Division 2 — Building Permit Procedures
§129.0211 Closing of Building Permit Application
San Diego Zoning Code · 2026-06 edition · updated 2026-07-25 · San Diego
(a) If two years have elapsed since the date a Building Permit application is deemed complete and the applicant has not requested that a Building Permit be issued, the application file shall be closed. Plans and other data submitted for review may be returned to the applicant or destroyed by the Building Official. To reapply, the applicant shall submit a new Building Permit application with required submittal materials and shall be subject to all applicable fees and regulations in effect on the date the new application is filed.
(b) The application file for City projects and for residential master planned developments shall be closed after two years have elapsed since the date the Building Permit application is deemed complete . For the purposes of this section, residential master planned developments are residential developments submitted with one or more building types constructed in phases on one or multiple lots .
(c) The Building Official may extend a Building Permit application for a period not exceeding 180 calendar days from the date the Building Permit application was deemed complete if the Building Official determines that circumstances beyond the control of the applicant prevented issuance of the Building Permit.
(d) The Building Official may extend a Building Permit application for one additional period not exceeding 180 calendar days if the Building Official determines that the building standards effective at the time that the Building Permit application was submitted are sufficient to protect public health and safety or the project complies with significant life and safety building standards effective at the time that the Building Permit application was submitted and:
(1) The additional application extension is in the public interest; or
(2) Circumstances beyond the control of the applicant prevented the issuance of the Building Permit.
(e) A Building Permit application shall not be extended more than 360 calendar days from the date the Building Permit application was deemed complete .
(f) If a request to extend the closing date of a Building Permit application has been filed in accordance with this section, the existing Building Permit application shall be automatically extended until the Building Official has made a decision on the request for an extension.
Ch. Art. Div. 12 9 2 9
San Diego Municipal Code
Chapter 12: Land Development Reviews
(4-2026)
(g) The application for all Electrical, Plumbing, Mechanical, or Fire Permits associated with a Building Permit shall expire concurrently with the Building Permit.
(Added 12-9-1997 by O-18451 N.S.; effective 1-1-2000.) (Amended 3-1-2006 by O-19468 N.S.; effective 4-1-2006.) (Amended 7-31-2012 by O-20187 N.S.; effective 8-30-2012.) (Amended 1-18-2018 by O-20897 N.S.; effective 2-17-2018.) (Amended 4-9-2020 by O-21181 N.S.; effective 5-9-2020.) (Amended 3-11-2022 by O-21439 N.S.; effective 4-10-2022.) (Amended 9-18-2023 by O-21725 N.S.; effective 10-18-2023.) (Amended 8-5-2024 by O-21859 N.S.; effective 9-4-2024.)
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸ Contents — San Diego Zoning Code
- Chapter 9
- Division 2 — House Numbers
- Division 3 — Advertising Displays Adjacent to Scenic Freeways,…
- Division 1 — General Provisions and Definitions
- Division 2 — Financing Facilities
- Division 3 — Bonds
- Division 1 — Housing Code
- Division 2 — Mobilehome Parks and Special Occupancy Parks
- Division 3 — San Diego Housing Commission
- Division 4 — Interim School Facilities Financing Ordinance
- Division 6 — Housing Impact Fees On Commercial Development
- Division 7 — Residential Tenant Protections
- Division 8 — Prohibition of Discrimination Based on a Tenant’s…
- Division 9 — Notice of Tenant’s Right to Operate a Daycare Home
- Division 10 — Affordable Housing Preservation
- Division 11 — Prohibition of Anti-Competitive Automated Rent P…
- Division 12 — Residential Tenant Utility Fees
- Division 1 — In General
- Division 2 — Responsibilities of City Council
- Division 3 — Administration of Program
- Division 5 — Designation of Residential Rehabilitation Areas a…
- Division 6 — Limitations on Amount of Loan
- Division 7 — Terms of Conventional RAP Loans
- Division 9 — Miscellaneous Provisions
- Division 19.7 — The Centre City Planned District
- Division 19.8 — The Centre City Planned District
- Division 2 — Land Development Authorities and Advisory Boards
- Division 2 — Fees and Deposits
- Division 3 — Notice
- Division 4 — Public Hearings
- Division 5 — Decision Process
- Division 1 — Definitions
- Division 2 — Rules for Calculation and Measurement
- Division 2 — Enforcement Authorities For the Land Development …
- Division 4 — Procedures For Abatement of Unsafe, Dangerous,
- Division 1 — Adoption And Amendment Procedures for Land Use Pl…
- Division 1 — Zoning and Rezoning Procedures
- Division 3 — Zoning Use Certificate Procedures
- Division 5 — Residential High Occupancy Permit
- Division 6 — Mobile Food Truck Permit
- Division 1 — General Subdivision Procedures
- Division 2 — Certificate of Compliance
- Division 4 — Tentative Maps (Added 12-9-1997 by O-18451 N.S.)
- Division 5 — Parcel Maps (Added 12-9-1997 by O-18451 N.S.; eff…
- Division 6 — Final Maps
- Division 7 — Merger of Parcels (Added 12-9-1997 by O-18451 N.S…
- Division 8 — Reversion to Acreage
- Division 9 — Public Right-of-Way Vacations
- Division 10 — Easement Vacations
- Division 3 — Conditional Use Permit Procedures
- Division 4 — Neighborhood Development Permit Procedures (Added…
- Division 5 — Site Development Permit Procedures
- Division 6 — Planned Development Permit Procedures (Added 12-9…
- Division 8 — Variance Procedures
- Division 1 — General Review Procedures for Previously Conformi…
- Division 2 — Review Procedures for Previously Conforming Signs
- Division 1 — General Procedures and Authorities for Implementa…
- Division 2 — Procedures for Determination of
- Division 3 — Procedures for Preparation and Review of Environm…
- Division 1 — General Construction Permit Authority and Procedu…
-
▸ Division 2 — Building Permit Procedures
Overview- §129.0201 Purpose of Building Permit Procedures
- §129.0202 When a Building Permit Is Required
- §129.0203 Exemptions from a Building Permit
- §129.0204 How to Apply for a Building Permit
- §129.0205 Deferred Submittals of Required Building Permit Appl…
- §129.0206 Who May Prepare Plans for Building Permits
- §129.0207 Preparation of Plans, Reports, Calculations and othe…
- §129.0208 Coordination Responsibilities of Architect or Engine…
- §129.0209 Change of Architect or Engineer of Record
- §129.0210 Plan Review Procedures
- §129.0211 Closing of Building Permit Application
- §129.0212 Decision Process for a Building Permit
- §129.0213 Issuance of a Building Permit
- §129.0214 Requirements for Approved Plans
- §129.0215 Issuance of a Building Permit for a Part of a Struct…
- §129.0216 Initial Utilization of a Building Permit
- §129.0217 Maintaining Utilization of a Building Permit
- §129.0218 Expiration of a Building Permit
- §129.0219 Extension of Time for the Utilization of a Building …
- 129.0220 Required Inspections for a Building Permit
- §129.0221 Expiration of a Building Permit for Relocation of a …
- Division 3 — Electrical Permit Procedures (Added 12-9-1997 by …
- Division 4 — Plumbing/Mechanical Permit Procedures
- Division 6 — Grading Permit Procedures (Added 12-9-1997 by O-1…
- Division 7 — Public Right-of-Way Permits
- Division 9 — Fire Permit Procedures
- Division 4 — Residential Base Zones
- Division 5 — Commercial Base Zones
- Division 6 — Industrial Base Zones
- Division 7 — Mixed-Use Base Zones
- Division 2 — Airport Approach Overlay Zone
- Division 3 — Airport Environs Overlay Zone
- Division 6 — Sensitive Coastal Overlay Zone
- Division 7 — Mobilehome Park Overlay Zone (Added 12-9-1997 by …
- Division 8 — Parking Impact Overlay Zone
- Division 9 — Residential Tandem Parking Overlay Zone
- Division 10 — Transit Area Overlay Zone
- Division 11 — Urban Village Overlay Zone
- Division 12 — Mission Trails Design District
- Division 13 — Clairemont Height Limit Overlay Zone
- Division 15 — Airport Land Use Compatibility Overlay Zone
- Division 16 — Community Enhancement Overlay Zone