Victorville Municipal Code Art. 20 Electric Vehicle Charging Station Streamlined Permitting Process

Victorville Municipal Code · 2026-10 edition · updated 2026-10-04 · Victorville

Cite as: Victorville Municipal Code Article 20 · Text as of 2026-10-04

Sec. 16-5.20.010: - Purpose

As required by State Law, the purpose of this Article is to create an expedited, streamlined electric vehicle charging station permitting process that complies with AB 1236 (Chapter 598, Statutes 2015, Cal. Government Code § 65850.7) to achieve timely and cost-effective installations of electric vehicle charging stations.

(Ord. No. 2374, § 6, 10-3-17)

Exceptions & meaning →

Sec. 16-5.20.020: - Definitions

For the purposes of this Article of the Development Code, the following definitions shall apply:

(a) "Electric vehicle charging station" or "charging station" means any level of electric vehicle supply equipment station that is designed and built in compliance with Article 625 of the California Electrical Code, as it reads on the effective date of this Chapter, and delivers electricity from a source outside an electric vehicle into a plug-in electric vehicle.

(b) "Specific, adverse impact" means a significant, quantifiable, direct, and unavoidable impact, based on objective, identified, and written public health or safety standards, policies, or conditions as they existed on the date the application was deemed complete.

(c) "Electronic submittal" means the utilization of one or more of the following:

(1) Electronic mail or email.

(2) The internet.

(3) Facsimile.

(Ord. No. 2374, § 6, 10-3-17)

Exceptions & meaning →

Sec. 16-5.20.030: - Expedited permitting process

Consistent with Government Code Section 65850.7, the Building Official shall implement an expedited, streamlined permitting process for electric vehicle charging stations, and adopt a checklist of all requirements with which electric vehicle charging stations shall comply with in order to be eligible for expedited review. The expedited, streamlined permitting process and checklist may refer to the recommendations contained in the most current version of the "Plug-In Electric Vehicle Infrastructure Permitting Checklist" of the "Zero-Emission Vehicles in California: Community Readiness Guidebook" as published by the Governor's Office of Planning and Research. The City's adopted checklist shall be reviewed, approved, and updated as necessary by the Building Official; and shall be published on the City's website.

(Ord. No. 2374, § 6, 10-3-17)

Exceptions & meaning →

Sec. 16-5.20.040: - Permit application processing

(a) Prior to submitting an application for processing, the applicant shall verify that the installation of an electric vehicle charging station will not have specific, adverse impact to public health and safety and building occupants. Verification by the applicant includes but is not limited to: electrical system capacity and loads; electrical system wiring, bonding and overcurrent protection; building infrastructure affected by charging station equipment and associated conduits; areas of charging station equipment and vehicle parking.

(b) A permit application that satisfies the information requirements in the City's checklist shall be deemed complete and be promptly processed. Upon confirmation by Building Division that the permit application and supporting documents meets the requirements of the City checklist, and is consistent with all applicable laws and health and safety standards, the Building Official, or designee shall, consistent with Government Code Section 65850.7, approve the application and issue all necessary permits. Such approval does not authorize an applicant to energize or utilize the electric vehicle charging station until approval is granted by the City. If the Building Official determines that the permit application is incomplete, a written correction notice shall be issued to the applicant, detailing all deficiencies in the application and any additional information required to be eligible for expedited permit issuance.

(c) Consistent with Government Code Section 65850.7, the Building Official shall allow for electronic submittal of permit applications covered by this Article and associated supporting documentations. In accepting such permit applications, the Building Official shall also accept electronic signatures on all forms, applications, and other documentation in lieu of a wet signature by any applicant.

(Ord. No. 2374, § 6, 10-3-17)

Exceptions & meaning →

Sec. 16-5.20.050: - Technical review

(a) It is the intent of this Article to encourage the installation of electric vehicle charging stations by removing obstacles to permitting for charging stations so long as the action does not supersede the Building Official's authority to address higher priority life-safety situations. If a permit application is deemed incomplete, a written correction notice detailing all deficiencies in the permit application and any additional information or documentation required to be eligible for expedited permit issuance shall be sent to the applicant for resubmission.

(b) In the technical review of a charging station, consistent with Government Code Section 65850.7, the Building Official shall not condition the approval for any electric vehicle charging station permit on the approval of such a system by an association, as that term is defined by Civil Code Section 4080.

(Ord. No. 2374, § 6, 10-3-17)

Exceptions & meaning →

Sec. 16-5.20.060: - Electric vehicle charging station installation requirements

(a) Electric vehicle charging station equipment shall meet the requirements of the California Electrical Code, the Society of Automotive Engineers, the National Electrical Manufacturers Association, and accredited testing laboratories such as Underwriters Laboratories, and rules of the Public Utilities Commission or a Municipal Electric Utility Company regarding safety and reliability.

(b) Installation of electric vehicle charging stations and associated wiring, bonding, disconnecting means and overcurrent protective devices shall meet the requirements of Article 625 and all applicable provisions of the California Electrical Code.

(c) Installation of electric vehicle charging stations shall be incorporated into the load calculations of all new or existing electrical services and shall meet the requirements of the California Electrical Code. Electric vehicle charging equipment shall be considered a continuous load.

(d) Anchorage of either floor-mounted or wall-mounted electric vehicle charging stations shall meet the requirements of the California Building or Residential Code as applicable per occupancy, and the provisions of the manufacturer's installation instructions. Mounting of charging stations shall not adversely affect building elements.

(Ord. No. 2374, § 6, 10-3-17)

Exceptions & meaning →

Get a plain-English answer with a citation back to this text.

Ask AI about this code
▸Contents — Victorville Municipal Code

GoCodebook provides public access, search, citation, multilingual explanation, and practical interpretation of legally adopted building regulations. It is not a substitute for the official ICC or California code publications.