Sec. 14-40. - Adoption.¶
The 2022 California Building Code, codified in Part 2 of Title 24 of the California Code of Regulations, including Appendices C, F, G, I, and J, as such code may be amended from time to time, except as hereinafter amended by this division, is adopted by reference as the building code of the city.
(Ord. No. 2003, § 3(Exh. A), 11-8-22)
Sec. 14-41. - Amendments.¶
Chapter I, Division II Scope and Administration, is deleted in its entirety from the California Building Code, 2022 Edition and replaced to read as follows:
DIVISION II SCOPE AND APPLICATION
PART 1 SCOPE AND APPLICATION
Section 101 General
[A] 101.1 Title. These regulations shall be known as the Building Code of City of Hemet, hereinafter referred to as "this code."
[A] 101.2 Scope. The provisions of this code shall apply to the construction, alteration, relocation, enlargement, replacement, repair, equipment, use and occupancy, location, maintenance, removal and demolition of every building or structure or any appurtenances connected or attached to such buildings or structures.
Exception: Detached one- and two-family dwellings and multiple single-family dwellings and townhouses not more than three stories above grade plane in height with a separate means of egress, and their accessory structures not more than three stories above grade plane in height, shall comply with the California Residential Code.
[A] 101.2.1 Appendices. Provisions in the appendices shall not apply except for Appendix Chapters C, F, G, I and J.
[A] 101.3 Intent. The purpose of this code is to establish the minimum requirements to provide a reasonable level of safety, public health and general welfare through structural strength, means of egress facilities, stability, sanitation, adequate light and ventilation, energy conservation, and safety to life and property from fire, explosion and other hazards, and to provide a reasonable level of safety to fire fighters and emergency responders during emergency operations.
[A] 101.4 Referenced codes. The other codes listed in Sections 101.4.1 through 101.4.6 and referenced elsewhere in this code shall be considered part of the requirements of this code to the prescribed extent of each such reference.
[A] 101.4.1 Gas. The provisions of the California Mechanical Code shall apply to the installation of gas piping from the point of delivery, gas appliances and related accessories as covered in this code. These requirements apply to gas piping systems extending from the point of delivery to the inlet connections of appliances and the installation and operation of residential and commercial gas appliances and related accessories.
[A] 101.4.2 Mechanical. The provisions of the California Mechanical Code shall apply to the installation, alterations, repairs and replacement of mechanical systems, including equipment, appliances, fixtures, fittings and/or appurtenances, including ventilating, heating, cooling, air-conditioning and refrigeration systems, incinerators and other energy-related systems.
[A] 101.4.3 Plumbing. The provisions of the California Plumbing Code shall apply to the installation, alteration, repair and replacement of plumbing systems, including equipment, appliances, fixtures, fittings and appurtenances, and where connected to a water or sewage system and all aspects of a medical gas system. The provisions of the International Private Sewage Disposal Code shall apply to private sewage disposal systems.
[A] 101.4.4 Property maintenance. The provisions of the International Property Maintenance Code shall apply to existing structures and premises; equipment and facilities; light, ventilation, space heating, sanitation, life and fire safety hazards; responsibilities of owners, operators and occupants; and occupancy of existing premises and structures.
[A] 101.4.5 Fire prevention. The provisions of the California Fire Code shall apply to matters affecting or relating to structures, processes and premises from the hazard of fire and explosion arising from the storage, handling or use of structures, materials or devices; from conditions hazardous to life, property or public welfare in the occupancy of structures or premises; and from the construction, extension, repair, alteration or removal of fire suppression, automatic sprinkler systems and alarm systems or fire hazards in the structure or on the premises from occupancy or operation.
[A] 101.4.6 Energy. The provisions of the California Energy Code shall apply to all matters governing the design and construction of buildings for energy efficiency.
[A] 101.4.7 Existing buildings. The provisions of the California Existing Building Code shall apply to matters governing the repair, alteration, change of occupancy, addition to and relocation of existing buildings.
[OSHPD 1] The provisions of the Chapter 2A, 3A, 4A, and 5A of the California Existing Building Code shall apply to all matters governing the repairs, alterations, change of occupancy, additions, and relocation of existing structures and portions thereof under OSHPD jurisdiction. All references to Chapters 3, 4 and 5 of the California Existing Building Code shall be replaced by equivalent provisions in Chapters 3A, 4A and 5A.
[OSHPD 1R, 2, 4 & 5] The provisions of the California Existing Building Code, Chapters 2, 3, 4 and 5 shall apply to all matters governing the repairs, alterations, change of occupancy, additions and relocation of existing structures and portions thereof under OSHPD jurisdiction.
Section 102 Applicability
[A] 102.1 General. Where there is a conflict between a general requirement and a specific requirement, the specific requirement shall be applicable. Where, in any specific case, different sections of this code specify different materials, methods of construction or other requirements, the most restrictive shall govern.
[A] 102.2 Other laws. The provisions of this code shall not be deemed to nullify any provisions of local, state or federal law.
[A] 102.3 Application of references. References to chapter or section numbers, or to provisions not specifically identified by number, shall be construed to refer to such chapter, section or provision of this code.
[A] 102.4 Referenced codes and standards. The codes and standards referenced in this code shall be considered part of the requirements of this code to the prescribed extent of each such reference and as further regulated in Sections 102.4.1 through 102.4.4.
[A] 102.4.1 Conflicts. Where conflicts occur between provisions of this code and referenced codes and standards, the provisions of this code shall apply.
[A] 102.4.2 Provisions in referenced codes and standards. Where the extent of the reference to a referenced code or standard includes subject matter that is within the scope of this code, shall take precedence over the provisions in the referenced code or standard.
102.4.3 Code references. [OSHPD 1, 1R, 2, 3, 4 & 5, DSA-SS & DSA-SS/CC] All reference to International Codes or other similar codes in referenced standards shall be replaced by equivalent provisions in the California Building Standards Codes.
102.4.4 Reference in standards. [OSHPD 1, 1R, 2, 3, 4 & 5, DSA-SS & DSA-SS/CC] All references listed in reference standards shall be replaced by referenced standards listed in Chapter 35 of this code, where applicable, and shall include all amendments to the reference standards in this code.
[A] 102.5 Partial invalidity. In the event that any part or provision of this code is held to be illegal or void, this shall not have the effect of making void or illegal any of the other parts or provisions.
[A] 102.6 Existing structures. The legal occupancy of any structure existing on the date of adoption of this code shall be permitted to continue without change, except as otherwise specifically provided in this code, the California Existing Building Code or the California Fire Code.
[A] 102.6.1 Buildings not previously occupied. A building or portion of a building that has not been previously occupied or used for its intended purpose in accordance with the laws in existence at the time of its completion shall comply with the provisions of the California Building Code or California Residential Code, as applicable, for new construction or with any current permit for such occupancy.
[A] 102.6.2 Buildings previously occupied. The legal occupancy of any building existing on the date of adoption of this code shall be permitted to continue without change, except as otherwise specifically provided in this code, the California Fire Code or International Property Maintenance Code, or as is deemed necessary by the building official for the general safety and welfare of the occupants and the public.
PART 2 ADMINISTRATION AND ENFORCEMENT
Section 103 Department of Life Safety
[A] 103.1 Creation of enforcement agency. The Department of Life Safety is hereby created and the official in charge thereof shall be known as the Chief Building Official. Any reference in the Hemet Municipal Code, including codes adopted by reference, to the building official shall be interpreted as referring to the Chief Building Official of the City of Hemet.
[A] 103.2 Appointment. The Chief Building Official shall be appointed by the City Manager.
[A] 103.3 Deputies. The City Manager shall have the authority to appoint the building official, deputy building officials, related technical officers, inspectors, plan examiners and other employees. Such officials shall have powers as delegated by the Chief Building Official.
Section 104 Duties and Powers of Building Official
[A] 104.1 General. The building official is hereby authorized and directed to enforce the provisions of this code. The building official shall have the authority to render interpretations of this code and to adopt policies and procedures in order to clarify the application of its provisions. Such interpretations, policies and procedures shall be in compliance with the intent and purpose of this code. Such policies and procedures shall not have the effect of waiving requirements specifically provided for in this code.
[A] 104.2 Applications and permits. The building official shall receive applications, review construction documents and issue permits for the erection, and alteration, demolition and moving of buildings and structures, inspect the premises for which such permits have been issued and enforce compliance with the provisions of this code.
[A] 104.2.1 Determination of substantially improved or substantially damaged existing buildings and structures in flood hazard areas. For applications for reconstruction, rehabilitation, repair, alteration, addition or other improvement of existing buildings or structures located in flood hazard areas, the building official shall determine if the proposed work constitutes substantial improvement or repair of substantial damage. Where the building official determines that the proposed work constitutes substantial improvement or repair of substantial damage, and where required by this code, the building official shall require the building to meet the requirements of Section 1612.
[A] 104.3 Notices and orders. The building official shall issue all necessary notices or orders to ensure compliance with this code.
[A] 104.4 Inspections. The building official shall make all of the required inspections, or the building official shall have the authority to accept reports of inspection by approved agencies or individuals. Reports of such inspections shall be in writing and be certified by a responsible officer of such approved agency or by the responsible individual. The building official is authorized to engage such expert opinion as deemed necessary to report upon unusual technical issues that arise, subject to the approval of the appointing authority.
[A] 104.5 Identification. The building official shall carry proper identification when inspecting structures or premises in the performance of duties under this code.
[A] 104.6 Right of entry. Where it is necessary to make an inspection to enforce the provisions of this code, or where the building official has reasonable cause to believe that there exists in a structure or upon a premises a condition which is contrary to or in violation of this code which makes the structure or premises unsafe, dangerous or hazardous, the building official is authorized to enter the structure or premises at reasonable times to inspect or to perform the duties imposed by this code, provided that if such structure or premises be occupied that credentials be presented to the occupant and entry requested. If such structure or premises is unoccupied, the building official shall first make a reasonable effort to locate the owner or other person having charge or control of the structure or premises and request entry. If entry is refused, the building official shall have recourse to the remedies provided by law to secure entry.
[A] 104.7 Department records. The building official shall keep official records of applications received, permits and certificates issued, fees collected, reports of inspections, and notices and orders issued. Such records shall be retained in the official records for the period required for retention of public records.
[A] 104.8 Liability. The building official, member of the board of appeals or employee charged with the enforcement of this code, while acting for the jurisdiction in good faith and without malice in the discharge of the duties required by this code or other pertinent law or ordinance, shall not thereby be civilly or criminally rendered liable personally and is hereby relieved from personal liability for any damage accruing to persons or property as a result of any act or by reason of an act or omission in the discharge of official duties.
[A] 104.8.1 Legal defense. Any suit or criminal complaint instituted against an officer or employee because of an act performed by that officer or employee in the lawful discharge of duties and under the provisions of this code shall be defended by legal representatives of the jurisdiction until the final termination of the proceedings. The building official or any subordinate shall not be liable for cost in any action, suit or proceeding that is instituted in pursuance of the provisions of this code.
[A] 104.9 Approved materials and equipment. Materials, equipment and devices approved by the building official shall be constructed and installed in accordance with such approval.
[A] 104.9.1 Used materials and equipment. The use of used materials which meet the requirements of this code for new materials is permitted. Used equipment and devices shall not be reused unless approved by the building official.
[A] 104.10 Modifications. Where there are practical difficulties involved in carrying out the provisions of this code, the building official shall have the authority to grant modifications for individual cases, upon application of the owner or the owner's authorized agent, provided that the building official shall first find that special individual reason makes the strict letter of this code impractical, the modification is in compliance with the intent and purpose of this code and that such modification does not lessen health, accessibility, life and fire safety or structural requirements. The details of action granting modifications shall be recorded and entered in the files of the department of building safety.
[A] 104.10.1 Flood hazard areas. The building official shall not grant modifications to any provision required in flood hazard areas as established by Section 1612.3 unless a determination has been made that:
A showing of good and sufficient cause that the unique characteristics of the size, configuration or topography of the site render the elevation standards of Section 1612 inappropriate.
A determination that failure to grant the variance would result in exceptional hardship by rendering the lot undevelopable.
A determination that the granting of a variance will not result in increased flood heights, additional threats to public safety, extraordinary public expense, cause fraud on or victimization of the public, or conflict with existing laws or ordinances.
A determination that the variance is the minimum necessary to afford relief, considering the flood hazard.
Submission to the applicant of written notice specifying the difference between the design flood elevation and the elevation to which the building is to be built, stating that the cost of flood insurance will be commensurate with the increased risk resulting from the reduced floor elevation, and stating that construction below the design flood elevation increases risks to life and property.
[A] 104.11 Alternative materials, design and methods of construction and equipment. The provisions of this code are not intended to prevent the installation of any material or to prohibit any design or method of construction not specifically prescribed by this code, provided that any such alternative has been approved. An alternative material, design or method of construction shall be approved where the building official finds that the proposed design is satisfactory and complies with the intent of the provisions of this code, and that the material, method or work offered is, for the purpose intended, not less than the equivalent of that prescribed in this code in quality, strength, effectiveness, fire resistance, durability and safety. Where the alternative material, design or method of construction is not approved, the building official shall respond in writing, stating the reasons why the alternative was not approved.
[DSA-SS, DSA-SS/CC & OSHPD 1, 1R, 2, 4 & 5] Alternative system shall satisfy ASCE 7 Section 1.3, unless more restrictive requirements are established by this code for an equivalent system.
[DSA-SS, DSA-SS/CC] Alternative systems shall also satisfy the California Administrative Code, Section 4-304.
[OSHPD 1, 1R, 2, 4 & 5] Alternative systems shall also satisfy the California Administrative Code, Section 7-104.
[A] 104.11.1 Research reports. Supporting data, where necessary to assist in the approval of materials or assemblies not specifically provided for in this code, shall consist of valid research reports from approved sources.
[A] 104.11.2 Tests. Whenever there is insufficient evidence of compliance with the provisions of this code, or evidence that a material or method does not conform to the requirements of this code, or in order to substantiate claims for alternative materials or methods, the building official shall have the authority to require tests as evidence of compliance to be made at no expense to the jurisdiction. Test methods shall be as specified in this code or by other recognized test standards. In the absence of recognized and accepted test methods, the building official shall approve the testing procedures. Tests shall be performed by an approved agency. Reports of such tests shall be retained by the building official for the period required for retention of public records.
104.11.3 Peer review. [OSHPD 1, 1R, 2, 4 & 5] When peer review is required for new or existing buildings, it shall be performed pursuant to Section 1617A.1.41.
104.11.4 Earthquake monitoring instruments. [OSHPD 1 & 4] The enforcement agency may require earthquake monitoring instruments for any building that receives approval of an alternative system for the Lateral Force Resisting System (LFRS). There shall be a sufficient number of instruments to characterize the response of the building during an earthquake and shall include at least one tri-axial free field instrument or equivalent. A proposal for instrumentation and equipment specifications shall be forwarded to the enforcement agency for review and approval.
The instruments shall be interconnected for common start and common timing. Each instrument shall be located so that access is maintained at all times and is unobstructed by room contents. A sign stating "MAINTAIN CLEAR ACCESS TO THIS INSTRUMENT" shall be posted in a conspicuous location.
The Owner of the building shall be responsible for the implementation of the instrumentation program. Maintenance of the instrumentation and removal/processing of the records shall be the responsibility of the enforcement agency or its designated agent.
Section 105 Permits
[A] 105.1 Required. Any owner or owner's authorized agent who intends to construct, enlarge, alter, repair, move, demolish or change the occupancy of a building or structure, or to erect, install, enlarge, alter, repair, remove, convert or replace any electrical, gas, mechanical or plumbing system, the installation of which is regulated by this code, or to cause any such work to be performed, shall first make application to the building official and obtain the required permit.
[A] 105.1.1 Annual permit. In lieu of an individual permit for each alteration to an already approved electrical, gas, mechanical or plumbing installation, the building official is authorized to issue an annual permit upon application therefor to any person, firm or corporation regularly employing one or more qualified tradespersons in the building, structure or on the premises owned or operated by the applicant for the permit.
[A] 105.1.2 Annual permit records. The person to whom an annual permit is issued shall keep a detailed record of alterations made under such annual permit. The building official shall have access to such records at all times or such records shall be filed with the building official as designated.
[A] 105.2 Work exempt from permit. Exemptions from permit requirements of this code shall not be deemed to grant authorization for any work to be done in any manner in violation of the provisions of this code or any other laws or ordinances of this jurisdiction. Permits shall not be required for the following:
One-story detached accessory structures used as tool and storage sheds, playhouses and similar uses, provided the floor area is not greater than 120 square feet (11 m2) and all setbacks per the Hemet Municipal Code are adhered to.
Oil derricks.
Retaining walls, concrete and masonry walls that are not over 36 inches in height measured from the top of the footing to the top of the wall, unless supporting a surcharge or impounding Class I, II or IIIA liquids.
Water tanks supported directly on grade if the capacity is not greater than 5,000 gallons (18 925 L) and the ratio of height to diameter or width is not greater than 2:1.
Sidewalks and driveways not more than 30 inches (762 mm) above adjacent grade, and not over any basement or story below and are not part of an accessible route.
Painting, papering, tiling, carpeting, cabinets, counter tops and similar finish work.
Temporary motion picture, television and theater stage sets and scenery.
Prefabricated swimming pools accessory to a Group R-3 occupancy that are less than 24 inches (610 mm) deep, are not greater than 5,000 gallons (18 925 L) and are installed entirely above ground.
Shade cloth structures constructed for nursery or agricultural purposes, not including service systems.
Swings and other playground equipment accessory to detached one- and two-family dwellings.
Window awnings in Group R-3 and U occupancies, supported by an exterior wall that do not project more than 54 inches (1372 mm) from the exterior wall and do not require additional support.
Non-fixed and movable fixtures, cases, racks, counters and partitions not over 5 feet 9 inches (1753 mm) in height.
[A] 105.2.1 Emergency repairs. Where equipment replacements and repairs must be performed in an emergency situation, the permit application shall be submitted within the next working business day to the building official.
[A] 105.2.2 Public service agencies. A permit shall not be required for the installation, alteration or repair of generation, transmission, distribution or metering or other related equipment that is under the ownership and control of public service agencies by established right.
[A] 105.3 Application for permit. To obtain a permit, the applicant shall first file an application therefor in writing on a form furnished by the department of building safety for that purpose. Such application shall:
Identify and describe the work to be covered by the permit for which application is made.
Describe the land on which the proposed work is to be done by legal description, street address or similar description that will readily identify and definitely locate the proposed building or work.
Indicate the use and occupancy for which the proposed work is intended.
Be accompanied by construction documents and other information as required in Section 107.
State the valuation of the proposed work.
Be signed by the applicant, or the applicant's authorized agent.
Give such other data and information as required by the building official.
[A] 105.3.1 Action on application. The building official shall examine or cause to be examined applications for permits and amendments thereto within a reasonable time after filing. If the application or the construction documents do not conform to the requirements of pertinent laws, the building official shall reject such application in writing, stating the reasons therefor. If the building official is satisfied that the proposed work conforms to the requirements of this code and laws and ordinances applicable thereto, the building official shall issue a permit therefor as soon as practicable.
[A] 105.3.2 Time limitation of application. An application for a permit for any proposed work shall be deemed to have been abandoned 180 days after the date of filing, unless such application has been pursued in good faith or a permit has been issued; except that the building official is authorized to grant one or more extensions of time for additional periods not exceeding 180 days each. The extension shall be requested in writing and justifiable cause demonstrated and shall be accompanied by an application extension fee as stated in the City of Hemet Fee Schedule. [OSHPD 1, 1R, 2, 4 & 5] Time limitation shall be in accordance with the California Administrative Code, Chapter 7, Section 7-129.
[A] 105.4 Validity of permit. The issuance or granting of a permit shall not be construed to be a permit for, or an approval of, any violation of any of the provisions of this code or of any other ordinance of the jurisdiction. Permits presuming to give authority to violate or cancel the provisions of this code or other ordinances of the jurisdiction shall not be valid. The issuance of a permit based on construction documents and other data shall not prevent the building official from requiring the correction of errors in the construction documents and other data. The building official is also authorized to prevent occupancy or use of a structure where in violation of this code or of any other ordinances of this jurisdiction.
[A] 105.5 Expiration. Every permit issued shall become invalid unless the work on the site authorized by such permit is commenced within 12 months after its issuance, or if the work authorized on the site by such permit is suspended or abandoned for a period of 180 days after the time the work commenced. Before such work can be recommenced after a permit expires, a new permit shall first be obtained to do so, and a fee therefore shall be one half the amount required for a new permit for such work, provided no changes have been made or will be made in the original plans and specifications for such work, and provided further that such suspension or abandonment has not exceeded one year. In order to renew action on a permit after expiration, the permittee shall pay a new full permit fee.
The building official is authorized to grant, in writing, one or more extensions of time, for periods of not more than 180 days per extension. Any permittee holding an unexpired permit may apply for an extension of the time within which work may commence under that permit when the permittee is unable to commence work within the time required. The extension shall be requested in writing prior to the permit expiring and show justifiable cause demonstrating that circumstances beyond the control of the permittee have prevented action from being taken. The extension request is also subject to a fee in accordance with the City of Hemet fee schedule.
105.5.2 Time limit on permitted construction. For any project for which a tentative and final tract map is not required, the maximum allowable time to complete construction for any work that requires a building permit including, but not limited to, any construction, reconstruction, rehabilitation, renovation, addition(s), modification(s), improvement(s), or alteration(s), shall be limited to three (3) years, unless an extension is granted in accordance with Section 105.5.3.
For building permits issued on or after July 1, 2021, the time limit to complete construction shall begin on the date of issuance of the first or original building permit. For building permits issued prior to July 1, 2021, the time limit to complete construction shall be three (3) years from July 1, 2021.
Final inspection and approval of the construction work by the City shall mark the date of construction completion for purposes of this section. Time limits set forth herein shall not be extended by issuance of a subsequent building permit(s) for the same project.
105.5.3 Extension of time limit to complete construction. The maximum allowable time to complete construction, as set forth in Section 105.5.2, may be extended as follows:
- Application for Extension to Building Official.
a) A property owner, or authorized agent of the property owner, may request an extension by filing with the Building Official, in writing and on a form provided by the Building Official, an application for extension which sets forth:
(i) the address of the project site;
(ii) the name of the applicant and property owner;
(iii) when the first or original building permit was issued;
(iv) the length of time extension requested, which shall not be greater than three hundred and sixty-five (365) calendar days;
(v) how many previous extensions have been granted;
(vi) the basis for the requested extension;
(vii) the new end project date if the application is approved;
(viii) a brief description of the improvements that are the subject of the application; and
(ix) any other information requested by the City.
b) Unless authorized by the Building Official in writing, an application for extension shall be submitted no later than forty-five (45) calendar days prior to the expiration of the building permit. The application for extension to the Building Official shall be accompanied the fee set forth in the City's master fee schedule.
c) Within forty-five (45) days of a request for extension, the Building Official may ministerially grant, conditionally grant or deny a request for extension for a period not to exceed three hundred sixty-five (365) calendar days. The Building Official shall only grant an extension if he/she determines adequate progress has been made towards completion of construction and the request for extension is necessary for its completion. The decision of the Building Official shall be final and non-appealable.
d) Notwithstanding subsection (c) above, for building permits issued prior to July 1, 2018, the Building Official ministerially grant, conditionally grant or deny a request for extension for a period not to exceed one hundred eighty (180) days. The Building Official shall only grant an extension if he/she determines adequate progress has been made towards completion of construction and the request for extension is necessary for its completion.
- Application for Additional Extension(s).
a) If construction of the project has not been completed within the timeframe authorized by the Building Official, a property owner, or authorized agent of the property owner, may request an additional extension by filing with the City Clerk, in writing and on a form provided by the City Clerk, an application for extension which sets forth:
(i) the address of the project site;
(ii) the name of the applicant and property owner;
(iii) when the first or original building permit was issued;
(iv) the length of time extension requested, which shall not be greater than one hundred and eighty (180) calendar days;
(v) how many previous extensions have been granted;
(vi) the basis for the requested extension;
(vii) the new end project date if the application is approved;
(viii) a brief description of the improvements that are the subject of the application; and
(ix) any other information requested by the City.
b) Unless authorized by the Building Official in writing, an application for extension shall be submitted no later than forty-five (45) calendar days prior to the expiration of the building permit.
c) An application for extension filed with the City Clerk shall be accompanied by a hearing and noticing fee identified in the City's master fee schedule.
- Scheduling and Noticing.
a) For an application for an additional extension set forth in subsection (2), a Hearing Officer, designated by the City Manager, shall hear and decide whether a second application for extension, or third application for extension, shall be granted, conditionally granted, or denied. The City Council shall hear and decide whether any additional application for extension shall be granted, conditionally granted, or denied. The applicable hearing body shall be referred to herein as the "review authority."
b) For any application for extension to be heard by a Hearing Officer, the City Manager shall appoint a Hearing Officer with the requisite qualifications and experience to consider the application for extension. The Hearing Officer shall not be a City employee and the employment, performance evaluation, compensation, and benefits of the Hearing Officer, if any, shall not be conditioned, either directly or indirectly, upon the outcome of any decision by the Hearing Officer.
Within seven (7) calendar days of the City Clerk's receipt of an application for extension, the City Manager or his/her designee shall notify the applicant of the name of the Hearing Officer. If the applicant wishes to challenge the designated Hearing Officer, the applicant shall have seven (7) calendar days from the date of service of the notice to submit to the City Manager a request, in writing, to disqualify the Hearing Officer, which sets forth the basis for disqualification. A Hearing Officer may only be disqualified for:
(i) bias;
(ii) prejudice;
(iii) a conflict of interest; or
(iv) a reason for which a judge may be disqualified after a showing of good cause under the laws of the State of California.
The City Manager will review any request for disqualification and make a decision as to whether a Hearing Officer shall be disqualified. The City Manager's decision shall be final. If the City Manager disqualifies a Hearing Officer, the City Manager shall designate a new Hearing Officer in accordance with the procedures in this subsection.
c) The applicant shall be notified of the time and place set for the hearing of the application, at least ten (10) calendar days prior to the date of the hearing. All hearings on an application to be heard by the review authority shall be noticed in the following manner:
(i) Mailed to property owners within three hundred (300) feet of the project site that is the subject of the application, at least ten (10) calendar days in advance of the hearing. The notice shall contain: the address of the project site; the length of time extension requested; the new end project date if the application is approved; the name of the applicant and property owner; a brief description of the improvements; the date, time, and place of the hearing; and a statement informing the person they have the ability to attend the hearing and provide comments; and
(ii) Posted by the applicant at the project site, that is the subject of the application, at least ten (10) calendar days before the scheduled hearing. The size, location and number of sign(s) shall be posted as determined by the City Manager or his/her designee. The applicant shall be responsible for maintaining the sign(s) in a satisfactory condition and shall remove all sign(s) within twenty-four (24) hours following the conclusion of the hearing.
The failure of any person or entity to receive notice given in compliance with this subsection shall not invalidate the actions of the applicable review authority.
- Conduct of Hearing.
a) A hearing shall be held at the date, time, and place for which notice was given.
b) The review authority shall only consider evidence and testimony, presented by the applicant or any other interested person, relevant to whether:
(i) special circumstances warrant an extension of time;
(ii) the failure to meet the time limit was caused by circumstances beyond the property owner's, applicant's or their contractor's control; and
(iii) any approval should contain conditions to ensure timely completion of the project in a manner that limits impacts on surrounding property owners. Any documents submitted by City staff shall constitute prima facie evidence of the respective facts contained in those documents.
c) The review authority may grant, or conditionally grant, up to a one hundred and eighty (180) calendar day extension, per application for extension, if it finds special circumstances warrant an extension of time or the failure to meet the time limit was caused by circumstances beyond the property owner's, applicant's or their contractor's control. If the review authority makes the findings to grant an extension, the review authority shall consider whether conditions are necessary to ensure timely completion of the project in a manner that limits impacts on surrounding property owners. The review authority shall deny the application if it cannot make the findings set forth in this subsection. Notwithstanding the above, for building permits issued prior to July 1, 2018, the review authority may grant, or conditionally grant, up to a ninety (90) calendar day extension, per application for extension, if it finds special circumstances warrant an extension of time or the failure to meet the time limit was caused by circumstances beyond the property owner's, applicant's or their contractor's control.
d) A hearing may be continued without further notice, provided the Hearing Officer or chair of the review authority announces the date, time, and place to which the hearing will be continued before the adjournment or recess of the hearing.
e) The review authority may announce a tentative decision and defer its action on a final decision until appropriate findings and/or conditions of approval have been prepared.
f) The review authority shall issue a written decision, setting forth its findings, and the decision shall be final and effective on the date the decision is made, unless otherwise specified by the review authority. The review authority shall provide the City Clerk with its final decision within three (3) calendar days of the date of decision and the City Clerk shall mail a copy of the final decision to the applicant within ten (10) calendar days of receipt of the final decision.
Judicial Proceeding. Nothing herein shall prohibit the Building Official from issuing a building permit or extending a building permit if the extension is a term of an enforceable settlement agreement between the City and the property owner or a term of a court order/judgment.
Judicial Review. The decision of the review authority shall not be appealable to any City body. A person shall not seek judicial review related to any application for extension until the person has first exhausted all administrative procedures.
City Council Report The City Manager or their designee shall prepare and submit a report to the City Council on a quarterly basis that describes those building permits that have been extended and which are expired under this Ordinance.
105.5.4 Correlation with Codes. Sections 105.5.2 or 105.5.3 limit the total time to complete construction and shall not relieve any person or entity from complying with any other applicable provision of federal, state or local law including, but not limited to, construction related laws adopted by the City.
[A] 105.6 Suspension or revocation. The building official is authorized to suspend or revoke a permit issued under the provisions of this code wherever the permit is issued in error or on the basis of incorrect, inaccurate or incomplete information, or in violation of any ordinance or regulation or any of the provisions of this code.
[A] 105.6.1. Unfinished buildings and structures. Whenever the building official determines by inspection that work in or on any building or structure for which a permits has been issued and the work started thereon has been suspended for a period 180 days or more, the owner of the property upon which such building or structure is located or other person or agent of control of said property, upon receipt of notice in writing from the building official to do so, shall, within 60 days from the date of such written notice, obtain a new permit to complete the required work and diligently pursue the work to completion or shall remove or demolish the building or structure within 90 days from the date of written notice.
[A] 105.7 Placement of permit. The building permit or copy shall be kept on the site of the work until the completion of the project.
Section 106 Floor and Roof Design Loads
[A] 106.1 Live loads posted. In commercial, institutional or industrial buildings, for each floor or portion thereof designed for live loads exceeding 50 psf (2.40 kN/m2), such design live loads shall be conspicuously posted by the owner or the owner's authorized agent in that part of each story in which they apply, using durable signs. It shall be unlawful to remove or deface such notices.
106.1.1 Snow load posting. [DSA-SS & DSA-SS/CC, OSHPD 1, 1R, 2, 4 & 5] Snow loads used in design shall be posted as for live loads.
106.1.2 Snow load posting. [DSA-SS & DSA-SS/CC] When design snow loads at exterior balconies, decks and other elevated walking surfaces exceed 50 psf, the design snow loads shall be posted as for live loads. When design roof (not ground) snow loads exceed 20 psf, the roof design snow loads for each roof level of the building shall similarly be conspicuously posted with signs stating the maximum design roof snow loads.
[A] 106.2 Issuance of certificate of occupancy. A certificate of occupancy required by Section 111 shall not be issued until the floor load signs, required by Section 106.1, have been installed.
[A] 106.3 Restrictions on loading. It shall be unlawful to place, or cause or permit to be placed, on any floor or roof of a building, structure or portion thereof, a load greater than is permitted by this code.
Section 107 Submittal Documents
[A] 107.1 General. Submittal documents consisting of construction documents, statement of special inspections, geotechnical report and other data shall be submitted in two or more sets with each permit application. The construction documents shall be prepared by a registered design professional where required by the statutes of the jurisdiction in which the project is to be constructed. Where special conditions exist, the building official is authorized to require additional construction documents to be prepared by a registered design professional or other qualified individual as determined by the building official.
Exception: The building official is authorized to waive the submission of construction documents and other data not required to be prepared by a registered design professional if it is found that the nature of the work applied for is such that review of construction documents is not necessary to obtain compliance with this code.
[A] 107.2 Construction documents. Construction documents shall be in accordance with Sections 107.2.1 through 107.2.8.
[A] 107.2.1 Information on construction documents. Construction documents shall be dimensioned and drawn upon suitable material. Electronic media documents are permitted to be submitted when approved by the building official. Construction documents shall be of sufficient clarity to indicate the location, nature and extent of the work proposed and show in detail that it will conform to the provisions of this code and relevant laws, ordinances, rules and regulations, as determined by the building official.
[A] 107.2.2 Fire protection system shop drawings. Shop drawings for the fire protection system(s) shall be submitted to indicate conformance to this code and the construction documents and shall be approved prior to the start of system installation. Shop drawings shall contain all information as required by the referenced installation standards in Chapter 9.
[A] 107.2.3 Means of egress. The construction documents shall show in sufficient detail the location, construction, size and character of all portions of the means of egress including the path of the exit discharge to the public way in compliance with the provisions of this code. In other than occupancies in Groups R-2, R-3, and I-1, the construction documents shall designate the number of occupants to be accommodated on every floor, and in all rooms and spaces.
[A] 107.2.4 Exterior wall envelope. Construction documents for all buildings shall describe the exterior wall envelope in sufficient detail to determine compliance with this code. The construction documents shall provide details of the exterior wall envelope as required, including flashing, intersections with dissimilar materials, corners, end details, control joints, intersections at roof, eaves or parapets, means of drainage, water-resistive membrane and details around openings.
The construction documents shall include manufacturer's installation instructions that provide supporting documentation that the proposed penetration and opening details described in the construction documents maintain the weather resistance of the exterior wall envelope. The supporting documentation shall fully describe the exterior wall system which was tested, where applicable, as well as the test procedure used.
[A] 107.2.5 Exterior balconies and elevated walking surfaces. Where balconies or other elevated walking surfaces are exposed to water from direct or blowing rain, snow, or irrigation, and the structural framing is protected by an impervious moisture barrier, the construction documents shall include details for all elements of the impervious moisture barrier system. The construction documents shall include manufacturer's installation instructions.
[A] 107.2.6 Site plan. The construction documents submitted with the application for permit shall be accompanied by a site plan showing to scale the size and location of new construction and existing structures on the site, distances from lot lines, the established street grades and the proposed finished grades and, as applicable, flood hazard areas, floodways, and design flood elevations; and it shall be drawn in accordance with an accurate boundary line survey. In the case of demolition, the site plan shall show construction to be demolished and the location and size of existing structures and construction that are to remain on the site or plot. The building official is authorized to waive or modify the requirement for a site plan when the application for permit is for alteration or repair or when otherwise warranted.
[A] 107.2.6.1 Design flood elevations. Where design flood elevations are not specified, they shall be established in accordance with Section 1612.3.1.
[A] 107.2.7 Structural information. The construction documents shall provide the information specified in Section 1603.
[A]107.2.8 Relocatable buildings. Construction documents for relocatable buildings shall comply with Section 3112.
[A] 107.3 Examination of documents. The building official shall examine or cause to be examined the accompanying submittal documents and shall ascertain by such examinations whether the construction indicated and described is in accordance with the requirements of this code and other pertinent laws or ordinances.
[A] 107.3.1 Approval of construction documents. When the building official issues a permit, the construction documents shall be approved, in writing or by stamp, as "Reviewed for Code Compliance." One set of construction documents so reviewed shall be retained by the building official. The other set shall be returned to the applicant, shall be kept at the site of work and shall be open to inspection by the building official or a duly authorized representative.
[A] 107.3.2 Previous approvals. This code shall not require changes in the construction documents, construction or designated occupancy of a structure for which a lawful permit has been heretofore issued or otherwise lawfully authorized, and the construction of which has been pursued in good faith within 180 days after the effective date of this code and has not been abandoned.
[A] 107.3.3 Phased approval. The building official is authorized to issue a permit for the construction of foundations or any other part of a building or structure before the construction documents for the whole building or structure have been submitted, provided that adequate information and detailed statements have been filed complying with pertinent requirements of this code. The holder of such permit for the foundation or other parts of a building or structure shall proceed at the holder's own risk with the building operation and without assurance that a permit for the entire structure will be granted.
[A] 107.3.4 Design professional in responsible charge. Where it is required that documents be prepared by a registered design professional, the building official shall be authorized to require the owner or the owner's authorized agent to engage and designate on the building permit application a registered design professional who shall act as the registered design professional in responsible charge. If the circumstances require, the owner or the owner's authorized agent shall designate a substitute registered design professional in responsible charge who shall perform the duties required of the original registered design professional in responsible charge. The building official shall be notified in writing by the owner or the owner's authorized agent if the registered design professional in responsible charge is changed or is unable to continue to perform the duties.
The registered design professional in responsible charge shall be responsible for reviewing and coordinating submittal documents prepared by others, including phased and deferred submittal items, for compatibility with the design of the building.
[A] 107.3.4.1 Deferred submittals. Deferral of any submittal items shall have the prior approval of the building official. The registered design professional in responsible charge shall list the deferred submittals on the construction documents for review by the building official.
Documents for deferred submittal items shall be submitted to the registered design professional in responsible charge who shall review them and forward them to the building official with a notation indicating that the deferred submittal documents have been reviewed and found to be in general conformance to the design of the building. The deferred submittal items shall not be installed until the deferred submittal documents have been approved by the building official. [OSHPD 1, 1R, 2, 4 & 5] Deferred submittals shall be in accordance with the California Administrative Code, Chapter 7, Section 7-126.
[A] 107.4 Amended construction documents. Work shall be installed in accordance with the approved construction documents, and any changes made during construction that are not in compliance with the approved construction documents shall be resubmitted for approval as an amended set of construction documents.
[A] 107.5 Retention of construction documents. One set of approved construction documents shall be retained by the building official for a period of not less than 180 days from date of completion of the permitted work, or as required by state or local laws.
Section 108 Temporary Structures and Uses
[A] 108.1 General. The building official is authorized to issue a permit for temporary structures and temporary uses. Such permits shall be limited as to time of service, but shall not be permitted for more than 180 days. The building official is authorized to grant extensions for demonstrated cause.
[A] 108.2 Conformance. Temporary structures and uses shall comply with the requirements in Section 3103.
[A] 108.3 Temporary power. The building official is authorized to give permission to temporarily supply and use power in part of an electric installation before such installation has been fully completed and the final certificate of completion has been issued. The part covered by the temporary certificate shall comply with the requirements specified for temporary lighting, heat or power in NFPA 70.
[A] 108.4 Termination of approval. The building official is authorized to terminate such permit for a temporary structure or use and to order the temporary structure or use to be discontinued.
Section 109 Fees
[A] 109.1 Payment of fees. A permit shall not be valid until the fees prescribed by law have been paid, nor shall an amendment to a permit be released until the additional fee, if any, has been paid. A permit shall be considered revoked if the payment of such permit is returned for insufficient funds.
[A] 109.2 Schedule of permit fees. On buildings, structures, electrical, gas, mechanical, and plumbing systems or alterations requiring a permit, a fee for each permit shall be paid as required, in accordance with the City of Hemet Fee Schedule.
[A] 109.2.1 Fee Not Specified. When a permit is required for buildings, structures, electrical, gas, mechanical and plumbing systems or alterations and a fee is not specifically specified in the City of Hemet Fee Schedule, a fee shall be charged based on the Fully Burdened Hourly Rate (FBHR) staff classification performing the inspection as set forth in the in the City of Hemet Fee Schedule or the actual cost to the jurisdiction by an outside consultant. The administration cost for processing such inspection shall be charged at the FBHR for the staff classification performing such work.
[A] 109.3 Building permit valuations. The applicant for a permit shall provide an estimated permit value at time of application. Permit valuations shall include total value of work, including materials and labor, for which the permit is being issued, such as electrical, gas, mechanical, plumbing equipment and permanent systems. If, in the opinion of the building official, the valuation is underestimated on the application, the permit shall be denied, unless the applicant can show detailed estimates to meet the approval of the building official. Final building permit valuation shall be set by the building official.
[A] 109.4 Work commencing before permit issuance. Any person who commences any work on a building, structure, electrical, gas, mechanical or plumbing system before obtaining the necessary permits shall be subject to a special investigation fee. The special investigation fee shall be double the permit fee. This fee shall be in addition to the required permit fees. The special investigation fee shall be made before a permit may be issued for such work.
[A] 109.5 Related fees. The payment of the fee for the construction, alteration, removal or demolition for work done in connection to or concurrently with the work authorized by a building permit shall not relieve the applicant or holder of the permit from the payment of other fees that are prescribed by law.
[A] 109.6 Refunds. The building official is authorized to establish a refund policy and may authorize refunding of any fee paid hereunder in the following situations:
Wherein a fee was erroneously paid or collected.
The building official may authorize refunding of not more than 75 percent of the permit application fee when an application for a permit is withdrawn or cancelled before any plan review is performed.
The building official may authorize refunding of not more than 75 percent of the permit fee when an application for permit is withdrawn or canceled before any inspections are performed.
The building official shall not authorize refunding of any fees paid except on written application filed by the original applicant not later than 180 days after the date of fee payment. Except for the refund of fees paid in error, no refund of permit or plan review fees shall be made where the permit or plan review fee paid is $100.00 or less.
[A] 109.7 Plan Review Fees. On buildings, structures, electrical, gas, mechanical and plumbing systems or alterations requiring a plan review, a fee for each plan review shall be paid as stated in the City of Hemet Fee Schedule. Upon submittal of construction documents, this fee shall be due and payable before the construction documents will be reviewed.
The plan review fees specified in this subsection are separate fees from the permit fees specified in Section 109.2 and are in addition to the permit fees.
When plans require three (3) or more reviews, are incomplete or changed so as to require additional plan review, an additional plan review fee shall be charged at the rate shown in the City of Hemet Fee Schedule or actual accrued fees by outside consultants to the City of Hemet.
[A] 109.8 Fee Not Specified. When a plan review is required for buildings, structures, electrical, gas, mechanical and plumbing systems or alterations and a fee is not specifically specified in the City of Hemet Fee Schedule, a fee shall be charged based on the Fully Burdened Hourly Rate (FBHR) staff classification performing the plan review as set forth in the City of Hemet Fee Schedule or the actual cost to the jurisdiction by an outside consultant. The administration cost for processing such plan review shall be charged at the FBHR for the staff classification performing such work.
Section 110 Inspections
[A] 110.1 General. Construction or work for which a permit is required shall be subject to inspection by the building official and such construction or work shall remain visible and able to be accessed for inspection purposes until approved. Approval as a result of an inspection shall not be construed to be an approval of a violation of the provisions of this code or of other ordinances of the jurisdiction. Inspections presuming to give authority to violate or cancel the provisions of this code or of other ordinances of the jurisdiction shall not be valid. It shall be the duty of the owner or the owner's authorized agent to cause the work to remain visible and able to be accessed for inspection purposes. Neither the building official nor the jurisdiction shall be liable for expense entailed in the removal or replacement of any material required to allow inspection.
[A] 110.2 Preliminary inspection. Before issuing a permit, the building official is authorized to examine or cause to be examined buildings, structures and sites for which an application has been filed.
[A] 110.3 Required inspections. The building official, upon notification, shall make the inspections set forth in Sections 110.3.1 through 110.3.10.
[A] 110.3.1 Footing and foundation inspection. Footing and foundation inspections shall be made after excavations for footings are complete and any required reinforcing steel is in place. For concrete foundations, any required forms shall be in place prior to inspection. Materials for the foundation shall be on the job, except where concrete is ready mixed in accordance with ASTM C94, the concrete need not be on the job.
[A] 110.3.2 Concrete slab and under-floor inspection. Concrete slab and under-floor inspections shall be made after in-slab or under-floor reinforcing steel and building service equipment, conduit, piping accessories and other ancillary equipment items are in place, but before any concrete is placed or floor sheathing installed, including the subfloor.
[A] 110.3.3 Lowest floor elevation. In flood hazard areas, upon placement of the lowest floor, including the basement, and prior to further vertical construction, the elevation certification required in Section 1612.5 shall be submitted to the building official.
[A] 110.3.4 Frame inspection. Framing inspections shall be made after the roof deck or sheathing, all framing, fire-blocking and bracing are in place and pipes, chimneys and vents to be concealed are complete and the rough electrical, plumbing, heating wires, pipes and ducts are approved.
110.3.4.1 [HCD 1] Moisture content verification. Moisture content of framing members shall be verified in accordance with the California Green Building Standards Code (CALGreen), Chapter 4, Division 4.5.
[A] 110.3.5 Lath, gypsum board and gypsum panel product inspection. Lath, gypsum board and gypsum panel product inspections shall be made after lathing, gypsum board and gypsum panel products, interior and exterior, are in place, but before any plastering is applied or gypsum board and gypsum panel product joints and fasteners are taped and finished.
Exception: Gypsum board and gypsum panel products that are not part of a fire-resistance-rated assembly or a shear assembly.
[A] 110.3.6 Weather-exposed balcony and walking surface waterproofing. Where balconies or other elevated walking surfaces are exposed to water from direct or blowing rain, snow or irrigation, and the structural framing is protected by an impervious moisture barrier, all elements of the impervious moisture barrier system shall not be concealed until inspected and approved.
Exception: Where special inspections are provided in accordance with Section 1705.1.1, Item 3.
[A] 110.3.7 Fire- and smoke-resistant penetrations. Protection of joints and penetrations in fire-resistance-rated assemblies, smoke barriers and smoke partitions shall not be concealed from view until inspected and approved.
[A] 110.3.8 Energy efficiency inspections. Inspections shall be made to determine compliance with Chapter 13 and shall include, but not be limited to, inspections for: envelope insulation R- and U-values, fenestration U-value, duct system R-value, and HVAC and water-heating equipment efficiency.
[A] 110.3.9 Other inspections. In addition to the inspections specified in Sections 110.3.1 through 110.3.7, the building official is authorized to make or require other inspections of any construction work to ascertain compliance with the provisions of this code and other laws that are enforced by the department of building safety.
[A] 110.3.10 Special inspections. For special inspections, see Chapter 17.
[A] 110.3.11 Final inspection. The final inspection shall be made after all work required by the building permit is completed.
[A] 110.3.11.1 Flood hazard documentation. If located in a flood hazard area, documentation of the elevation of the lowest floor as required in Section 1612.5 shall be submitted to the building official prior to the final inspection.
110.3.11.2 [HCD 1] Operation and maintenance manual. At the time of final inspection, a manual, compact disc, web-based reference or other media acceptable to the enforcing agency shall be placed in the building in accordance with the California Green Building Standards Code (CALGreen), Chapter 4, Division 4.4.
[A] 110.4 Inspection agencies. The building official is authorized to accept reports of approved inspection agencies, provided such agencies satisfy the requirements as to qualifications and reliability.
[A] 110.5 Inspection requests. It shall be the duty of the holder of the building permit or their duly authorized agent to notify the building official when work is ready for inspection. It shall be the duty of the permit holder to provide access to and means for inspections of such work that are required by this code.
[A] 110.6 Approval required. Work shall not be done beyond the point indicated in each successive inspection without first obtaining the approval of the building official. The building official, upon notification, shall make the requested inspections and shall either indicate the portion of the construction that is satisfactory as completed, or notify the permit holder or his or her agent wherein the same fails to comply with this code. Any portions that do not comply shall be corrected and such portion shall not be covered or concealed until authorized by the building official.
[A] 110.7 Re-Inspection Fee. When a requested inspection is not complete and requires a re-inspection by the City, the owner shall pay a re-inspection fee prior to the work being re-inspected. A re-inspection fee shall also be charged when the City is unable to gain access to the area of work to be inspected.
Section 111 Certificate of Occupancy
[A] 111.1 Use and occupancy. No building or structure shall be used or occupied, and no change in the existing occupancy classification of any building or structure or portion thereof shall be made until the Building Official has issued a certificate of occupancy for said building or structure in accordance with the provisions of Section 111.2. Issuance of a certificate of occupancy shall not be construed as an approval of a violation of the provisions of this code or of other ordinances of the City. Certificates presuming to give authority to violate or cancel the provisions of this code or other ordinances of the City shall not be valid.
[A] 111.2 Certificate issued. After the building official inspects the building or structure and finds no violations of the provisions of this code or other laws that are enforced by the department of building safety, the building official shall issue a certificate of occupancy that contains the following:
The building permit number.
The address of the structure.
The name and address of the owner or the owner's authorized agent.
A description of that portion of the structure for which the certificate is issued.
A statement that the described portion of the structure has been inspected for compliance with the requirements of this code for the occupancy and division of occupancy and the use for which the proposed occupancy is classified.
The name of the building official.
The edition of the code under which the permit was issued.
The use and occupancy, in accordance with the provisions of Chapter 3.
The type of construction as defined in Chapter 6.
The design occupant load.
If an automatic sprinkler system is provided, whether the sprinkler system is required.
Any special stipulations and conditions of the building permit.
[A] 111.3 Temporary occupancy. The building official is authorized to issue a temporary certificate of occupancy before the completion of the entire work covered by the permit, provided that such portion or portions shall be occupied safely. The building official shall set a time period during which the temporary certificate of occupancy is valid.
[A] 111.4 Revocation. The building official is authorized to, in writing, suspend or revoke a certificate of occupancy or completion issued under the provisions of this code wherever the certificate is issued in error, or on the basis of incorrect information supplied, or where it is determined that the building or structure or portion thereof is in violation of any ordinance or regulation or any of the provisions of this code.
[A] 111.5 Expiration. Every application for Certificate of Occupancy shall become invalid unless an inspection of the business is performed within 60 days after the application date. The building official is authorized to grant, in writing, one or more extension of time, for periods not more than 60 days each. The extension shall be requested in writing and justifiable cause demonstrated and be accompanied by an extension fee stated in the City of Hemet Fee Schedule. The provisions shall not be perceived as to allow a business to conduct business without first being issued a Certificate of Occupancy.
[A] 111.6 Certificate of Occupancy Fee. On buildings, structures, and areas requiring a certificate of occupancy under Section 111.1 a fee for each application shall be paid a required fee as stated in the City of Hemet Fee Schedule. Upon all required submittal documents, this fee shall be due and payable at time of application submittal.
Section 112 Service Utilities
[A] 112.1 Connection of service utilities. No person shall make connections from a utility, source of energy, fuel or power to any building or system that is regulated by this code for which a permit is required, until released by the building official.
[A] 112.2 Temporary connection. The building official shall have the authority to authorize the temporary connection of the building or system to the utility source of energy, fuel or power.
[A] 112.3 Authority to disconnect service utilities. The building official shall have the authority to authorize disconnection of utility service to the building, structure or system regulated by this code and the referenced codes and standards set forth in Section 101.4 in case of emergency where necessary to eliminate an immediate hazard to life or property or where such utility connection has been made without the approval required by Section 112.1 or 112.2. The building official shall notify the serving utility, and wherever possible the owner and occupant of the building, structure or service system of the decision to disconnect prior to taking such action. If not notified prior to disconnecting, the owner or occupant of the building, structure or service system shall be notified in writing, as soon as practical thereafter.
Section 113 Board of Appeals
[A] 113.1 General. In order to hear and decide appeals of orders, decisions or determinations made by the building official relative to the application and interpretation of this code, there shall be and is hereby created a board of appeals consisting of five members who are qualified by experience and training to pass upon matters pertaining to building construction and who are not employees of the jurisdiction. The Building official shall be an ex officio member and shall act as secretary to said Board, but shall have no vote upon any matter before the Board. The Board of Appeals shall be appointed by the City Council and shall hold office at its pleasure. The board shall adopt rules and procedures for conducting its business and shall render all decisions and findings in writing to the appellant with a duplicate copy to the building official.
[A] 113.2 Limitations on authority. An application for appeal shall be based on a claim that the true intent of this code or the rules legally adopted thereunder have been incorrectly interpreted, the provisions of this code do not fully apply or an equally good or better form of construction is proposed. The Board of Appeals shall have no authority relative to interpretation of administrative provisions of this Code, nor shall the board have authority to waive requirements of this code.
[A] 113.3 Appeal Hearing Fee. A fee, as provided in the current City of Hemet Fee Study shall accompany an application for a hearing before the Board of Appeals.
[A] 113.4 Special Purposes Members. For the purpose of appeals to the standards of Title 24 of the California Code of Regulations affecting accommodations for persons with disabilities, two (2) members shall be added who shall have a disability as defined by Section 202 of the California Building Code, 2022 Edition.
[A] 113.5 Notice of Appeal. Within the limitations provided for below, a person aggrieved by any order, act or determination of the building official or his subordinates, may appeal therefrom to the board of appeals. The appeal shall be taken by filing a written notice of appeal within 15 days, exclusive of holidays, after the date of making the order or determination or performing the act and by paying the appeal hearing fee. The notice of appeal must be in writing on a form provided by the city, and the notice must be filed and the fee paid at the office of the building official. The notice of appeal shall be sufficient to identify the act, order or determination appealed from and stated wherein it is erroneous or invalid. The operation of the act, order, or determination appealed from its suspended by the filing of the notice and appeal upon the determination of the appeal or termination of proceedings thereunder.
[A] 113.6 Hearing. The chairman of said board shall fix the time and place of hearing the appeal. The date of hearing shall not be less than 5 days nor more than 15 days after the date of filing the notice of appeal, and the hearing must not be postponed for more than ten days without good and sufficient cause. The board shall give written notice of the time and place of such hearing to the appellant and the officer or head of the department or division who act, order, or determination is appealed from. Witnesses may be sworn and examined and evidence produced by interested parties, who may appear in person or by attorney. The board shall keep a record of each appeal and proceeding thereunder. At the conclusion of the hearing, the board shall prepare and file its written findings and decision. The affirmative vote of two-thirds of the board is necessary to modify or reverse the order, act or determination appealed from. The failure of the board to file its findings and decisions within five days after termination of the hearing shall result in the automatic confirmation of the order, act or determination appealed from.
[A] 113.7 Final Decision. Any person aggrieved or affected by a decision of the board may appeal to the city council from such decision at any time within ten days after the date upon which the board announces its decision or loses jurisdiction. An appeal to the city council shall be taken by [filing] a letter of appeal with the building division and by concurrently paying to such division an appeal hearing fee in the amount established by the City of Hemet Fee Schedule. Such letter shall set forth the grounds upon which the appeal is based. Within 15 days after the receipt of the letter of appeal and the filing fee, the building division shall transmit to the city council the letter of appeal and the record of appeal at the board and the board's findings and decisions. The city council may firm, reverse, or modify the decision of the board.
[A] 113.8 Absence of Board of Appeals. [In] the event the board as established in Section 113.1 herein above should for any reason not be appointed by the city council or cease to exist after such appointment, the city council may serves as the board of appeals.
Section 114 Violations
[A] 114.1 Unlawful acts. It shall be unlawful for any person, firm or corporation to erect, construct, alter, extend, repair, move, remove, demolish or occupy any building, structure or equipment regulated by this code, or cause same to be done, in conflict with or in violation of any of the provisions of this code.
[A] 114.2 Notice of violation. The building official is authorized to serve a notice of violation or order on the person responsible for the erection, construction, alteration, extension, repair, moving, removal, demolition or occupancy of a building or structure in violation of the provisions of this code, or in violation of a permit or certificate issued under the provisions of this code. Such order shall direct the discontinuance of the illegal action or condition and the abatement of the violation.
[A] 114.3 Prosecution of violation. If the notice of violation is not complied with promptly, the building official is authorized to request the legal counsel of the jurisdiction to institute the appropriate proceeding at law or in equity to restrain, correct or abate such violation, or to require the removal or termination of the unlawful occupancy of the building or structure in violation of the provisions of this code or of the order or direction made pursuant thereto.
[A] 114.4 Violation penalties. Any person who violates a provision of this code or fails to comply with any of the requirements thereof or who erects, constructs, alters or repairs a building or structure in violation of the approved construction documents or directive of the building official, or of a permit or certificate issued under the provisions of this code, shall be subject to penalties as prescribed by law.
[A] 114.5 Violation Penalties. Any person, firm or corporation violating any of the provisions, regulations, requirements, additions, amendments and/or deletions of this code is guilty of a misdemeanor and the penalty for such a misdemeanor shall be set forth in Chapter 1-8 of the Hemet Municipal Code.
[A] 114.5.1 In addition thereto, violation of this code is declared to be a public nuisance, and the city attorney may institute necessary legal procedures for the abatement, removal or enjoinment thereof in the manner provided by law, or any take such other steps as he or she deems necessary to accommodate these ends.
Section 115 Stop Work Order
[A] 115.1 Authority. Where the building official finds any work regulated by this code being performed in a manner either contrary to the provisions of this code or dangerous or unsafe, the building official is authorized to issue a stop work order.
[A] 115.2 Issuance. The stop work order shall be in writing and shall be given to the owner of the property involved, the owner's authorized agent or the person performing the work. Upon issuance of a stop work order, the cited work shall immediately cease. The stop work order shall state the reason for the order and the conditions under which the cited work will be permitted to resume.
[A] 115.3 Unlawful continuance. Any person who shall continue any work after having been served with a stop work order, except such work as that person is directed to perform to remove a violation or unsafe condition, shall be subject to penalties as prescribed by law.
Section 116 Unsafe Structures and Equipment
[A] 116.1 Conditions. Structures or existing equipment that are or hereafter become unsafe, insanitary or deficient because of inadequate means of egress facilities, inadequate light and ventilation, or which constitute a fire hazard, or are otherwise dangerous to human life or the public welfare, or that involve illegal or improper occupancy or inadequate maintenance, shall be deemed an unsafe condition. Unsafe structures shall be taken down and removed or made safe, as the building official deems necessary and as provided for in this section. A vacant structure that is not secured against entry shall be deemed unsafe.
[A] 116.2 Record. The building official shall cause a report to be filed on an unsafe condition. The report shall state the occupancy of the structure and the nature of the unsafe condition.
[A] 116.3 Notice. If an unsafe condition is found, the building official shall serve on the owner, agent or person in control of the structure, a written notice that describes the condition deemed unsafe and specifies the required repairs or improvements to be made to abate the unsafe condition, or that requires the unsafe structure to be demolished within a stipulated time. Such notice shall require the person thus notified to declare immediately to the building official acceptance or rejection of the terms of the order.
[A] 116.4 Method of service. Such notice shall be deemed properly served if a copy thereof is (a) delivered to the owner personally; (b) sent by certified or registered mail addressed to the owner at the last known address with the return receipt requested; or (c) delivered in any other manner as prescribed by local law. If the certified or registered letter is returned showing that the letter was not delivered, a copy thereof shall be posted in a conspicuous place in or about the structure affected by such notice. Service of such notice in the foregoing manner upon the owner's agent or upon the person responsible for the structure shall constitute service of notice upon the owner.
[A] 116.5 Restoration. Where the structure or equipment determined to be unsafe by the building official is restored to a safe condition, to the extent that repairs, alterations or additions are made or a change of occupancy occurs during the restoration of the structure, such repairs, alterations, additions and change of occupancy shall comply with the requirements of Section 105.2.2 and the California Existing Building Code.
[A] 116.6 Intent. This section establishes standard place cards to be used to indicate the condition of a structure for continued occupancy. The section further authorizes the building official and his or her authorized representatives to post the appropriate place card at each entry point to a building or structure upon completion of a safety assessment.
[A] 116.7 Application of Provisions. The provisions of this section are applicable to all buildings and structures and all occupancies regulated by the city. The city council may extend the provisions as necessary.
[A] 116.8 Definitions. Safety Assessment means a visual, non-destructive examination of a building or structure for continued occupancy.
[A] 116.9 Place cards.
- The following are verbal descriptions of the official jurisdiction place cards to be used to designate the condition for continued occupancy of buildings or structures.
a. "INSPECTED - Lawful Occupancy Permitted" (Green Placard) is to be posted on any building or structure wherein no apparent structural hazard has been found. This placard is not intended to mean that there is no damage to the building or structure.
b. "RESTRICTED USE" (Yellow Placard) is to be posted on each building or structure that has been damage wherein the damage has resulted in some form of restriction to the continued occupancy. The individual who posts this placard will note in general terms the type of damage encountered and will clearly and concisely note the restrictions on continued occupancy.
c. "UNSAFE - Do Not Enter or Occupy" is to be posted on each building or structure that has been damaged such that continued occupancy poses a threat to life safety. Buildings or structures posted with this placard shall not be entered under any circumstance except as authorized in writing by the building official, or his or her authorized representative. Safety assessment teams shall be authorized to enter these buildings at any time. This placard is not to be used or considered as a demolition order. The individual who posts this placard will note in general terms the type of damage encountered.
The number of the ordinance codified in this section, the name of the jurisdiction, its address and phone number shall be permanently affixed to each placard.
Once it has been attached to a building or structure, a placard is not to be removed, altered or covered until done so by an authorized representative of the building official. It is unlawful for any person, firm or corporation to alter, remove, cover or deface a placard unless authorized pursuant to this section.
Section 117 Rubbish and Debris
117.1 Rubbish and Debris. Every person who constructs, alters, adds to, rehabilitates, places or repairs any building structure or building service equipment is subject to the following provision relating to rubbish and debris:
Collection and Disposal. During the process of constructing a building or structure, the construction site and the general area around the site shall be kept clear of rubbish and debris that result from the construction activities. Rubbish and debris shall not be allowed to accumulate on or be blown from the site and shall be placed inappropriate containers or removed from the construction site to an authorized disposal area. All containers shall be emptied periodically at an authorized disposal area so they will remain usable for the collection of rubbish and debris. When the building or structure is completed, a final cleanup of the site shall be conducted by the permittee.
Inspections. A permit holder shall not be entitled to, and no building inspector shall make an inspection of any phase of completed construction work, including the final inspection, if the construction site or general area thereof contains an accumulation of construction rubbish and debris. If a building inspector is unable to conduct a requested inspection because of an accumulation of rubbish and debris, a re-inspection fee may be assessed and required to be paid prior to a request for re-inspection is made. Failure to maintain a construction site clear of waste and other trash or debris, and in such a manner that is determined to constitute a health and safety hazard or constitutes a public nuisance, shall result in the issuance of a Stop Work order.
Rubbish and debris for the purpose of this section, includes, but is not limited to, stub ends of cut lumber, broken lumber and other scrap wood, scrap cement and plaster, scrap metal, paper cartons, wrappings, and similar materials that result from the process of constructing a building or structure."
Section 118 Working Hours
[A] 118 Working Hours. Construction activities shall be permitted between the hours of 6:00 a.m. and 6:00 p.m. during the months of June through September and between the hours of 7:00 a.m. and 6:00 p.m. during the months of October through May. Saturday construction shall be permitted between the hours of 7:00 a.m. and 6:00 p.m. Sunday construction shall be prohibited. Exceptions to these standards may be granted only by the City building official and/or the city council. This subsection is not intended to prohibit infrequent homeowner or small construction on the site of an existing home.
Subsection 1505.6 of Section 1505 of the California Building Code, 2022 Edition is amended to read as follows:
1505.6 Wood shingles and shakes. It shall be unlawful to install or cause to be installed, wood-shake or wood-shingle roofs on a building.
Exception: Any building which presently has wooden shakes or shingles may be re-roofed with a listed and approved Class A assembly with a rated wood shake or shingle. Approved fire-retardant-treated wood shakes and shingles are those complying with UBC Standard 15-3 or 15-4 which are impregnated by the full-cell vacuum-pressure process with fire-retardant chemicals, which have been qualified by UBC Standard 15-2 for use on Class A roofs.
Roof coverings on buildings located in a designated fire hazard area shall be rated as Class A. All wood-shingles and wood-shakes are prohibited in high fire hazard areas.
Subsection J110.1 of Section J110 of Appendix J of the California Building Code, 2022 Edition, is amended to read as follows:
J110.1 General. The faces of cut and fill slopes shall be prepared and maintained to control erosion and to provide stability.
Exception: Erosion control measures need not be provided on cut slopes not subject to erosion due to erosion-resistant character of materials.
Unless otherwise recommended in the approved soil engineering or engineering geology report, cut and fill slopes shall be planted in accordance with this section. The protection for the slopes shall be installed as soon as practicable and prior to calling for final permit approval.
Subsection J110.2 of Section J110 of Appendix J of the California Building Code, 2022 Edition, is amended to read as follows:
J110.2. Planting.
All slopes equal to or greater than three feet in vertical height shall be planted with drought-tolerant grass or ground cover in order to protect the slope from erosion and instability. Other slopes as deemed necessary by the building official shall also be planted.
Slopes exceeding 15 feet in vertical height shall be planted with drought-tolerant shrubs, spaced at no more than ten feet on center; or trees, spaced not to exceed 20 feet on center; or a combination of such shrubs and trees at equivalent spacing, in addition to a drought-tolerant grass or ground cover. Fifty percent of the total number of trees provided shall be of a drought-tolerant nature and a minimum five-gallon size. The plants selected and planting methods used shall be suitable for the soil and climatic conditions found on the site. The landscape design shall consider and locate plants in zones, according to their water needs. Plant materials and planting patterns may be varied upon the recommendations of a landscape architect or a slope control specialist with approval of the building official.
If a species other than those from the recommended plants list provided by the street and park supervisor is selected, a written statement shall be submitted by a landscape architect or slope control specialist certifying that the plant is drought-tolerant and suitable for erosion control and slope stabilization purposes. This statement must accompany the grading plan at the time of submittal. Plant material shall be allowed that is specifically identified as being drought-tolerant and suitable for erosion control and slope stabilization on an erosion control landscape plan signed by a registered landscape architect.
Section J110 of Appendix Chapter J, of the California Building Code, 2022 Edition, is amended by adding a new subsection J110.3 to read as follows:
J110.3 Plans.
- Erosion-control landscape plan requirements. Landscape plans shall be submitted for all slopes required to be planted. The landscape plan may be incorporated as part of the grading plan unless, in the opinion of the building official, the plan becomes too obscured to be effective. A landscape plan shall include:
a. A slope planting schedule that provides common and scientific names and specifications of all plants, including the names of all species, number and size of each tree and shrub and the spacing of each tree.
b. The location of the planting.
Erosion-control landscape plans involving more than four structures shall be prepared and signed by a registered landscape architect. This plan shall include the details necessary to complete the project including scope of work, materials to be used (seed mixtures, plant species listed by size, quantity, fertilizer used and rate of application), construction methods, maintenance and timetable for project completion.
Irrigation plan requirements. Except where approved by the building official, slopes required to be planted shall be provided with an approved system of irrigation designed to cover all portions of the slope and shall be of sufficient clarity to indicate the extent of work proposed. The irrigation system shall have zones which take into account the water requirements of the different types of plant species located in the zone and shall be adjusted to vary the water within the zone in accordance with the needs of the plant material. Care shall be taken to minimize runoff. Turf areas shall be irrigated separately from slope areas. The irrigation system provided shall make use of automatic timers, moisture sensors and low precipitation heads or emitters. The use of a drip type irrigation system is highly recommended wherever possible. Seasonal irrigation requirements of the plant species proposed shall be determined and recommendations provided as to the duration and frequency of irrigation. Specifications for proposed devices, size and type of pipe, flow and precipitation rates are to be included on the erosion-control landscape plan.
An approved backflow prevention device shall be installed in each irrigation system, which conforms to Chapter 6 of the Uniform Plumbing Code. Projects with access to or of sufficient size to economically justify the use of reclaimed water through use of a dual distribution system are encouraged to do so. Prior to building official approval, reclaimed water irrigation systems are subject to the approval of the state water quality control board.
If the planting requirements specified in Section 4 are waived by the building official, the requirements specified in this subsection may be waived.
- Sediment control plan. A sediment control plan shall be incorporated as part of the grading plan by a registered civil engineer or erosion control specialist. The plan shall minimize the deposition of sediment from rough graded lots and streets to adjacent properties.
a. Temporary sediment control measures may consist of the placement of straw or hay bales, gravel or earth-filled sandbags, gravel or earthen berms, filter fabric type fences and desilting basins with energy dissipaters.
b. The placement and design of sediment control measures shall be based on a hydrologic study of the site.
c. The sediment control plan shall specify the placement of the sediment control measures including spacing, alignment and typical detail.
d. In addition, all notes and related information shall be included on the sediment control plan.
e. The sediment control plan shall be submitted and approved prior to the issuance of a grading permit.
Section J110 of Appendix Chapter J, of the California Building Code, 2022 Edition, is amended by adding a new subsection J110.4 to read as follows:
J110.4 Planting method. Planting shall commence as soon as slopes are completed on any portion of the site and shall provide for rapid short-term coverage of the slope as well as long-term permanent coverage. Minimum requirements shall include:
Planting holes. Planting holes shall be excavated twice as wide as the diameter and two inches less than the depth of the root ball of the plant. The planting holes shall be backfilled with a mixture of native soil, slowly decomposing organic matter and an appropriate fertilizer. The construction of a watering basin at the base of all trees and shrubs at a distance encompassing the drip line is recommended in order to encourage deep percolation of irrigation. The application of mulch to the surface area of the watering basin will help minimize the amount of irrigation lost to evaporation. Commercially prepared mulch, wood chips, grass clippings or a combination of vegetal matter may be used in this regard.
Staking. Each tree shall be staked in order to anchor the root system and to support the trunk in an upright position. Stake material shall be of adequate dimension and length to support the tree. Ties used for tying the tree to the stake shall have a broad surface to minimize rubbing or girdling and have some elasticity. In lieu of stakes, a three-wire, tie-down system may be used.
Ground cover spacing. Ground covers are to be spaced in such a manner that 100 percent coverage of the planted slope will be achieved in as short a time as possible.
The finish grading and drainage, provided on the adjacent all-planted slopes, shall promote healthy plant growth and minimize erosion and runoff.
Exceptions: Waiver of planting requirements. Waiver of planting and irrigation requirements may be approved by the building official if found to be unreasonable or unnecessary for one of the following reasons:
The erosion resistant character of material composing the slopes makes planting unnecessary.
The unavailability of water making irrigation either impossible or impractical.
Slope heights are less than those requiring planting by subsection (a) of this section.
Section J110 of Appendix Chapter J, of the California Building Code, 2022 Edition, is amended by adding a new subsection J110.5 to read as follows:
J110.5 Planting maintenance. All vegetation planted for erosion control shall be maintained in a healthy, vigorous condition. Maintenance of slopes shall include watering, weeding and restoration of any plant material that may die. Slopes that are affected by the future installation of walls, fences, swimming pools or any other building must be properly replanted upon the completion of subsequent projects.
Section J110 of Appendix Chapter J, of the California Building Code, 2022 Edition, is amended by adding a new subsection J110.6 to read as follows:
J110.6 Bonding. A performance bond for all projects involving more than four structures and such other projects, as may be determined by the building official, shall be required for erosion control remedies, at the time the landscaping plan is approved. The bond shall be released upon approval of the final planting inspection but may be earlier released in the discretion of the building official.
Section J110.7 of Appendix Chapter J, of the California Building Code, 2022 Edition, is amended by adding a new subsection J110.7 to read as follows:
J110 Final planting inspection. A final planting inspection shall be required for all building sites requiring planting. For building sites not requiring a performance bond, the final planting inspection shall be approved prior to the building permit final inspection. Any required irrigation system and all planting shall be installed at the time of the final planting inspection. A [function test] of the irrigation system may be required. For building sites requiring a performance bond, slope certification required by the next subsection shall be approved prior to the building permit final inspection. The final planting inspection shall be performed at the end of the one-year bond period.
Section J110 of Appendix Chapter J, of the California Building Code, 2022 Edition, is amended by adding a new subsection J110.8 to read as follows:
J110.8 Slope verification. A site inspection shall be performed by the responsible landscape architect to assure compliance with the approved plans and to perform a functional test of the sprinkler system. Said landscape architect shall verify in writing to the building official that the soils, additives, amendments, weed control, planting of the slopes and the installation of the irrigation system comply to the approved plans and to all the provisions of this section. Verification to contain a statement as to grow stock vitality.
(Ord. No. 2003, § 3(Exh. A), 11-8-22; Ord. No. 2021, § 2, 10-10-23)
Secs. 14-42—14-44. - Reserved.¶