Section 511C — SPECIAL PROCEDURE
511C.8 Open Front Design Procedure.
San Francisco Building Inspection Commission Codes · 2022 edition · updated 2026-08-28 · San Francisco
A single-story building with an open front on one side and crosswalls parallel to the open front may be designed by the following procedure:
- Effective diaphragm span, Li, for use in Figure 5C-1 shall be determined in accordance with the following formula:
Li = 2[(Ww /Wd)L+L]x (5C-17)
- Diaphragm demand-capacity ratio shall be calculated as:
DCR = 0.332(Wd+Ww) / [(vuD)+Vcb] (5C-18)