Chapter 39 — PROCESSING AND EXTRACTION FACILITIES
Section 3904 — SYSTEMS AND EQUIPMENT
2025 California Fire Code (Title 24, Part 9) · 2025 edition · updated 2026-07-29 · California
Italicized text is a California amendment to the model code, as printed in the official publication.
3904.1 General requirements. ¶
Systems and equipment used with the processing or extraction of oils and products from plants shall comply with Sections 3904.2 through 3904.2.2.3 and Section 5003.2, and other applicable provisions of this code, the California Build- ing Code and the California Mechanical Code .
3904.2 Systems and equipment. ¶
Systems or equipment used for the extraction or processing of oils from plant material shall comply with Section 3904.2.1 or 3904.2.2.
3904.2.1 Listings. Systems or equipment used for the extraction of oils from plant material shall be listed and labeled in accordance with UL 1389 and installed in accordance with the listing and the manufacturer’s installation instructions.
3904.2.2 Approvals. Systems or equipment used for the extraction of oils from plant material shall be approved for the specific use. The system shall be reviewed by a registered design professional. The registered design professional shall review and consider any information provided by the system’s designer or manufacturer. A technical report in accordance with Section 3904.2.2.1 shall be prepared and submitted to the fire code official for review and approval. The firm or individual preparing the technical report shall be approved by the fire code official prior to performing the analysis.
3904.2.2.1 Technical report. A technical report, reviewed and approved by the fire code official as required by Section 3904.2, is required prior to the equipment being located or installed at the facility. The report shall be prepared by a registered design professional or other professional approved by the fire code official.
3904.2.2.2 Report content. The technical report shall contain all of the following:
Manufacturer information.
Preparer of record of the technical report.
Date of review and report revision history.
Signature page, including all of the following: 4.1. Author of the report. 4.2. Date of report. 4.3. Date and signature of registered design professional of record performing the design or peer review.
Model number of the item evaluated. If the equipment is provided with a serial number, the serial number shall be included for verification at the time of site inspection.
Methodology of the design or peer review process used to determine minimum safety requirements. Methodology shall consider the basis of design, and shall include a code analysis and code path to demonstrate whether specific codes or standards are applicable.
Equipment description. A list of every component and subassembly, such as fittings, hose, quick disconnects, gauges, site glass, gaskets, valves, pumps, vessels, containers and switches, of the system or equipment, indicating the manufacturer, model number, material and solvent compatibility. Manufacturer’s data sheets shall be provided.
A general flow schematic or general process flow diagram of the process. Post-processing or winterization shall be included in this diagram. Primary components of the process equipment shall be identified and match the equipment list required in Item 7. Operating temperatures, pressures and solvent state of matter shall be identified in each primary step or component. A piping and instrumentation diagram (PID or P&ID) shall be provided.
Analysis of the vessel(s) if pressurized beyond standard atmospheric pressure. Analysis shall include purchased and fabricated components.
Structural analysis for the frame system supporting the equipment.
Process safety analysis of the extraction system, from the introduction of raw product to the end of the extraction
process. 12. Comprehensive process hazard analysis considering failure modes and points of failure throughout the process. The process hazard analysis shall include a review of emergency procedure information provided by the manufacturer of the equipment or process and not that of the facility, building or room. 13. Review of the assembly instructions, operational and maintenance manuals provided by the manufacturer. 14. List of references used in the analysis.
3904.2.2.3 Site inspection. Prior to operation of the extraction equipment, where required by the fire code official, the engineer of record or approved professional, as approved in Section 3904.2, shall inspect the site of the extraction process once equipment has been installed for compliance with the technical report and the building analysis. The engineer of record or approved professional shall provide a report of findings and observations of the site inspection to the fire code official prior to the approval of the extraction process. The field inspection report authored by the engineer of record shall include the serial number of the equipment used in the process and shall confirm that the equipment installed is the same model and type of equipment identified in the technical report.
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸ Contents — 2025 California Fire Code (Title 24, Part 9)
- Chapter 1 — ADMINISTRATION
- Chapter 2 — DEFINITIONS
- Chapter 3 — GENERAL REQUIREMENTS
- Chapter 4 — EMERGENCY PLANNING AND PREPAREDNESS
- Chapter 5 — FIRE SERVICE FEATURES
- Chapter 6 — BUILDING SERVICES AND SYSTEMS
- Chapter 7 — FIRE AND SMOKE PROTECTION FEATURES
- Chapter 8 — INTERIOR FINISH, DECORATIVE MATERIALS AND FURNISHI…
- Chapter 9 — FIRE PROTECTION AND LIFE SAFETY SYSTEMS
- Chapter 10 — MEANS OF EGRESS
- Chapter 11 — CONSTRUCTION REQUIREMENTS FOR EXISTING BUILDINGS
- Chapter 12 — ENERGY SYSTEMS
- Chapter 20 — AVIATION FACILITIES
- Chapter 21 — DRY CLEANING
- Chapter 22 — COMBUSTIBLE DUST-PRODUCING OPERATIONS
- Chapter 23 — MOTOR FUEL-DISPENSING FACILITIES AND REPAIR GARAGES
- Chapter 24 — FLAMMABLE FINISHES
- Chapter 25 — FRUIT AND CROP RIPENING
- Chapter 26 — FUMIGATION AND INSECTICIDAL FOGGING
- Chapter 27 — SEMICONDUCTOR FABRICATION FACILITIES
- Chapter 28 — LUMBER YARDS AND AGRO-INDUSTRIAL, SOLID BIOMASS A…
- Chapter 29 — MANUFACTURE OF ORGANIC COATINGS
- Chapter 30 — INDUSTRIAL OVENS
- Chapter 31 — TENTS, TEMPORARY SPECIAL EVENT STRUCTURES AND OTH…
- Chapter 32 — HIGH-PILED COMBUSTIBLE STORAGE
- Chapter 33 — FIRE SAFETY DURING CONSTRUCTION AND DEMOLITION
- Chapter 34 — TIRE REBUILDING AND TIRE STORAGE
- Chapter 35 — WELDING AND OTHER HOT WORK
- Chapter 36 — MARINAS
- Chapter 37 — COMBUSTIBLE FIBERS
- Chapter 38 — RESERVED
-
▸ Chapter 39 — PROCESSING AND EXTRACTION FACILITIES
- Chapter 40 — STORAGE OF DISTILLED SPIRITS AND WINES
- Chapter 41 — TEMPORARY HEATING AND COOKING OPERATIONS
- Chapter 48 — MOTION PICTURE AND TELEVISION PRODUCTION STUDIO S…
- Chapter 49 — REQUIREMENTS FOR WILDLAND-URBAN INTERFACE FIRE AR…
- Chapter 50 — HAZARDOUS MATERIALS—GENERAL PROVISIONS
- Chapter 51 — AEROSOLS
- Chapter 52 — RESERVED
- Chapter 53 — COMPRESSED GASES
- Chapter 54 — CORROSIVE MATERIALS
- Chapter 55 — CRYOGENIC FLUIDS
- Chapter 56 — EXPLOSIVES AND FIREWORKS
- Chapter 57 — FLAMMABLE AND COMBUSTIBLE LIQUIDS
- Chapter 58 — FLAMMABLE GASES AND FLAMMABLE CRYOGENIC FLUIDS
- Chapter 59 — FLAMMABLE SOLIDS
- Chapter 60 — HIGHLY TOXIC AND TOXIC MATERIALS
- Chapter 61 — LIQUEFIED PETROLEUM GASES
- Chapter 62 — ORGANIC PEROXIDES
- Chapter 63 — OXIDIZERS, OXIDIZING GASES AND OXIDIZING CRYOGENI…
- Chapter 64 — PYROPHORIC MATERIALS
- Chapter 65 — PYROXYLIN (CELLULOSE NITRATE) PLASTICS
- Chapter 66 — UNSTABLE (REACTIVE) MATERIALS
- Chapter 67 — WATER-REACTIVE SOLIDS AND LIQUIDS
- Chapter 80 — REFERENCED STANDARDS
- Appendix Chapter 4 — SPECIAL DETAILED REQUIREMENTS BASED ON US…
- Appendix A — BOARD OF APPEALS
- Appendix B — FIRE-FLOW REQUIREMENTS FOR BUILDINGS
- Appendix BB — FIRE-FLOW REQUIREMENTS FOR BUILDINGS
- Appendix C — FIRE HYDRANT LOCATIONS AND DISTRIBUTION
- Appendix CC — FIRE HYDRANT LOCATIONS AND DISTRIBUTION
- Appendix D — FIRE APPARATUS ACCESS ROADS
- Appendix E — HAZARD CATEGORIES
- Appendix F — HAZARD RANKING
- Appendix G — CRYOGENIC FLUIDS—WEIGHT AND VOLUME EQUIVALENTS
- Appendix H — HAZARDOUS MATERIALS MANAGEMENT PLANS AND HAZARDOU…
- Appendix I — FIRE PROTECTION SYSTEMS—NONCOMPLIANT CONDITIONS
- Appendix J — BUILDING INFORMATION SIGN
- Appendix K — CONSTRUCTION REQUIREMENTS FOR EXISTING AMBULATORY…
- Appendix L — REQUIREMENTS FOR FIREFIGHTER AIR REPLENISHMENT SY…
- Appendix M — HIGH-RISE BUILDINGS—RETROACTIVE AUTOMATIC SPRINKL…
- Appendix N — INDOOR TRADE SHOWS AND EXHIBITIONS
- Appendix O — VALET TRASH AND RECYCLING COLLECTION IN GROUP R-2…
- Appendix P — TEMPORARY HAUNTED HOUSES, GHOST WALKS AND SIMILAR…
- Appendix Q — COMMUNITY WILDLAND-URBAN INTERFACE (WUI) FIRE HAZ…