§112.0602 Process CIP/Public Project-Two
San Diego Zoning Code · 2026-06 edition · updated 2026-07-25 · San Diego
An application for a Site Development Permit for a capital improvement program project or a public project determined to be in compliance with the Environmentally Sensitive Lands Regulations, Historical Resources Regulations without deviation, or a City-issued Coastal Development Permit in the non- appealable area of the Coastal Overlay Zone shall be acted upon in accordance with Process CIP/Public ProjectTwo. An application for a Process CIP/Public Project-Two decision may be initially approved, conditionally approved, or denied by a staff person designated by the City Manager pursuant to Section 111.0205. A public hearing will not be held. An appeal hearing is available upon written request, in accordance with Section 112.0603. A Process CIP/Public Project-Two decision shall be made in the following manner.
(a) Notice. The designated staff person shall mail a Notice of Future Decision to the persons identified in Section 112.0302(b). Persons who wish to receive notice of the approval or denial of the application may request this information from the staff person. The request must be received no later than 10 business days after the date on which the Notice of Future Decision is mailed.
(b) Decision Process. The designated staff person may approve, conditionally approve, or deny the application without a public hearing. The decision shall be made no less than 11 business days after the date on which the Notice of Future Decision is mailed to allow for sufficient time for public comment.
Notification of the decision shall be given to the applicant and to those persons who request notification in accordance with this section, no later than 2 business days after the decision date .
(“Process CIP-Two” added 10-22-2013 by O-20309 N.S.; effective 12-12-2013.) (Retitled from “Process CIP-Two” to “Process CIP/Public Project-Two” and amended 1-8-2020 by O-21164 N.S.; effective 2-9-2020.) (Amended 1-27-2022 by O-21416 N.S.; effective 2-26-2022.) (Amended 10-12-2022 by O-21546 N.S.; effective 11-11-2022.)
Ch. Art. Div. 11 2 6 3
San Diego Municipal Code
Chapter 11: Land Development Procedures
(2-2025)
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸ Contents — San Diego Zoning Code
- Chapter 9
- Division 2 — House Numbers
- Division 3 — Advertising Displays Adjacent to Scenic Freeways,…
- Division 1 — General Provisions and Definitions
- Division 2 — Financing Facilities
- Division 3 — Bonds
- Division 1 — Housing Code
- Division 2 — Mobilehome Parks and Special Occupancy Parks
- Division 3 — San Diego Housing Commission
- Division 4 — Interim School Facilities Financing Ordinance
- Division 6 — Housing Impact Fees On Commercial Development
- Division 7 — Residential Tenant Protections
- Division 8 — Prohibition of Discrimination Based on a Tenant’s…
- Division 9 — Notice of Tenant’s Right to Operate a Daycare Home
- Division 10 — Affordable Housing Preservation
- Division 11 — Prohibition of Anti-Competitive Automated Rent P…
- Division 12 — Residential Tenant Utility Fees
- Division 1 — In General
- Division 2 — Responsibilities of City Council
- Division 3 — Administration of Program
- Division 5 — Designation of Residential Rehabilitation Areas a…
- Division 6 — Limitations on Amount of Loan
- Division 7 — Terms of Conventional RAP Loans
- Division 9 — Miscellaneous Provisions
- Division 19.7 — The Centre City Planned District
- Division 19.8 — The Centre City Planned District
- Division 2 — Land Development Authorities and Advisory Boards
- Division 2 — Fees and Deposits
- Division 3 — Notice
- Division 4 — Public Hearings
-
▸ Division 5 — Decision Process
Overview- § 112.0501 Overview of Decision Process
- §112.0502 Process One
- §112.0503 Process Two
- §112.0504 Process Two Appeal Hearing
- §112.0505 Process Three
- §112.0506 Process Three Appeals
- §112.0507 Process Four
- §112.0508 Process Four Appeals
- §112.0509 Process Five
- §112.0510 Contents of Appeal Applications
- §112.0511 No Development During Appeal Period
- § 112.0520 Environmental Determination Appeals
- §112.0601 Overview of Decision Process
- §112.0602 Process CIP/Public Project-Two
- §112.0603 Process CIP/Public Project-Two Appeal Hearing
- §112.0604 Process CIP/Public Project-Five
- Division 1 — Definitions
- Division 2 — Rules for Calculation and Measurement
- Division 2 — Enforcement Authorities For the Land Development …
- Division 4 — Procedures For Abatement of Unsafe, Dangerous,
- Division 1 — Adoption And Amendment Procedures for Land Use Pl…
- Division 1 — Zoning and Rezoning Procedures
- Division 3 — Zoning Use Certificate Procedures
- Division 5 — Residential High Occupancy Permit
- Division 6 — Mobile Food Truck Permit
- Division 1 — General Subdivision Procedures
- Division 2 — Certificate of Compliance
- Division 4 — Tentative Maps (Added 12-9-1997 by O-18451 N.S.)
- Division 5 — Parcel Maps (Added 12-9-1997 by O-18451 N.S.; eff…
- Division 6 — Final Maps
- Division 7 — Merger of Parcels (Added 12-9-1997 by O-18451 N.S…
- Division 8 — Reversion to Acreage
- Division 9 — Public Right-of-Way Vacations
- Division 10 — Easement Vacations
- Division 3 — Conditional Use Permit Procedures
- Division 4 — Neighborhood Development Permit Procedures (Added…
- Division 5 — Site Development Permit Procedures
- Division 6 — Planned Development Permit Procedures (Added 12-9…
- Division 8 — Variance Procedures
- Division 1 — General Review Procedures for Previously Conformi…
- Division 2 — Review Procedures for Previously Conforming Signs
- Division 1 — General Procedures and Authorities for Implementa…
- Division 2 — Procedures for Determination of
- Division 3 — Procedures for Preparation and Review of Environm…
- Division 1 — General Construction Permit Authority and Procedu…
- Division 2 — Building Permit Procedures
- Division 3 — Electrical Permit Procedures (Added 12-9-1997 by …
- Division 4 — Plumbing/Mechanical Permit Procedures
- Division 6 — Grading Permit Procedures (Added 12-9-1997 by O-1…
- Division 7 — Public Right-of-Way Permits
- Division 9 — Fire Permit Procedures
- Division 4 — Residential Base Zones
- Division 5 — Commercial Base Zones
- Division 6 — Industrial Base Zones
- Division 7 — Mixed-Use Base Zones
- Division 2 — Airport Approach Overlay Zone
- Division 3 — Airport Environs Overlay Zone
- Division 6 — Sensitive Coastal Overlay Zone
- Division 7 — Mobilehome Park Overlay Zone (Added 12-9-1997 by …
- Division 8 — Parking Impact Overlay Zone
- Division 9 — Residential Tandem Parking Overlay Zone
- Division 10 — Transit Area Overlay Zone
- Division 11 — Urban Village Overlay Zone
- Division 12 — Mission Trails Design District
- Division 13 — Clairemont Height Limit Overlay Zone
- Division 15 — Airport Land Use Compatibility Overlay Zone
- Division 16 — Community Enhancement Overlay Zone