Skip to content

Earlier editions: 2026-09

Title 15 — BUILDINGS AND CONSTRUCTION

Colton Municipal Code Ch. 15.11 Green Building Code

Colton Municipal Code · 2026-10 edition · updated 2026-10-04 · Colton

Cite as: Colton Municipal Code Chapter 15.11 · Text as of 2026-10-04

Footnotes:

--- (7) ---

Editor's note— Ord. No. O-12-25, § 9, adopted Dec. 16, 2025, repealed the former Ch. 15.11, § 15.11.010, and enacted a new Ch. 15.11 as set out herein. The former Ch. 15.11 pertained to similar subject matter and derived from Ord. No. O-04-15, § 9, 4-7-2015; Ord. No. O-26-16, § 9, 12-20-2016; Ord. No. O-15-19, § 9, 11-19-2019; Ord. No. O-14-22, § 9, 12-6-2022.

15.11.10 - Section 4. 106.4 and 5. 106.5.3 Electric Vehicle Charging Stations.

Sections: 15.11.010

15.11.010 is hereby added to Title 15 of the Colton Municipal Code to read as follows:

Section 15.11.010: Expedited, streamlined permitting process for electric vehicle charging stations as required by Government Section 65850.7.

15.11.010. Intent and purpose

The intent and purpose of this section is to adopt an expedited, streamlined electric vehicle charging systems to achieve timely and cost-effective installations of electric vehicle charging systems. This Chapter is designed to encourage the use of electric vehicle charging systems by removing unreasonable barriers, minimizing costs to property owners and the City, and expanding the ability of property owners to install electric vehicle charging systems. This section allows the city to achieve these goals while protecting the public health and safety.

15.11.020. Expedited Review and Process

Consistent with Government Code Section 65850.7, the Building Official shall implement an expedited administrative permit review process for electric vehicle charging stations and adopt a checklist of all requirements with which electric vehicle charging stations shall comply with in order to be eligible for expedited review. The expedited administrative permit review process and checklist may refer to the recommendations in the checklist prescribed by the most current version of the "Plug-In Electric Vehicle Infrastructure Permitting Checklist" of the "Zero-Emission Vehicles in California: Community Readiness Guidebook" published by the Governor's Office of Planning and Research. The City's adopted checklist shall be published on the City's website.

15.11.030. Electronic Submittals

Consistent with Government Code Section 65850.7, the Building Official shall allow for electronic submittal of permit applications covered by this Ordinance and associated supporting documentation. In accepting such permit applications, the Building Official shall also accept electronic signatures on all forms, applications, and other documentation in lieu of a wet signature by any applicant.

15.11.040. Association Approval

Consistent with Government Code Section 65850.7, the Building Official shall not condition the approval for any electric vehicle charging station permit on the approval of such a system by an association, as that term is defined by Civil Code Section 4080.

15.11.040. Permit Application Processing

A permit application that satisfies the information requirements in the City's adopted checklist shall be deemed complete and be promptly processed. Upon confirmation by the Building Official that the permit application and supporting documents meets the requirements of the City adopted checklist, and is consistent with all applicable laws, the Building Official shall, consistent with Government Code Section 65850.7, approve the application and issue all necessary permits. Such approval does not authorize an applicant to energize or utilize the electric vehicle charging station until approval is granted by the City. If the Building Official determines that the permit application is incomplete, he or she shall issue a written correction notice to the applicant, detailing all deficiencies in the application and any additional information required to be eligible for expedited permit issuance.

15.11.050. Technical Review

It is the intent of this Section to encourage the installation of electric vehicle charging stations by removing obstacles to permitting for charging stations so long as the action does not supersede the Building Official's authority to address higher priority life-safety situations. If the Building Official makes a finding based on substantial evidence that the electric vehicle charging station could have a specific adverse impact upon the public health or safety, as defined in Government Code 65850.7, the City may require the applicant to apply for a use permit

15.11.010 Section [Reserved for future amendments.]

(Ord. No. O-12-25, § 9, 12-16-2025)

Exceptions & meaning →

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — Colton Municipal Code

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.