§129.0112 Responsibilities of Permit Holder Regarding Inspections
San Diego Zoning Code · 2026-06 edition · updated 2026-07-25 · San Diego
(a) Requesting an Inspection. It shall be the responsibility of the permit holder or the person doing the work authorized by a construction permit to notify the Building Official when work is ready for inspection. The request shall be in accordance with procedures established by the City Manager. The Building Official may require that every request for inspection be filed at least one business day before the inspection is desired.
(b) Providing Access for Inspections. The permit holder is responsible for providing access to, and means for inspection of, the work to be inspected. Neither the Building Official nor the City shall be liable for expense entailed in the removal or replacement of any material required to allow inspection.
(c) Installation or Functional Testing. When required by the Building Official, the permit holder is responsible for performing installation testing or functional testing to demonstrate compliance with the San Diego Fire Code, the Building, Electrical, Plumbing, Mechanical, Residential Building, Green Building and Existing Building Regulations of the Land Development Code or with other applicable regulation of the Municipal Code. Tests shall be conducted in the presence of the Building Official.
(d) Reinspection. A fee may be assessed for reinspection if the inspected work is determined to be incomplete. If reinspection fees have been assessed on a site, no additional inspection of the work will be performed until the required fees have been paid.
(e) Maintaining Inspection Record Card. Before beginning any permitted work, the permit holder shall post an inspection record card on the site or the card shall be otherwise conveniently accessible to the Building Official or City Engineer. The card shall be kept accessible by the permit holder until final inspection approval has been granted by the Building Official or City Engineer.
(f) One set of the approved plans, permits, and specifications shall be kept on the site of the structure or work at all times during which work authorized by those plans is in progress, and shall be made available to City officials upon request.
(Added 12-9-1997 by O-18451 N.S.; effective 1-1-2000.)
(Amended 11-28-2005 by O-19444 N.S.; effective 2-9-2006.)
(Retitled to “Responsibilities of Permit Holder or Authorized Agent Regarding Inspections” and amended 7-31-2012 by O-20187 N.S.; effective 8-30-2012.) (Retitled to “Responsibilities of Permit Holder Regarding Inspections” and amended 1-18-2018 by O-20897 N.S.; effective 2-17-2018.)
Ch. Art. Div. 12 9 1 11
San Diego Municipal Code (10-2024)
Chapter 12: Land Development Reviews
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸ Contents — San Diego Zoning Code
- Chapter 9
- Division 2 — House Numbers
- Division 3 — Advertising Displays Adjacent to Scenic Freeways,…
- Division 1 — General Provisions and Definitions
- Division 2 — Financing Facilities
- Division 3 — Bonds
- Division 1 — Housing Code
- Division 2 — Mobilehome Parks and Special Occupancy Parks
- Division 3 — San Diego Housing Commission
- Division 4 — Interim School Facilities Financing Ordinance
- Division 6 — Housing Impact Fees On Commercial Development
- Division 7 — Residential Tenant Protections
- Division 8 — Prohibition of Discrimination Based on a Tenant’s…
- Division 9 — Notice of Tenant’s Right to Operate a Daycare Home
- Division 10 — Affordable Housing Preservation
- Division 11 — Prohibition of Anti-Competitive Automated Rent P…
- Division 12 — Residential Tenant Utility Fees
- Division 1 — In General
- Division 2 — Responsibilities of City Council
- Division 3 — Administration of Program
- Division 5 — Designation of Residential Rehabilitation Areas a…
- Division 6 — Limitations on Amount of Loan
- Division 7 — Terms of Conventional RAP Loans
- Division 9 — Miscellaneous Provisions
- Division 19.7 — The Centre City Planned District
- Division 19.8 — The Centre City Planned District
- Division 2 — Land Development Authorities and Advisory Boards
- Division 2 — Fees and Deposits
- Division 3 — Notice
- Division 4 — Public Hearings
- Division 5 — Decision Process
- Division 1 — Definitions
- Division 2 — Rules for Calculation and Measurement
- Division 2 — Enforcement Authorities For the Land Development …
- Division 4 — Procedures For Abatement of Unsafe, Dangerous,
- Division 1 — Adoption And Amendment Procedures for Land Use Pl…
- Division 1 — Zoning and Rezoning Procedures
- Division 3 — Zoning Use Certificate Procedures
- Division 5 — Residential High Occupancy Permit
- Division 6 — Mobile Food Truck Permit
- Division 1 — General Subdivision Procedures
- Division 2 — Certificate of Compliance
- Division 4 — Tentative Maps (Added 12-9-1997 by O-18451 N.S.)
- Division 5 — Parcel Maps (Added 12-9-1997 by O-18451 N.S.; eff…
- Division 6 — Final Maps
- Division 7 — Merger of Parcels (Added 12-9-1997 by O-18451 N.S…
- Division 8 — Reversion to Acreage
- Division 9 — Public Right-of-Way Vacations
- Division 10 — Easement Vacations
- Division 3 — Conditional Use Permit Procedures
- Division 4 — Neighborhood Development Permit Procedures (Added…
- Division 5 — Site Development Permit Procedures
- Division 6 — Planned Development Permit Procedures (Added 12-9…
- Division 8 — Variance Procedures
- Division 1 — General Review Procedures for Previously Conformi…
- Division 2 — Review Procedures for Previously Conforming Signs
- Division 1 — General Procedures and Authorities for Implementa…
- Division 2 — Procedures for Determination of
- Division 3 — Procedures for Preparation and Review of Environm…
-
▸ Division 1 — General Construction Permit Authority and Procedu…
Overview- §129.0101 Purpose of Construction Review Procedures
- §129.0102 When Construction Permit Procedures Apply
- §129.0103 Interpretation of Differing Regulations
- §129.0104 Construction Permit Authorities
- §129.0105 How to Apply for Construction Permit Review
- §129.0107 Decision Process for Construction Permits
- §129.0108 Issuance of a Construction Permit
- §129.0109 Use of Alternate Materials, Design, or Construction …
- §129.0110 Testing of Materials, Designs, or Construction Methods
- §129.0111 General Rules for Construction Permit Inspections
- §129.0112 Responsibilities of Permit Holder Regarding Inspecti…
- §129.0113 When a Certificate of Occupancy Is Required
- §129.0114 Issuance of a Certificate of Occupancy
- § 129.0115 Issuance of a Temporary Certificate of Occupancy
- §129.0116 Posting of Certificate of Occupancy
- §129.0117 Temporary Construction Permit
- §129.0118 Suspension or Revocation of a Certificate of Occupancy
- §129.0119 Bond Required for Construction Permit for Grading or…
- §129.0120 Lot Tie Agreements
- §129.0121 License and Insurance Requirements for Contractors a…
- §129.0122 Indemnification for Construction Permits
- Division 2 — Building Permit Procedures
- Division 3 — Electrical Permit Procedures (Added 12-9-1997 by …
- Division 4 — Plumbing/Mechanical Permit Procedures
- Division 6 — Grading Permit Procedures (Added 12-9-1997 by O-1…
- Division 7 — Public Right-of-Way Permits
- Division 9 — Fire Permit Procedures
- Division 4 — Residential Base Zones
- Division 5 — Commercial Base Zones
- Division 6 — Industrial Base Zones
- Division 7 — Mixed-Use Base Zones
- Division 2 — Airport Approach Overlay Zone
- Division 3 — Airport Environs Overlay Zone
- Division 6 — Sensitive Coastal Overlay Zone
- Division 7 — Mobilehome Park Overlay Zone (Added 12-9-1997 by …
- Division 8 — Parking Impact Overlay Zone
- Division 9 — Residential Tandem Parking Overlay Zone
- Division 10 — Transit Area Overlay Zone
- Division 11 — Urban Village Overlay Zone
- Division 12 — Mission Trails Design District
- Division 13 — Clairemont Height Limit Overlay Zone
- Division 15 — Airport Land Use Compatibility Overlay Zone
- Division 16 — Community Enhancement Overlay Zone