§129.0219 Extension of Time for the Utilization of a Building Permit

San Diego Zoning Code · 2026-06 edition · updated 2026-07-25 · San Diego

  • (a) Except for the relocation of structures , a permit holder may submit to the Building Official an application for an extension of time to utilize the Building Permit. The application shall be filed no later than one month in advance of the end of the utilization period in Sections 129.0216 or 129.0217. The Building Official may extend the time in which the permit holder may utilize the Building Permit one time, for a period not exceeding 180 calendar days from the end of the utilization period in Sections 129.0216 or 129.0217, if the Building Official determines that circumstances beyond the control of the permit holder prevented completion of the work. All Electrical, Plumbing, or Mechanical Permits associated with a Building Permit shall be extended concurrently with the utilization period of the Building Permit.

Ch. Art. Div. 12 9 2 12

San Diego Municipal Code

Chapter 12: Land Development Reviews

(4-2026)

  • (b) If an application for an extension of time has been filed for the utilization of a Building Permit in accordance with Section 129.0219(a), the existing Building Permit shall automatically be extended until the Building Official has made a decision on the application for an extension of the utilization period.

  • (c) If the Building Permit has expired before an application is submitted for an extension of time for the utilization of a Building Permit, no extension shall be granted. If the previous permit holder or any other applicant wants to proceed with the same development , a new application is required and the application is treated in all respects as a new application.

  • (d) If an extension of time for the utilization of a Building Permit has been previously approved in accordance with Section 129.0219(a), the Building Official may extend the time for the utilization of the Building Permit one additional time, for a period not exceeding 180 calendar days, if the Building Official finds the following:

    • (1) There has not been a significant change in the regulations applicable to the site since the date the permit was issued;

    • (2) The additional extension is in the public interest; and

    • (3) Circumstances beyond the control of the applicant prevented the authorized work from proceeding.

  • (e) If no extension is granted, and the Building Permit has become void pursuant to Section 129.0217, the property owner, permit holder or applicant shall, within 90 calendar days from the date of a written notice from the City, obtain a new Building Permit to complete the work and diligently pursue the work to completion, or remove or demolish the building or structure within 180 calendar days from the date of the written notice. A violation of Section 129.0219 may be prosecuted administratively or judicially pursuant to San Diego Municipal Code Section 121.0311. This Section in no way limits any separate enforcement authority of the City under California Health and Safety Code Section 17980.9 to impose stricter rehabilitation time frames for vacant single family dwellings.

ndar days from the date of the written notice. A violation of Section 129.0219 may be prosecuted administratively or judicially pursuant to San Diego Municipal Code Section 121.0311. This Section in no way limits any separate enforcement authority of the City under California Health and Safety Code Section 17980.9 to impose stricter rehabilitation time frames for vacant single family dwellings.

(Added 12-9-1997 by O-18451 N.S.; effective 1-1-2000.) (Amended 3-1-2006 by O-19468 N.S.; effective 4-1-2006.) (Retitled to “Extension of Time for the Utilization of a Building Permit” and amended 7-31-2012 by O-20187 N.S.; effective 8-30-2012.) (Amended 1-18-2018 by O-20897 N.S.; effective 2-17-2018.) (Amended 5-8-2023 by O-21642 N.S.; effective 6-7-2023.)

Ch. Art. Div. 12 9 2 13

San Diego Municipal Code (4-2026)

Chapter 12: Land Development Reviews

Get a plain-English answer with a citation back to this text.

Ask AI about this code
Contents — San Diego Zoning Code
San Diego Zoning Code
  1. Chapter 9
  2. Division 2 — House Numbers
  3. Division 3 — Advertising Displays Adjacent to Scenic Freeways,…
  4. Division 1 — General Provisions and Definitions
  5. Division 2 — Financing Facilities
  6. Division 3 — Bonds
  7. Division 1 — Housing Code
  8. Division 2 — Mobilehome Parks and Special Occupancy Parks
  9. Division 3 — San Diego Housing Commission
  10. Division 4 — Interim School Facilities Financing Ordinance
  11. Division 6 — Housing Impact Fees On Commercial Development
  12. Division 7 — Residential Tenant Protections
  13. Division 8 — Prohibition of Discrimination Based on a Tenant’s…
  14. Division 9 — Notice of Tenant’s Right to Operate a Daycare Home
  15. Division 10 — Affordable Housing Preservation
  16. Division 11 — Prohibition of Anti-Competitive Automated Rent P…
  17. Division 12 — Residential Tenant Utility Fees
  18. Division 1 — In General
  19. Division 2 — Responsibilities of City Council
  20. Division 3 — Administration of Program
  21. Division 5 — Designation of Residential Rehabilitation Areas a…
  22. Division 6 — Limitations on Amount of Loan
  23. Division 7 — Terms of Conventional RAP Loans
  24. Division 9 — Miscellaneous Provisions
  25. Division 19.7 — The Centre City Planned District
  26. Division 19.8 — The Centre City Planned District
  27. Division 2 — Land Development Authorities and Advisory Boards
  28. Division 2 — Fees and Deposits
  29. Division 3 — Notice
  30. Division 4 — Public Hearings
  31. Division 5 — Decision Process
  32. Division 1 — Definitions
  33. Division 2 — Rules for Calculation and Measurement
  34. Division 2 — Enforcement Authorities For the Land Development …
  35. Division 4 — Procedures For Abatement of Unsafe, Dangerous,
  36. Division 1 — Adoption And Amendment Procedures for Land Use Pl…
  37. Division 1 — Zoning and Rezoning Procedures
  38. Division 3 — Zoning Use Certificate Procedures
  39. Division 5 — Residential High Occupancy Permit
  40. Division 6 — Mobile Food Truck Permit
  41. Division 1 — General Subdivision Procedures
  42. Division 2 — Certificate of Compliance
  43. Division 4 — Tentative Maps (Added 12-9-1997 by O-18451 N.S.)
  44. Division 5 — Parcel Maps (Added 12-9-1997 by O-18451 N.S.; eff…
  45. Division 6 — Final Maps
  46. Division 7 — Merger of Parcels (Added 12-9-1997 by O-18451 N.S…
  47. Division 8 — Reversion to Acreage
  48. Division 9 — Public Right-of-Way Vacations
  49. Division 10 — Easement Vacations
  50. Division 3 — Conditional Use Permit Procedures
  51. Division 4 — Neighborhood Development Permit Procedures (Added…
  52. Division 5 — Site Development Permit Procedures
  53. Division 6 — Planned Development Permit Procedures (Added 12-9…
  54. Division 8 — Variance Procedures
  55. Division 1 — General Review Procedures for Previously Conformi…
  56. Division 2 — Review Procedures for Previously Conforming Signs
  57. Division 1 — General Procedures and Authorities for Implementa…
  58. Division 2 — Procedures for Determination of
  59. Division 3 — Procedures for Preparation and Review of Environm…
  60. Division 1 — General Construction Permit Authority and Procedu…
  61. Division 2 — Building Permit Procedures
  62. Division 3 — Electrical Permit Procedures (Added 12-9-1997 by …
  63. Division 4 — Plumbing/Mechanical Permit Procedures
  64. Division 6 — Grading Permit Procedures (Added 12-9-1997 by O-1…
  65. Division 7 — Public Right-of-Way Permits
  66. Division 9 — Fire Permit Procedures
  67. Division 4 — Residential Base Zones
  68. Division 5 — Commercial Base Zones
  69. Division 6 — Industrial Base Zones
  70. Division 7 — Mixed-Use Base Zones
  71. Division 2 — Airport Approach Overlay Zone
  72. Division 3 — Airport Environs Overlay Zone
  73. Division 6 — Sensitive Coastal Overlay Zone
  74. Division 7 — Mobilehome Park Overlay Zone (Added 12-9-1997 by …
  75. Division 8 — Parking Impact Overlay Zone
  76. Division 9 — Residential Tandem Parking Overlay Zone
  77. Division 10 — Transit Area Overlay Zone
  78. Division 11 — Urban Village Overlay Zone
  79. Division 12 — Mission Trails Design District
  80. Division 13 — Clairemont Height Limit Overlay Zone
  81. Division 15 — Airport Land Use Compatibility Overlay Zone
  82. Division 16 — Community Enhancement Overlay Zone

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.