Section 2105A
California Building Code (Title 24, Part 2) · 2019 edition · updated 2026-09-12 · California
Italicized text is a California amendment to the model code, as printed in the official publication.
QUALITY ASSURANCE
2105 A .1 General. A quality assurance program shall be used to ensure that the constructed masonry is in compliance with the approved construction documents.
The quality assurance program shall comply with the inspection and testing requirements of Chapter 17 A, TMS 602 and Sections 2105A.2 through 2105A.4.
2105A.2 Compressive strength,¶
f ′ m . The specified compres- sive strength, f ′ m, assumed in design shall be 2,000 psi (13.79 MPa) for all masonry construction using materials and details of construction required herein. Testing of the con- structed masonry shall be provided in accordance with Sec- tion 2105A.5 or 2105A.6.
Exception: Subject to the approval of the enforcement agency, higher values of f ′ m may be used in the design of reinforced grouted masonry and reinforced hollow-unit masonry. The approval shall be based on prism test results submitted by the architect or engineer which demonstrate the ability of the proposed construction to meet prescribed performance criteria for strength and stiffness. The design shall take into account the mortar joint depth. In no case shall the f ′ m assumed in design exceed 3,000 psi (20.7 MPa).
Where an f ′ m greater than 2,000 psi (13.79 MPa) is approved, the architect or structural engineer shall estab- lish a method of quality control of the masonry construc- tion acceptable to the enforcement agency which shall be described in the contract specifications. Compliance with the requirements for the specified strength of constructed masonry shall be provided using prism test method in accordance with Section 2105A.5. Substantiation for the
Copyright © 2019 ICC. ALL RIGHTS RESERVED. Accessed by Kevin Day (kevin.day@dgs.ca.gov), (California Building Standards Commission) Order Number #100735044 on Jul 24, 2019 03:54 PM (PDT) pursuant to License Agreement with ICC. No further reproduction or distribution authorized. Single user only, copying and networking prohibited. ANY UNAUTHORIZED REPRODUCTION OR DISTRIBUTION IS A VIOLATION OF THE FEDERAL COPYRIGHT ACT AND THE LICENSE AGREEMENT, AND SUBJECT TO CIVIL AND CRIMINAL PENALTIES THEREUNDER.
100735044
MASONRY
3. Sampled in such a manner as to exclude any masonry unit webs, mortar joint, or reinforcing steel. If all cells contain reinforcement, alternate core locations or means to detect void or delami- nation shall be selected by the registered design professional and approved by the building official.
Visual examination of all cores shall be made by an approved agency and the condition of the cores reported as required by the California Administrative Code. Shear test both joints between the grout core and the outside wythes or face shell of the masonry 28 days after grouting of the sample area using a shear test apparatus acceptable to the enforce- ment agency. Core samples shall not be soaked before test- ing. Core samples to be tested shall be stored in sealed plastic bags or non-absorbent containers immediately after coring and for at least 5 days prior to testing. The average unit shear value for each pair of cores (4 shear tests) from each 5,000 square feet of wall area (or less) on the cross sec- tion of core shall not be less than 2.5 √ f ′ m psi.
l not be soaked before test-_ ing. Core samples to be tested shall be stored in sealed plastic bags or non-absorbent containers immediately after coring and for at least 5 days prior to testing. The average unit shear value for each pair of cores (4 shear tests) from each 5,000 square feet of wall area (or less) on the cross sec- tion of core shall not be less than 2.5 √ f ′ m psi.
All cores shall be submitted to an approved agency for examination, even where the core specimens failed during the cutting operation. The approved agency shall report the loca- tion where each core was taken, the findings of their visual examination of each core, identify which cores were selected for shear testing, and the results of the shear tests.
Exceptions:
1. Core sampling and testing is not required for non- bearing nonshear masonry walls, not exceeding a total wall height of 12 feet above top of foundation, built with single-wythe hollow unit concrete masonry that attaches opposite face shells using webs cast as single unit, when designed using an f ′ m not exceeding 2,000 psi (13.79 MPa).
2. An infrared thermographic survey or other nonde- structive test procedures, shall be permitted to be approved as an alternative system to detect voids or delamination in grouted masonry in-lieu of core sampling and testing. [OSHPD 1 & 4] Infrared ther- mographic surveys or other nondestructive test pro- cedures shall also include core tests with a minimum of two cores taken from each building for each 10,000 square feet (930 m 2 ) of the wall.
2105A.5 Masonry prism method testing.¶
Prism test method performed prior to the start or during construction shall be in accordance with TMS 602 Section 1.4 B.3. Prism test method performed on constructed walls shall be in accordance with TMS 602 Section 1.4 B.4.
2105A.6 Unit strength method testing.¶
Unit strength method testing shall be performed in accordance with TMS 602 Sec- tion 1.4 B.2.
Get a plain-English answer with a citation back to this text.
Ask AI about this code▸Contents — California Building Code (Title 24, Part 2)
- Chapter 2 — DEFINITIONS AND ABBREVIATIONS
- Appendix G — FLOOD-RESISTANT
- Appendix L — EARTHQUAKE RECORDING
- Appendix M — TSUNAMI-GENERATED
- Chapter 1 — SCOPE AND ADMINISTRATION
- Chapter 3 — OCCUPANCY CLASSIFICATION AND USE
- Chapter 4 — SPECIAL DETAILED REQUIREMENTS BASED
- Chapter 5 — GENERAL BUILDING HEIGHTS AND AREAS
- Chapter 6 — TYPES OF CONSTRUCTION
- Chapter 7 — FIRE AND SMOKE PROTECTION FEATURES
- Chapter 7A — MATERIALS AND CONSTRUCTION
- Chapter 8 — INTERIOR FINISHES
- Chapter 9 — FIRE PROTECTION AND LIFE SAFETY SYSTEMS
- Chapter 10 — MEANS OF EGRESS
- Chapter 11A — HOUSING ACCESSIBILITY
- Chapter 11B — ACCESSIBILITY TO PUBLIC BUILDINGS, PUBLIC ACCOMM…
- Chapter 12 — INTERIOR ENVIRONMENT
- Chapter 14 — EXTERIOR WALLS
- Chapter 15 — ROOF ASSEMBLIES AND ROOFTOP STRUCTURES
- Chapter 16 — STRUCTURAL DESIGN
- Chapter 16A — STRUCTURAL DESIGN
- Chapter 17 — SPECIAL INSPECTIONS AND TESTS
- Chapter 18 — SOILS AND FOUNDATIONS
- Chapter 19 — CONCRETE
- Chapter 20 — ALUMINUM
▸Chapter 21 — MASONRY
Overview- Section 2102
- Section 2101
- Section 2103
- Section 2104
- Section 2105
- Section 2106
- Section 2107
- Section 2108
- Section 2109
- Section 2110
- Section 2111
- Section 2112
- Section 2113
- Section 2114
- Section 2115
- Section 2102A
- Section 2103A
- Section 2101A
- Section 2104A
- Section 2105A
- Section 2106A
- Section 2107A
- Section 2111A
- Section 2108A
- Section 2109A
- Section 2110A
- Section 2112A
- Section 2113A
- Section 2114A
- Chapter 22 — STEEL
- Chapter 23 — WOOD
- Chapter 24 — GLASS AND GLAZING
- Chapter 25 — GYPSUM BOARD, GYPSUM PANEL PRODUCTS AND PLASTER
- Chapter 26 — PLASTIC
- Chapter 27 — ELECTRICAL
- Chapter 28 — MECHANICAL SYSTEMS
- Chapter 30 — ELEVATORS AND CONVEYING SYSTEMS
- Chapter 31 — SPECIAL CONSTRUCTION
- Chapter 31B — PUBLIC POOLS
- Chapter 31C — RADIATION
- Chapter 31D — FOOD ESTABLISHMENTS
- Chapter 31F — MARINE OIL TERMINALS
- Chapter 32 — ENCROACHMENTS INTO THE PUBLIC RIGHT-OF-WAY
- Chapter 33 — SAFEGUARDS DURING CONSTRUCTION
- Chapter 35 — REFERENCED STANDARDS
- Appendix A — EMPLOYEE QUALIFICATIONS
- Appendix B — BOARD OF APPEALS
- Appendix C — GROUP U – AGRICULTURAL BUILDINGS
- Appendix D — FIRE DISTRICTS
- Appendix F — RODENTPROOFING
- Appendix H — SIGNS
- Appendix I — PATIO COVERS
- Appendix J — GRADING
- Appendix K — GROUP R-3 AND GROUP R-3.1 OCCUPANCIES
- Appendix N — REPLICABLE BUILDINGS
- Appendix O — EMERGENCY HOUSING