with the applicable requirements of Section 110.9 and complies with Reference Nonresidential Appendix NA7.7.1.
B. Certification that when an energy management control system is installed to function as a lighting control required by Part 6, it functionally meets all applicable requirements for each application for which it is installed, in accordance with Sections 110.9, 160, 170 and 180, and complies with Reference Nonresidential Appendix NA7.7.2. C. Certification that interlocked lighting systems used to serve an approved area comply with Section 170.2(e)2A and comply with Reference Nonresidential Appendix NA7.7.4. D. Certification that lighting controls installed to earn a lighting power adjustment factor (PAF) comply with Section 170.2(e)2B and comply with Reference Nonresidential Appendix NA7.7.5.
E. Reserved.
- When certification is required by Title 24, Part 1, Section 10-103.1, the acceptance testing specified by Section 160.5(e) shall be performed by a Certified Lighting Controls Acceptance Test Technician (CLCATT). If the CLCATT is operating as an employee, the CLCATT shall be employed by a Certified Lighting Controls Acceptance Test Employer. The CLCATT shall disclose on the Certificate of Acceptance a valid CLCATT certification identification number issued by an approved Acceptance Test Technician Certification Provider. The CLCATT shall complete all Certificate of Acceptance documentation in accordance with the applicable requirements in Section 10-103(a)4.
NOTE: Authority: Sections 25213, 25218, 25218.5, 25402 and 25402.1, Public Resources Code . Reference: Sections 25007, 25008, 25218.5, 25310, 25402, 25402.1, 25402.4, 25402.5, 25402.8 and 25943, Public Resources Code .
SECTION 160.6—MANDATORY REQUIREMENTS FOR ELECTRIC POWER DISTRIBUTION SYSTEMS
Multifamily buildings shall comply with the applicable requirements of Sections 160.6(a) through 160.6(e).
(a) Service electrical metering. Each electrical service or feeder that provides power to the common use areas (interior and exterior) shall have a permanently installed metering system that measures electrical energy use in accordance with Table 160.6-A.
Exception to Section 160.6(a): Service or feeder for which the utility company provides a metering system for the multifamily building that indicates instantaneous kW demand and kWh for a utility-defined period.
232 2025 CALIFORNIA ENERGY CODE
§ 110.2 High relevance — show source text
B Ceiling-Mounted Air Conditioners and Condensing Units Serving Computer Rooms–Minimum Efficiency Requirements Table 110.2-M Cellular Foam Insulation 120.4(F), 150.0(M)9,160.3(b)5I, 160.3(c)2G Cement-Based Roof Coatings 110.8(i)4 Central Boiler 140.4(a), 170.2(c)3A Chiller 140.4(a)2 Forced-air 150.0(h)4, 150.0(m)13, 150.0(o), 150.1(c)10, 160.2(b)2A, 160.3(b)4, 160.3(b)5, 170.2(c)3B Furnace 110.5, 110.5(a) Water heating system 110.10(c), 150.1(c)8, 170.2(d)3 Centrifugal Fan Table 110.2-F, 140.4(h), 170.2(C)4F Centrifugal Water Chilling 110.2(a) Certificate of Acceptance 10-103(a)4, 10-103(b)1B, 10-103.1(c)3, 110.6(a)6, 120.5(a), 120.5(b), 120.6(a)7, 120.6(b)6, 120.6(c)8, 120.6(e)6, 120.6(f), 120.6(g), 120.6(i), 130.4(a), 130.4(c),
2025 CALIFORNIA ENERGY CODE 301
on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.
INDEX
140.9(b)3, 140.9(c), 160.3(d)1, 160.3(d)2, 160.3(d)3, 160.5(e)1, 3 Compliance 10-103(a), 120.8(d), 150.1(b)3, 170.1(d) Installation 10-103(a)3, 150.1(b)3, 150.1(c)7, 150.2(b)1F Verification 10-103(a)5, 150.1(b)3 Certification 110.0(B), 110.2, 110.3(A), 110.4(a), 110.6(a), 110.8(a), 110.8(g), 110.9(c), 110,11, 120.5(b), 130.4(b), 130.4(c), 140.9(a)4, 150.0(n)3, 160.3(d)3, 160.4(c), 160.5(e) Certification Identification Number 10-103(C)3G, 120.5(B), 130.4(c), 160.3(d)3, 160.5(e) Certification Requirements 110.0(B), 110.6(a)1, 110.8(g)1 Certified 110.6(a)6, 110.8(i)1, 120.5(a) Equipment 110.4(a)1, 150.0(h), 150.0(p)1A Lighting Controls Acceptance Test Employer 130.4(c), 160.
§ 140.9 High relevance — show source text
INDEX
140.9(b)3, 140.9(c), 160.3(d)1, 160.3(d)2, 160.3(d)3, 160.5(e)1, 3 Compliance 10-103(a), 120.8(d), 150.1(b)3, 170.1(d) Installation 10-103(a)3, 150.1(b)3, 150.1(c)7, 150.2(b)1F Verification 10-103(a)5, 150.1(b)3 Certification 110.0(B), 110.2, 110.3(A), 110.4(a), 110.6(a), 110.8(a), 110.8(g), 110.9(c), 110,11, 120.5(b), 130.4(b), 130.4(c), 140.9(a)4, 150.0(n)3, 160.3(d)3, 160.4(c), 160.5(e) Certification Identification Number 10-103(C)3G, 120.5(B), 130.4(c), 160.3(d)3, 160.5(e) Certification Requirements 110.0(B), 110.6(a)1, 110.8(g)1 Certified 110.6(a)6, 110.8(i)1, 120.5(a) Equipment 110.4(a)1, 150.0(h), 150.0(p)1A Lighting Controls Acceptance Test Employer 130.4(c), 160.5(e) Mechanical Acceptance Test Employer 120.5(b), 160.3(d)3 Mechanical Acceptance Test Technician (CMATT) 120.5(b), 160.3(d)3 CFA and Dwelling Unit Adjustment Factors Table 150.1-C, Table 170.2-T CFM Per Square Foot 110.6(A)1, 120.1(D)3, 120.6(c)5, 140.3(a)9, 140.4(e)1, 141.0(b)2Q, 150.1(c)12A, Table 160.2-B, Table 160.2-C, 170.2(c)4N CFM Per Ton 150.0(M)13, 150.1(C)7, 150.2(B)1F, 160.3(b)5L, 170.2(c)3B, 180.2(b)2A Chalk Board 140.6(b)4 Chilled Water piping 120.3(b)2, 160.3(c)1C, 160.4(f)2B Water plant Table 120.2-A, 140.4(h)5, 140.4(j), Table 160.3-C, 170.2(c)4F Water system 120.6(h), 140.4(k)2, 140.4(m), 170.2(c)4C, I, K Water system cooling capacity Table 140.4-E, Table 170.2-E-2 Chiller 10-103(c)3B, 110.2(a), Table 120.2-A, 120.5(a)8, 16, 120.6(b)2A, Table 130.5-B, 140.
§ 62.2 Medium relevance — show source text
[ASHRAE 62.2: Table B1] Table 150.0-D, Table 160.2-A Infiltration Rate 110.6(a)1, 150.0(o)1C Initial Solar Reflectance 110.8(i)2 Initial Wattage Allowance (IWA) 140.7(d)1C, Table 140.7-A, 170.2(e)6D, Table 170.2-B Inlet-to-Outlet 150.0(h)4, 160.3(b)4 Input Capacity per stack 120.9(a)2, 160.4(e)1B Power 120.6(a)4G, 120.6(b)5H, 120.10(a), 140.4(c)1, Table 140.4-A, 140.4(p)1, 140.8(b)2, Table 160.5-B, 170.2(c)4A, Table 170.2-B, 170.2(e)7B Rating 110.2(d), Table 110.2-I 110.3(c)6, 120.6(i), 150.0(n)4, 160.4(d) Wattage 130.0(c)3-7, 140.8(b)3, 160.5(b)1C-G, 170.2(e)7B Installation 10-103(a)2B, 10-103(a)4, 10103(a)5A, 10-103(d)2, 10-103.1(b)2, 10103.2(b)2, 100.0(e)4, 110.0, 110.3(c)4A, 110.4(b), 110.6(b), 110.8(b), 110.8(d), 120.0, 120.6(i)3, 120.8, 130.0(a-b), 130.0(e), Table 130.5-B, Table 140.6-A, 140.9(c)3B, 141.0(b)2E, 150.0(e), 150.0(h)4, 150.0(m)11B, 150.0(m)12B, 150.0(n)1, 150.0(s-v), 150.1(b)3B, Table 150.1-A, 150.2(b)1E-F, 150.2(b)1J, 160.1(f), 160.3(b)4, 160.5, 160.9, Table 170.2-A, 180.2(b)2A, 180.2(b)2B Installation Certificate 110.10(e)2, 10103(a)3, 10-103(a)5A, 10-103(b)1, 10103(d)A-B, 10-103.1(c)3H-I, 10-103.2(c)3H-I, 100.0(h), 130.4, 140.6(a)1A, 140.6(a)2A, 140.6(c)2G, 150.1(b)3B, 150.1(c)7A, 160.5(e), 170.1(d)2, 170.2(e)2 Installation Criteria 10-115(a)4B, 110.2(e), 110.3(c), 110.8(g),
§ 140.3 Medium relevance — show source text
A
Above Grade Wall 140.3(a)9, 150.0(c), 160.1(b) Accent Luminaire 140.6(c)3G, 170.2(e)4 Accent, Display and Feature 140.6(b)4 Acceptance Requirements 10-103(a), 100.1(b), 110.6(a)6, 120.5(a), 120.6(a)7, 120.6(b)6, 120.6(c)8, 120.6(e)8, 120.6(f)5, 120.6(g)2, 120.6(i)4, 130.4(a), 140.9(b)3, 140.9(c)3-4, 160.3(d)1-2, 160.5(e)1 Acceptance Test Technician Certification Provider 10-103(a)4B, 10103.1(a), 10-109(i)B, 120.5(b), 130.4(c), 160.3(d)3, 160.5(e)3 Acceptance Testing 10-103(a)4, 10-103.1(a-b), 10-103.1(c)3, 10-103(e), 10-103.2(a-b), 120.5(b), 130.4(c), 141.0(b)2I, 141.0(b)2L, 160.3(d)3, 160.5(e)3, 180.2(4)B2 Actual Outdoor Lighting Power 140.7(a), 170.2(e)6 Addition Or Alteration 120.6(b)1–4, 140.9(b)1–2, 150.2(c), 180.4 Additional Credit 141.0(b)3C, 150.2(b)2, 180.2(c)2 Additional Fan Power Allowances 141.0(b)2C, Table 141.0-D Additional Multifamily Lighting Power Allowance for Specific Applications Table 170.2-S Additions 10-103(a)1C, 2A, 3D, 10-103(d)2, 10-106(a), 100.0(e)3, Table 100.0-A, Table 110.2-E, 120.0, Table 120.2-A, 120.6(c), 120.6(e), 130.0(a-b), 140.0, 140.6(a), 140.7(a), 141.0, 141.0(a), 141.1, 141.1(b–c), 150.0,150.1(a–b), 150.2, 150.2(a, c), 160.0, Table 160.3-C, 160.5(b), 170.0(a), 170.2(e)6A, 180.0, 180.1(a–b), 180.4 Adiabatic Gas Cooler 120.6(a)8, 120.6(b)5 Adjusted Indoor Lighting Power 140.6, 140.6(a)2 Adjustment Credits 180.2(b) Adjustment Factor 130.4(a, b, d), 140.6(a)2, 4, 140.6(c)3G, H, Table 140.6-A,
§ 10-109 Medium relevance — show source text
(b) Performance approach. A building complies with the performance approach if the energy consumption calculated for the proposed design building is no greater than the energy budget calculated for the standard design building using Commission-certified compliance software as specified by Sections 10-109(c) and 10-116.
- Energy budget. The energy budget is expressed in terms of source energy and long-term system cost (LSC). A. Long-term system cost (LSC). The LSC energy budget is determined by applying the mandatory and prescriptive requirements of the standard design to the proposed design building and has two components, the Efficiency LSC and the Total LSC.
i. The Efficiency LSC energy is the sum of the LSC energy for space-conditioning, water heating, mechanical ventilation, and the self-utilization credit.
ii. The Total LSC energy is the sum of the Efficiency LSC energy and LSC energy from the photovoltaic system, battery energy storage systems (BESS), lighting, demand flexibility, and other plug loads. B. Source energy. The source energy budget is determined by applying the mandatory and prescriptive requirements of the standard design to the proposed design building. The source energy is the total annual source energy. Exception to Section 150.1(b)1. A community shared solar electric generation system, or other renewable electric generation system, or community shared BESS, which provides dedicated power, utility energy reduction credits, or payments for energy bill reductions to the permitted building and is approved by the Energy Commission as specified in Title 24, Part 1, Section 10-115, may offset part or all of the solar electric generation system and demand flexibility Energy Design Rating required to comply with the Standards, as calculated according to methods established by the Commission in the Residential ACM Reference Manual.
- Compliance demonstration requirements for performance standards. A. Certificate of compliance and application for a building permit. The application for a building permit shall include documentation pursuant to Sections 10-103(a)1 and 10-103(a)2 which demonstrates, using an approved calculation method, that the building has been designed so that its energy consumption does not exceed the standard design energy budgets for the applicable climate zone. Exception to Section 150.1(b)2A Multiple orientation: A permit applicant may demonstrate compliance with the energy budget requirements of Section 150.1(a) and (b) for any orientation of the same building model if the documentation demonstrates that the building model with its proposed designs and features would comply in each of the four cardinal orientations.
B. Field verification. When performance of installed features, materials, components, manufactured devices or systems above the minimum specified in Section 150.1(c) is necessary for the building to comply with Section 150.1(b), or is necessary to achieve a more stringent local ordinance, field verification shall be performed in accordance with the applicable requirements in the following subsections, and the results of the verification(s) shall be documented on applicable certificates of installation pursuant to Section 10-103(a)3 and applicable certificates of verification pursuant to Section 10-103(a)5. i. EER2/SEER2/CEER/HSPF2 Rating. When performance compliance requires installation of a space-conditioning system with a rating that is greater than the minimum rating required by Table 150.1-A or specified for the standard design, the installed system shall be field verified in accordance with the procedures specified in the applicable sections of Reference Residential Appendix RA3.4. ii. **Variable capacity heat pump (VCHP) compliance option.
§ 120.6 Medium relevance — show source text
D. New screw compressors with nominal electric motor power greater than 150 HP shall include the ability to automatically vary the compressor volume ratio (Vi) in response to operating pressures. 6. Infiltration barriers. Passageways between freezers and higher-temperature spaces, and passageways between coolers and nonrefrigerated spaces, shall have an infiltration barrier consisting of strip curtains, an automaticallyclosing door or an air curtain designed by the manufacturer for use in the passageway and temperature for which it is applied. Exception 1 to Section 120.6(a)6: Openings with less than 16 square feet of opening area. Exception 2 to Section 120.6(a)6: Dock doorways for trailers. 7. Refrigerated warehouse acceptance. Before an occupancy permit is granted for a new refrigerated warehouse, or before a new refrigeration system serving a refrigerated warehouse is operated for normal use, the following equipment and systems shall be certified as meeting the acceptance requirements for code compliance, as specified by the Reference Nonresidential Appendix NA7. A certificate of acceptance shall be submitted to the enforcement agency that certifies that the equipment and systems meet the acceptance requirements: A. Electric resistance underslab heating systems shall be tested in accordance with NA7.10.1. B. Evaporators fan motor controls shall be tested in accordance with NA7.10.2. C. Evaporative condensers shall be tested in accordance with NA7.10.3.1.
D. Air-Cooled condensers shall be tested in accordance with NA7.10.3.2.
E. Adiabatic condensers shall be tested in accordance with NA7.10.3.3.
F. Variable speed compressors shall be tested in accordance with NA7.10.4. G. Transcritical CO 2 refrigeration systems shall be tested in accordance with NA7.20.1. 8. Transcritical CO 2 gas coolers. New fan-powered gas coolers on all new transcritical CO 2 refrigeration systems shall conform to the following: A. Air-cooled gas coolers are prohibited in Climate Zones 9 through 15. B. Design leaving gas temperature for air-cooled gas coolers shall be less than or equal to the design dry-bulb temperature plus 6°F. Exception to Section 120.6(a)8B: Design leaving gas temperature for air-cooled gas coolers in Climate Zones 2, 4 and 8 shall be less than or equal to the design dry-bulb temperature plus 8°F.
2025 CALIFORNIA ENERGY CODE 83
on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.
NONRESIDENTIAL, HOTEL/MOTEL OCCUPANCIES, AND COVERED PROCESSES—MANDATORY REQUIREMENTS
C. Design leaving gas temperature for adiabatic gas coolers necessary to reject the design total heat of rejection of a refrigeration system assuming dry mode performance shall be less than or equal to the design dry-bulb temperature plus 15°F. D. All gas cooler fans shall be continuously variable speed, with the speed of all fans serving a common condenser high side controlled in unison.
E. While operating below the critical point, the gas cooler pressure shall be controlled in accordance with Section 120.6(a)4F.
§ 5.3 Medium relevance — show source text
(g) Duct sealing. Duct systems shall comply with Subsection 1 or 2 below:
- New duct systems that meet the criteria in Subsections A, B, C and D below shall be sealed to a leakage rate not to exceed 6 percent of the nominal air handler airflow rate as confirmed through acceptance testing, in accordance with Reference Nonresidential Appendix NA7.5.3; A. The duct system does not serve a healthcare facility; and B. The duct system provides conditioned air to an occupiable space for a constant volume, single zone, space-conditioning system; and C. The space-conditioning system serves less than 5,000 square feet of conditioned floor area; and D. The combined surface area of the ducts located outdoors or in unconditioned space is more than 25 percent of the total surface area of the entire duct system.
- New duct systems that are not subject to testing under Section 120.4(g)1 shall instead meet the duct leakage testing requirements of CMC Section 603.9.2.
Note: Authority: Sections 25213, 25218, 25218.5, 25402 and 25402.1, Public Resources Code. Reference: Sections 25007, 25008, 25218.5, 25310, 25402, 25402.1, 25402.4, 25402.8, and 25943, Public Resources Code.
SECTION 120.5—REQUIRED NONRESIDENTIAL MECHANICAL SYSTEM ACCEPTANCE
Nonresidential and hotel/motel buildings shall comply with the applicable requirements of Sections 120.5(a) through 120.5(b).
Exception to Section 120.5: Systems serving healthcare facilities.
(a) Before an occupancy permit is granted, the following equipment and systems shall be certified as meeting the Acceptance Requirements for Code Compliance, as specified by the Reference Nonresidential Appendix NA7. A Certificate of Acceptance shall be submitted to the enforcement agency that certifies that the equipment and systems meet the acceptance requirements:
Outdoor air ventilation systems shall be tested in accordance with NA7.5.1.
Constant volume, single zone unitary air conditioning and heat pump unit controls shall be tested in accordance with NA7.5.2.
Duct systems that are subject to testing under Section 120.4(g)1, Section 141.0(b)2Di or Section 141.0(b)2Dii shall be tested in accordance with NA7.5.3.
Air economizers, DOAS, HRV or ERV systems shall be tested in accordance with NA7.5.4. Exception 1 to Section 120.5(a)4: Air economizers installed by the HVAC system manufacturer and certified to the Commission as being factory calibrated and tested are not required to comply with the Functional Testing section of the air economizer controls acceptance test as described in NA7.5.4.2. Exception 2 to Section 120.5(a)4: The DOAS, HRV, or ERV unit that does not meet the exhaust air heat recovery ratio as specified in Section 140.4(q)1 or does not include bypass or control to disable energy recovery as specified in Section 140.4(q)2.
Demand control ventilation systems required by Section 120.1(c)3 shall be tested in accordance with NA7.5.5.
Supply fan variable flow controls shall be tested in accordance with NA7.5.6.
§ 0.15 Medium relevance — show source text
(c) Mandatory requirements for enclosed parking garages.
Mechanical ventilation systems for enclosed parking garages where the total design exhaust rate for the garage is greater than or equal to 10,000 cfm shall conform to all of the following:
Automatically detect contaminant levels and stage fans or modulate fan airflow rates to 50 percent or less of design capacity, provided acceptable contaminant levels are maintained.
Have controls and/or devices that will result in fan motor demand of no more than 30 percent of design wattage at 50 percent of design airflow.
CO shall be monitored with at least one sensor per 5,000 square feet, with the sensor located in the highest expected concentration locations, with at least two sensors per proximity zone. A proximity zone is defined as an area that is isolated from other areas either by floor or other impenetrable obstruction.
CO concentration at all sensors is maintained at ≤ 25 ppm or less at all times.
The ventilation rate shall be at least 0.15 cfm/ft [2] when the garage is scheduled to be occupied.
The system shall maintain the garage at negative or neutral pressure relative to other occupiable spaces when the garage is scheduled to be occupied.
CO sensors shall be:
A. Certified by the manufacturer to be accurate within plus or minus 5 percent of measurement. B. Factory calibrated. C. Certified by the manufacturer to drift no more than 5 percent per year. D. Certified by the manufacturer to require calibration no more frequently than once a year.
86 2025 CALIFORNIA ENERGY CODE
on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.
NONRESIDENTIAL, HOTEL/MOTEL OCCUPANCIES, AND COVERED PROCESSES—MANDATORY REQUIREMENTS
E. Monitored by a control system. The system shall have logic that automatically checks for sensor failure by the following means. Upon detection of a failure, the system shall reset to design ventilation rates and transmit an alarm to the facility operators. i. If any sensor has not been calibrated according to the manufacturer’s recommendations within the specified calibration period, the sensor has failed. ii. During unoccupied periods the system compares the readings of all sensors, e.g., if any sensor is more than 15 ppm above or below the average of all sensors for longer than four hours, the sensor has failed. iii. During occupied periods the system compares the readings of sensors in the same proximity zone, e.g., if the 30 minute rolling average for any sensor in a proximity zone is more than 15 ppm above or below the 30 minute rolling average for other sensor(s) in that proximity zone, the sensor has failed. 8. Parking garage ventilation system acceptance. Before an occupancy permit is granted for a parking garage system subject to Section 120.6(c), the following equipment and systems shall be certified as meeting the acceptance requirements for code compliance, as specified by the Reference Nonresidential Appendix NA7. A certificate of acceptance shall be submitted to the enforcement agency that certifies that the equipment and systems meet the acceptance requirements specified in NA7.12.
Exception 1 to Section 120.6(c): Any garage, or portion of a garage, where more than 20 percent of the vehicles expected to be stored have nongasoline combustion engines.
Exception 2 to Section 120.6(c): Additions and alterations to existing garages where less than 10,000 cfm of new exhaust capacity is being added.
§ 110.6 Medium relevance — show source text
Exception 1 to Section 110.6(a)2: If the fenestration product is a skylight in a building covered by the nonresidential standards with less than 200 square feet of skylight area, the default U -factor may be calculated as set forth in Reference Nonresidential Appendix NA6.
Exception 2 to Section 110.6(a)2: If the fenestration product is an alteration consisting of any area replacement of glass in a skylight product in a building covered by the nonresidential standards, the default U -factor may be calculated as set forth in Reference Nonresidential Appendix NA6. 3. Solar heat gain coefficient SHGC. The fenestration product’s SHGC shall be rated in accordance with NFRC 200, or use the applicable default SHGC set forth in Table 110.6-B.
Exception 1 to Section 110.6(a)3: If the fenestration product is a skylight in a building covered by the nonresidential standards with less than 200 square feet of skylight area, the default SHGC may be calculated as set forth in Reference Nonresidential Appendix NA6.
Exception 2 to Section 110.6(a)3: If the fenestration product is an alteration consisting of any area replacement of glass in a skylight product in a building covered by the nonresidential standards, the default SHGC may be calculated as set forth in Reference Nonresidential Appendix NA6. 4. Visible transmittance (VT). The fenestration product’s VT shall be rated in accordance with NFRC 200 or ASTM E972. For tubular daylighting devices VT shall be rated using NFRC 203.
Exception 1 to Section 110.6(a)4: If the fenestration product is a skylight in a building covered by the nonresidential standards with less than 200 square feet of skylight area, the default VT may be calculated as set forth in Reference Nonresidential Appendix NA6.
Exception 2 to Section 110.6(a)4: If the fenestration product is an alteration consisting of any area; replacement of glass in a skylight product in a building covered by the nonresidential standards, the default VT may be calculated as set forth in Reference Nonresidential Appendix NA6. 5. Labeling. Fenestration products and exterior doors shall: A. Have a temporary label for manufactured fenestration products and exterior doors or a label certificate when the component modeling approach (CMA) is used and for site-built fenestration meeting the requirements of Section 10-111(a)1. The temporary label shall not be removed before inspection by the enforcement agency; and B. Have a permanent label or label certificate when the component modeling approach (CMA) is used and for sitebuilt fenestration meeting the requirements of Section 10-111(a)2 if the product is rated using NFRC procedures. 6. Fenestration acceptance requirements. Before an occupancy permit is granted site-built fenestration products in other than single-family buildings shall be certified as meeting the Acceptance Requirements for Code Compliance, as specified in the Reference Nonresidential Appendix NA7 to ensure that site-built fenestration meets Standards requirements, including a matching label certificate for product(s) installed and be readily accessible at the project location. A certificate of accep
2025 CALIFORNIA ENERGY CODE 55
on Jul 18, 2025 11:14 AM (CDT) THEREUNDER.
§ 207.1.1 Medium relevance — show source text
**
A6.207.1.1 Efficiency.
A6.207.1.2 Controls for heat pumps with supplementary electric resistance heaters.
A6.207.1.3 Thermostats.
A6.207.1.4 Gas-and oil-fired furnace standby loss controls.||
|
|| |A6.207.2 Space conditioning systems.
A6.207.2.1 Supply air temperature reset controls.
A6.207.2.2 Electric resistance heating.
A6.207.2.3 Heat rejection systems.
A6.207.2.4 Hydronic system measures.
A6.207.2.5 Air distribution system duct leakage sealing.
A6.207.2.6 Variable air volume control for single zone systems.||
|
|| |A6.207.3 Service water-heating systems and equipment.
A6.207.3.1 Certification by manufacturers.
A6.207.3.2 Efficiency.
A6.207.3.3 Installation.||
|
|| |A6.207.4 Natural gas central furnaces, cooking equipment and pool and spa heaters.
Pilot lights prohibited.||||| |A6.207.5 Controls for space-conditioning systems.
A6.207.5.1 Thermostatic controls for each zone.
A6.207.5.2 Criteria for zonal thermostatic controls.
A6.207.5.3 Heat pump controls.
A6.207.5.4 Dampers for air supply and exhaust equipment.
A6.207.5.5 Automatic demand shed controls.||
|
|| |A6.207.6 Pipe insulation.||||| |SECTION A6.209 Lighting||||| |A6.209.1 Lighting control devices, ballasts and luminaires.
A6.209.1.1 All devices: Instructions and calibration.
A6.209.1.2 Indicator lights.
**A6.209.1.3 Automatic time switch control devices.§ 1220.4.2 Medium relevance — show source text
8|1220.4.2 – 1220.4.6| |1221.7|1221.6| |1308.2 – 1308.4.1|1308.3 – 1308.5.1| |Table 1308.3.1|Table 1308.4.1| |1308.4.2|1308.5.2| |1308.4.2.2 – 1308.6.4|1308.5.2.1 – 1308.7.3| |Table 1308.4.6.2|Table 1308.5.6.2| |1308.6.5 – 1308.13.1|1308.7.7 – 1308.14.1| |1312.1.2 – 1312.1.3|1312.1.1 – 1312.1.2| |Chapter 17|Appendix F| |Chapter 18|Chapter 17| |D 103.2|D 103.1| |E 503.5.6.7|E 503.5.6.6| |E 503.5.7.2 – E 503.5.7.6|E 503.5.7.1 – E 503.5.7.5| |Table E 503.5.7.2|Table E 503.5.7.1| |Table E 503.5.7.6|Table E 503.5.7.5| |Table E 503.5.10.1.2(1)|Table E 503.5.10(1)| |Table E 503.5.10.1.2(2)|Table E 503.5.10(2)| |E 503.5.10.1.2|E 503.5.10| |E 503.5.10.2 – E 503.5.10.2.2|E 503.5.10.1 – E 503.5.10.1.2| |E 503.5.12.1|E 503.5.12| |E 503.5.12.2|E 503.5.12.1| |E 503.6.5.4|E 503.6.5.4.1|
xxii 2025 CALIFORNIA MECHANICAL CODE
), Copyright © 2025 IAPMO, and may not be used for any other purpose or distributed to any other persons or parties.
RELATED PUBLICATIONS AND SERVICES
The Documents Listed are Not by this Reference Adopted by The State of California.
IAPMO provides a variety of other products which are useful for inspectors, building officials, architects, engineers,
manufacturers, contractors, plumbers, and apprentices.
IAPMO Headquarters Directory
4755 East Philadelphia Street, Ontario, California 91761-2816
Publication Order Desk Phone: 800-85-IAPMO
Publication Toll Free Fax: 877-85-CODES
E-mail: iapmo@iapmo.org
Website: www.iapmo.org
Free Code Question: 800-201-0335
Uniform Mechanical Code – 2024 Edition:
The Uniform Mechanical Code contains complete requirements for the installation and maintenance of heating, ventilating, cooking and refrigeration systems.
Uniform Mechanical Code Illustrated Training Manual:
Frequently asked questions
Who signs a Certificate of Acceptance?
The field tester(s) performing the acceptance tests sign and the responsible person (installer, contractor, or responsible certifier) also signs to certify the information is true and correct. Where Part 1 requires a certified tester, that tester must include their certification ID on the certificate.
When must certificates be submitted?
Certificates required by § 10-103(a) must be submitted to the enforcement agency before the final occupancy permit is granted.
Do I need a Certificate if equipment was factory‑tested?
Some factory‑calibrated/manufacturer‑certified equipment (example: some air economizers) may be exempt from parts of the field functional tests; the Code lists those exceptions. Even then, the presence of a qualifying manufacturer certification must be documented per the referenced section.
What if I don’t have the NA7.7.1 / NA7.7.2 checklist?
The Code requires Installation Certificates to “comply with” NA7.7.1 and NA7.7.2; the main-code excerpts reference those appendices. The full NA7 checklist text (line‑item fields to fill) is in the Nonresidential Appendix NA7 — that appendix text was not found in the uploaded files I searched. If you want, I can fetch the NA7.7.1/NA7.7.2 text and produce a completion-ready checklist.
Are different certificates required for multifamily buildings?
Yes — multifamily common areas and systems are covered by dedicated acceptance rules (see § 160.3(d) and related NA7 references) and in some cases require a CMATT to perform testing and include a CMATT ID on the Certificate of Acceptance.
More in California Energy Code
- Compliance paths, energy budgets, performance modeling and forms/software requirements
- Controls, commissioning, demand-response, sensors, and field verification/diagnostic testing
- Domestic hot water systems, efficiency, controls and installation requirements
- Electrical infrastructure, EV charging readiness, load management and demand controls
- Envelope construction, insulation, fenestration and thermal performance
- HVAC systems, ventilation rates, ducting, controls and testing
- Interior and exterior lighting power, controls and daylighting requirements
- Mandatory measures, appliance efficiency and certification requirements
- Photovoltaic requirements, BESS (battery energy storage) sizing and SARA procedures
- Reference appendices, test procedures, product certification and labeling requirements
- Scope, applicability, definitions and administrative requirements
Ask about the California Energy Code
Get cited, plain-English answers on the California Energy Code for your project — any code section, any scenario.
Start Free Trial