Division 3 — Electrical Permit Procedures (Added 12-9-1997 by O-18451 N.S.)
§129.0315 Electrical Permits for Temporary Installations
San Diego Zoning Code · 2026-06 edition · updated 2026-07-25 · San Diego
(a) The Building Official may issue a Temporary Electrical Permit for the following types of temporary electrical installations:
(1) Temporary power during the time construction is in progress;
(2) Temporary power for carnivals, conventions, festivals, fairs, and similar events. during the time the event is in progress, not to exceed 90 calendar days; and
(3) Temporary power for the testing of any permanent system of wiring prior to the final approval of that system during the time required for testing, not to exceed 30 calendar days.
(b) A Temporary Electrical Permit shall be issued only if the Building Official determines that the safety of life and property will not be jeopardized by the temporary electrical installation.
Ch. Art. Div. 12 9 3 6
San Diego Municipal Code
Chapter 12: Land Development Reviews
(5-2020)
(c) All temporary installations shall conform as nearly as practicable with the requirements of the Electrical Regulations of the San Diego Municipal Code for permanent installations. Deviations from the Electrical Regulations of the San Diego Municipal Code may be permitted if the Building Official determines that the deviations will not cause hazard to life or property.
(d) If the Building Official determines that the electrical installation is a hazard to life or property, the Building Official may immediately disconnect or order disconnection of all energy to the electrical installation and initiate proceedings to rescind or cancel the temporary permit covering the installation.
(e) Upon expiration of the time designated in the Temporary Electrical Permit, the Building Official may disconnect or order disconnection of all electrical energy authorized by the temporary permit.
(Added 12-9-1997 by O-18451 N.S.; effective 1-1-2000.)
(Retitled to “Electrical Permits for Temporary Installations” and amended 7-31-2012 by O-20187 N.S.; effective 8-30-2012.)
Ch. Art. Div. 12 9 3 7
San Diego Municipal Code
Chapter 12: Land Development Reviews
(5-2020)
Article 9: Construction Permits
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸ Contents — San Diego Zoning Code
- Chapter 9
- Division 2 — House Numbers
- Division 3 — Advertising Displays Adjacent to Scenic Freeways,…
- Division 1 — General Provisions and Definitions
- Division 2 — Financing Facilities
- Division 3 — Bonds
- Division 1 — Housing Code
- Division 2 — Mobilehome Parks and Special Occupancy Parks
- Division 3 — San Diego Housing Commission
- Division 4 — Interim School Facilities Financing Ordinance
- Division 6 — Housing Impact Fees On Commercial Development
- Division 7 — Residential Tenant Protections
- Division 8 — Prohibition of Discrimination Based on a Tenant’s…
- Division 9 — Notice of Tenant’s Right to Operate a Daycare Home
- Division 10 — Affordable Housing Preservation
- Division 11 — Prohibition of Anti-Competitive Automated Rent P…
- Division 12 — Residential Tenant Utility Fees
- Division 1 — In General
- Division 2 — Responsibilities of City Council
- Division 3 — Administration of Program
- Division 5 — Designation of Residential Rehabilitation Areas a…
- Division 6 — Limitations on Amount of Loan
- Division 7 — Terms of Conventional RAP Loans
- Division 9 — Miscellaneous Provisions
- Division 19.7 — The Centre City Planned District
- Division 19.8 — The Centre City Planned District
- Division 2 — Land Development Authorities and Advisory Boards
- Division 2 — Fees and Deposits
- Division 3 — Notice
- Division 4 — Public Hearings
- Division 5 — Decision Process
- Division 1 — Definitions
- Division 2 — Rules for Calculation and Measurement
- Division 2 — Enforcement Authorities For the Land Development …
- Division 4 — Procedures For Abatement of Unsafe, Dangerous,
- Division 1 — Adoption And Amendment Procedures for Land Use Pl…
- Division 1 — Zoning and Rezoning Procedures
- Division 3 — Zoning Use Certificate Procedures
- Division 5 — Residential High Occupancy Permit
- Division 6 — Mobile Food Truck Permit
- Division 1 — General Subdivision Procedures
- Division 2 — Certificate of Compliance
- Division 4 — Tentative Maps (Added 12-9-1997 by O-18451 N.S.)
- Division 5 — Parcel Maps (Added 12-9-1997 by O-18451 N.S.; eff…
- Division 6 — Final Maps
- Division 7 — Merger of Parcels (Added 12-9-1997 by O-18451 N.S…
- Division 8 — Reversion to Acreage
- Division 9 — Public Right-of-Way Vacations
- Division 10 — Easement Vacations
- Division 3 — Conditional Use Permit Procedures
- Division 4 — Neighborhood Development Permit Procedures (Added…
- Division 5 — Site Development Permit Procedures
- Division 6 — Planned Development Permit Procedures (Added 12-9…
- Division 8 — Variance Procedures
- Division 1 — General Review Procedures for Previously Conformi…
- Division 2 — Review Procedures for Previously Conforming Signs
- Division 1 — General Procedures and Authorities for Implementa…
- Division 2 — Procedures for Determination of
- Division 3 — Procedures for Preparation and Review of Environm…
- Division 1 — General Construction Permit Authority and Procedu…
- Division 2 — Building Permit Procedures
-
▸ Division 3 — Electrical Permit Procedures (Added 12-9-1997 by …
Overview- §129.0301 Purpose of Electrical Permit Procedures
- §129.0302 When an Electrical Permit Is Required
- §129.0303 Exemptions from an Electrical Permit
- §129.0305 General Rules for Electrical Permits
- §129.0306 Qualifications for Obtaining an Electrical Permit
- §129.0307 How to Apply for an Electrical Permit
- §129.0308 Decision Process for an Electrical Permit
- §129.0309 Issuance of an Electrical Permit and Closing of an E…
- §129.0310 Electrical Permit Expiration
- §129.0314 Required Inspections for an Electrical Permit
- §129.0315 Electrical Permits for Temporary Installations
- Division 4 — Plumbing/Mechanical Permit Procedures
- Division 6 — Grading Permit Procedures (Added 12-9-1997 by O-1…
- Division 7 — Public Right-of-Way Permits
- Division 9 — Fire Permit Procedures
- Division 4 — Residential Base Zones
- Division 5 — Commercial Base Zones
- Division 6 — Industrial Base Zones
- Division 7 — Mixed-Use Base Zones
- Division 2 — Airport Approach Overlay Zone
- Division 3 — Airport Environs Overlay Zone
- Division 6 — Sensitive Coastal Overlay Zone
- Division 7 — Mobilehome Park Overlay Zone (Added 12-9-1997 by …
- Division 8 — Parking Impact Overlay Zone
- Division 9 — Residential Tandem Parking Overlay Zone
- Division 10 — Transit Area Overlay Zone
- Division 11 — Urban Village Overlay Zone
- Division 12 — Mission Trails Design District
- Division 13 — Clairemont Height Limit Overlay Zone
- Division 15 — Airport Land Use Compatibility Overlay Zone
- Division 16 — Community Enhancement Overlay Zone