6-12.401 - New Development, and Redevelopment Requirements and Criteria.¶
(a) In addition to all requirements listed in this chapter, any Responsible Party undertaking New Development, and Redevelopment projects within the City is required to comply with the requirements listed in:
(1) The City's Municipal Separate Storm Sewer System, National Pollutant Discharge Elimination System Permit No. CAS004002;
(2) Ventura County Technical Guidance Manual as amended; and
(3) Simi Valley Municipal Code and written policies related to Development and Redevelopment.
(b) A Responsible Party undertaking New Development and Redevelopment projects must implement all post construction controls that are conditioned in the final approved development plans.
(§ 1, 2, Ord. No. 1195, eff. August 2, 2012)
6-12.402 - Post Construction BMPs.¶
(a) A Responsible Party undertaking a Development project must comply with the required post construction BMPs.
(b) A Responsible Party whose Development project is subject to post construction BMPs must:
(1) Provide an operation and maintenance plan, and written verification of on-going maintenance provisions for the BMPs;
(2) Retain the operation and maintenance plan on-site; and
(3) Comply with requests for inspection for proper installation and operation of the BMPs in accordance with this chapter.
(c) A Responsible party will not be issued a final certificate of occupancy until the requirements of this section have been met.
(§ 1, 2, Ord. No. 1195, eff. August 2, 2012)