Division 10 — CONTRACTS›Article 1 — CONTRACTS REQUIREMENTS

Los Angeles Municipal Code § 10.14 Provisions Pertaining to Listing of Subcontractors

Los Angeles Municipal Code · 2026-09 edition · updated 2026-10-04 · Los Angeles

Cite as: Los Angeles Municipal Code § 10.14 · Text as of 2026-10-04

  1. Definitions. For the purposes of this section the definitions of “contractor” and “subcontractor” contained in Section 10.8.1 of this article shall be applicable.

  2. Listing of Subcontractors. Each officer, department, board or commission awarding contracts for the construction of any public work or improvement within the City of Los Angeles shall provide in the bid documents prepared for such work or improvement that every person making a bid or offering to perform the work shall state therein:

    (a) The name and address of each subcontractor who will perform work or labor or render service to the bidder in or about the

    construction of the work or improvement in an amount in excess of one-half of one percent (1/2%) of the prime contractor’s total bid or $10,000.00, whichever is greater.

    (b) That portion of the work which will be done by each subcontractor.

The prime contractor shall list only the subcontractor for each such portion as is defined by the prime contractor in its bid. Failure of prime contractor to specify a subcontractor for any portion of the work shall constitute agreement by said contractor that it is fully qualified to perform that work and shall perform with its own forces.

  1. Substitution. No prime contractor whose bid is accepted may substitute any person as subcontractor in place of the subcontractor listed in the original bid or offer except in the following instances:

(a) When the subcontractor listed in the bid after a reasonable opportunity to do so fails or refuses to execute a written contract when such contract, based upon the general terms, conditions, plans and specifications for the project involved or the terms of such subcontractor’s written bid, is presented to it by the prime contractor.

(b) When the listed subcontractor becomes bankrupt or insolvent.

(c) When the listed subcontractor fails or refuses to perform its subcontract.

(d) When the listed subcontractor fails or refuses to meet the bond requirements of the prime contractor as set forth in Subsection 4

of this section.

(e) When the contractor demonstrates to the satisfaction of the awarding authority that the subcontractor was listed by inadvertent

clerical error.

(f) When the awarding authority determines that work being performed by the listed subcontractor is substantially unsatisfactory

and not in substantial accordance with the plans and specifications, or the listed subcontractor is substantially delaying or disrupting the progress of the work.

(g) When the listed subcontractor fails to submit an Affirmative Action Plan acceptable to the awarding authority.

The prime contractor, as a condition of asserting a claim of inadvertent clerical error in a listing of a subcontractor, shall within two working days after the time of the prime bid opening by the awarding authority given written notice to the awarding authority and copies of such notice to both the subcontractor it claims to have listed in error and the intended subcontractor who had bid to the prime contractor prior to bid opening. Any listed subcontractor who has been notified by the prime contractor in accordance with the provisions of this section as to an inadvertent clerical error shall be allowed six working days from the time of the prime bid opening within which to submit to the awarding authority and to the prime contractor written objection to the prime contractor’s claim of inadvertent clerical error.

In all other cases, the prime contractor must make a request in writing to the awarding authority for the substitution of subcontractors, giving reasons therefor. The awarding authority shall mail a written notice to the listed subcontractor giving reasons for the proposed substitution. The listed subcontractor shall have five working days from the date of such notice within which to file with the awarding authority written objections to the substitution.

Failure to file written objections pursuant to the provisions of this section within the times specified herein shall constitute a waiver of objection to the substitution by the listed subcontractor and, where the ground for substitution is an inadvertent clerical error, an agreement by the listed subcontractor that an inadvertent clerical error was made.

If written objections are filed, the awarding authority shall give five days’ notice to the prime contractor and to the listed subcontractor of a hearing by the awarding authority on the prime contractor’s request for substitution. The determination by the awarding authority shall be final.

  1. Subcontractor’s Performance Bonds. In the event any subcontractor submitting a bid to a prime contractor does not, upon the request of the prime contractor and at the expense of the prime contractor at the established charge or premium therefor, furnish to such prime contractor a bond or bonds issued by an admitted surety wherein the prime contractor shall be named the obligee, guaranteeing prompt and faithful performance of such subcontract and the payment of all claims for labor and materials furnished or used in and about the work to be performed and performed under such subcontract, the prime contractor may reject such bid and make a substitution of another subcontractor subject to the provisions of Subsection 3 of this section. Such bond or bonds may be required at the expense of the subcontractor only if the prime contractor in its written or published request for sub-bids (1) specifies that the expense of such bond or bonds shall be borne by the subcontractor and (2) clearly specifies the amount and requirements of such bond or bonds.

  2. Assignment. No contractor shall permit any subcontract to be voluntarily assigned or transferred or allow it to be performed by anyone other than the original subcontractor listed on the original bid without the consent of the awarding authority or its duly authorized officer.

  1. Penalties. A contractor violating any provisions of this section shall be deemed in violation of the contract and the City may at its

discretion:

(a) Cancel the contract.

(b) Assess the contractor a penalty of not more than 10% of the amount of the subcontract involved.

  1. Notwithstanding the requirements of this section, Council may, by ordinance, waive the requirements in Subsections 2. and 5. for specific projects involving the competitive sealed proposal process under Los Angeles City Charter Section 371(b) and provide in the ordinance alternative requirements.

In any proceeding under this section the prime contractor shall be entitled to a public hearing and to five days’ notice of the time and place thereof.

SECTION HISTORY

Added by Ord. No. 150,595, Eff. 4-2-78. Amended by: Subsec. 2.(a), Subsec. 3.(f) deleted, Subsecs. (g) and (h) relettered Subsecs. (f) and (g) respectively, Ord. No. 150,786, Eff. 4-24-78; Para. 2, Ord. No. 170,882, Eff. 3-1-96; Subsec. 7. added, Ord. No. 184,936, Eff. 7-11-17.

Sec. 10.14.1. Sale of Animals From the Los Angeles City Zoo.

(a) Animals from the Los Angeles City Zoo shall be sold only in compliance with the requirements of Section 53.80 of the Municipal Code of the City of Los Angeles. Every contract providing for the sale of animals from the Zoo shall include, as a material condition thereof, a requirement that such animals are not to be used for any Inhumane Purpose, as that term is defined in Section 53.80 of said Municipal Code. The contract shall incorporate therein by reference a written statement of the purpose or purposes for which the animals are being purchased, the actual user or recipient of the animals, and a certification that the animals are not being purchased for any Inhumane Purpose. Such statement and certification shall be provided by the purchaser as part of the purchaser’s offer to purchase. In addition, the contract for sale of such animals shall require that the purchaser provided a written certification, by the stated actual user or recipient of such animals, that the animals have been received and that they will be used in accordance with the purposes stated in the corresponding offer to purchase.

(b) No sale of animals from the Los Angeles City Zoo shall be made to any animal dealer or broker before the Zoo Director has established and implemented a procedure whereby the use or delivery of the animals to be sold to any such animal dealer or broker, as represented in the dealer’s or broker’s written offer to purchase, can be verified with the stated actual user or recipient of such animals.

(c) The Director of the Los Angeles City Zoo shall create and maintain a list of animal breeders, brokers and dealers recognized by the Director as being legitimately engaged in those activities. No breeder, broker or dealer of animals shall be placed on, or allowed to remain on, said list who is found to have purchased, sold or used any animals for any Inhumane Purpose, as that term is defined in Section 53.80 of said Municipal Code, within the preceding five years.

(d) Each breeder, broker or dealer of animals found by the Zoo Director to have purchased, sold or used any animals for any Inhumane Purposes within the preceding five years shall be deemed to be a non-responsible party for purposes of doing business with the City Zoo, and no contract for the transportation of animals or for any other services shall be entered into with that party during the five year period of time subsequent to such purchase, sale or use.

SECTION HISTORY

Added by Ord. No. 165,764, Eff. 5-19-90.

Exceptions & meaning →

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — Los Angeles Municipal Code

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.